In re Uciechowski
Appeal from a judgment of the Supreme Court (Williams, J.), entered September 22, 1994 in Sullivan County, which dismissed petitioner’s application, in a proceeding pursuant to CPLR article 78, to review a determination of the Zoning Board of Appeals of the Town of Fallsburg finding that respondent SYDA Foundation’s property was not in violation of the Town of Fallsburg Zoning Ordinance.
Petitioner is the owner of real property located in the Town of Fallsburg, Sullivan County, which is directly adjacent to property owned by respondent SYDA Foundation, a not-for-profit religious corporation. SYDA has constructed earthen berms along the perimeter of its property. Sometime prior to February 1992 SYDA apparently began adding to the height of these berms to the extent that they are now 14 feet high. By letter dated February 10, 1992 the Town Code Enforcement Officer (hereinafter CEO) informed SYDA that its berms exceeded the eight-foot height permitted for fences under the Town’s Zoning Ordinance and threatened enforcement action if the violation was not corrected. SYDA appealed the CEO’s deter-
SYDA then applied for an area variance from the height limitation and on May 21, 1992, after a public hearing, the ZBA granted a variance to SYDA allowing the construction of the berms to a height of 14 feet. In July 1992 petitioner commenced a CPLR article 78 proceeding challenging the ZBA’s grant of the variance; in September 1992 SYDA commenced a CPLR article 78 proceeding challenging the ZBA’s March 1992 determination that its berms were fences within the meaning of the Town Zoning Ordinance. In November 1992 Supreme Court granted petitioner’s application and annulled the May 1992 variance granted to SYDA because of administrative deficiencies, including the ZBA’s failure to issue findings of fact. In November 1993 Supreme Court granted SYDA’s application and annulled the ZBA’s March 1992 determination upon the same grounds.
Initially, respondents argue that the appeal should be deemed moot because of petitioner’s failure to seek injunctive relief prior to completion of the berms. Respondents are correct in asserting that petitioner’s delay in either seeking injunctive relief or commencing litigation may result in denial of the application because of laches (see, Ughetta v Barile,
However, we conclude that Supreme Court was correct in dismissing the petition on the merits. Initially, we note that this case comes before us in the context of a zoning matter and it is not for this Court to substitute its judgment for that of a zoning board (see, Matter of Brown v Turner,
We have considered each of petitioner’s remaining conten
Cardona, P. J., Mercure and White, JJ., concur. Ordered that the judgment is affirmed, without costs.
Notes
We reject petitioner’s contention that it was improper for Supreme Court to permit SYDA to commence its CPLR article 78 proceeding six months after the ZBA’s March 1992 determination. Petitioner was not a party to that proceeding in which he failed to intervene and from which no appeal was ever taken. Such an attempt by petitioner in the course of the instant proceeding constitutes an improper collateral attack on a court of coordinate jurisdiction (see, Bell v Town Bd.,