In Re the Palms at Water's Edge, L.P.
Memorandum Opinion on Debtor’s Objection to Claim of Thomas A. Lamb
Background
The debtor, The Palms at Waters Edge, L.P., filed an objection to the claim of Thomas A. Lamb, an architect. Doc. # 68 (Objection to Claim of Thomas A. Lamb); Doc. # 203 (Amended Objection to Claim of Thomas A. Lamb). Lamb claims that he is owed $266,875.00 for architectural work done for the debtor commissioned by the debtor’s agent, Wylie Eaton. The debtor objects to Lamb’s claim for three reasons. The debtor first claims there was no contract because no meeting of the minds existed as to who would pay Lamb and as to how much Lamb would be paid for the work. See Doc. # 203. The debtor also claims that Lamb’s claim is barred by the Statute of Frauds. Id. Finally, the debtor argues that Lamb is not entitled to an alternative claim of quantum meruit because the architectural designs provided no financial benefit to the debtor. Id.
Neither party contests that Texas law controls. Both parties are Texas residents, the property in question is located in Texas and the parties cite Texas cases in their pleadings. The court finds that Texas law controls.
Was there an oral contract between the parties?
The parties agree and the evidence supports a finding that there was no written contract between the parties. Lamb contends that there was an oral contract between the debtor and himself. See Doc. # 218 (Claimant’s Brief and Suggested Findings). The debtor responds that there was no meeting of the minds on what Lamb would be paid for his work or who would pay him.
Under Rule 3001(f) of the Federal Rules of Bankruptcy Procedure, a party correctly filing a proof of claim is deemed to have established a prima facie case.
In re Fidelity Holding Company, Ltd.,
An essential element of any valid contract is a meeting of the minds. When there is no written contract in evidence, and one party attests to a contractual agreement while the other vigorously denies any meeting of the minds, determining the existence of a contract is a question of fact under Texas law.
Runnells v. Firestone,
Here, the evidence shows that there was a meeting of the minds between Lamb and the debtor. Although Eaton denies the existence of an oral contract, conduct by both parties indicates otherwise. Eaton on behalf of the debtor sought out Lamb to produce architectural drawings for a condominium project to be built on Mustang Island. During meetings with Lamb, Eaton discussed what Lamb had to do and what Eaton wanted produced. Lamb set out to produce the architectural work within the constraints of those discussions. Eaton knew that Lamb was working on drawings for The Palms and never objected or complained about the architectural work being done for him. In Buxani, the court found that the parties had agreed to the terms of an oral contract, based on evidence that the parties allowed the work to begin and to continue without objection until the appellees billed them for the work. The facts in our case go even further than those in Buxani as Eaton used the work by Lamb to try to entice developers into financially backing the debtor to develop the land or to buy the land altogether.
With the exception of the price terms, the two parties agreed that Lamb would produce architectural work to be used to entice developers and build the project on Mustang Island. The absence of an express price term is not fatal to finding a meeting of the minds. Courts may supply a reasonable price term if all other elements of the contract are shown.
1
Burnside Air Conditioning & Heating, Inc. v. T.S. Young Corp.,
The debtor also contends that there was no meeting of the minds because the parties never agreed on who would pay for the work. Eaton testified to as much. The debtor also produced two contracts which it claims show that Lamb expected entities other than the debtor to pay for the architectural drawings.
A meeting of the minds can arise from the parties’ acts and conduct from which one party can reasonably draw the inference of a promise.
Buxani,
The debtor’s rebuttal evidence consisted of two contracts said to have been sent by Lamb to other entities in hopes of getting paid, one to Soledad Development, Inc. (and its president, Tom Harden) and one
Did the Statute of Frauds apply?
The debtor contends that even if there is a contract, it cannot be enforced because it is an oral contract “not to be performed within one year.” Thus, says the debtor, the contract violates the statute of frauds. 3
Texas law provides:
(a) A promise or agreement described in subsection (b) of this section is not enforceable unless the promise or agreement, or a memorandum of it, is
(1) in writing; and
(2) signed by the person to be charged with the promise or agreement or by someone lawfully authorized to sign for him.
(b) Subsection (a) of this section applies to: ...
... (6) an agreement which is not to be 'performed within one year from the date of making the agreement ...
Tex. Bus.
&
Com. Code Ann. § 26.01 (VeRnon 2002) (emphasis added). If an oral contract can be performed within one year under its terms, it is not within the statute of frauds.
Miller v. Riata Cadillac Co.,
The problem here is that it is unclear whether the contract could be performed in one year because, according to the testimony of both parties, the contract did not provide a time of performance for its obligations. Without more, the time of performance under this contract could be considered indefinite.
Cunningham and Dental Leasing v. Healthco, Inc.,
There is evidence in this record that enables the court to supply this term of the contract. Lamb testified that the oral agreement was like his standard written contracts. (Plaintiffs Exhibit # 1). He explained that this deal was no different from his normal written contracts except that it was not written. Thus, his written contracts are probative of the time-of-performance determination. Lamb testified that in his standard contracts, his work includes a schematic-design phase, a design-development phase, a construction-document phase, a bidding- and-negotiation phase, and a construction phase. 4 Lamb then broke down the normal time each phase would take were he to work on each phase continuously. He stated that the schematic-design phase and design-document phase would take five to six months to complete, the construction-document phase would take two to three months to complete and the bidding-and-negotiation phase would take a few weeks to complete. It is thus safe to say that the design-and-development phase of Lamb’s contracts — including this oral contract— would be expected to take eight to ten months. 5 If this were the end of the analysis, there would be no question that the performance term would fall inside the one-year limit and outside the statute of frauds. However, there is the problem of the construction phase of the contract. The parties disagreed over whether the construction phase was an essential portion of the contract such that it should be counted as well.
The court concludes that the construction phase was an essential portion of the contract whose performance must be considered for statute of frauds purposes. The construction phase of the contract involves the architect visiting the construction site to oversee the construction of the building. Lamb testified that this would occur only once or twice a week and was
The circumstances, substance of the work and situation of the parties shows that a reasonable time to complete the construction of this project would take no less than four months. Lamb knew that the debtor did not have the money or financial backing to develop this project when he received this assignment. Eaton told Lamb that he had to get a developer to finance him or buy the property in order to build this building. There was also never any clear evidence that it was possible to build a condominium such as this in just four months. That schedule could be met only if this project were “fast-tracked”- — an impossibility, considering the uncertainty of financing. Based on the foregoing evidence, the court concludes that neither party contemplated that this contract could be performed in anything less than a year. Under even the most optimistic conditions, the construction of the condominium would take more than four months to complete. Even though we cannot say how long it would take to perform this oral contract, the court can safely say it would take more than a year. Because the contract falls outside the one-year time limit, the statute of frauds applies, making the contract unenforceable.
Was Lamb entitled to recover under Quantum Meruit?
Lamb contends, as an alternative basis for recovery, that he is entitled to be paid for his services in quantum meruit. 8 The debtor disputes this claim, arguing that Lamb never offered evidence of acceptance, use and enjoyment by the debtor of the work of Lamb.
1. Valuable services were rendered or materials were furnished;
2. The services were rendered for the recipient sought to be charged;
3. The services and materials were accepted by the person sought to be charged, used and enjoyed by him; and
4. The services and materials were accepted under such circumstances as reasonably notified the defendant/reeipient that the plaintiff, in performing the services, expected to be paid by the recipient.
Vortt Exploration,
The court finds that Lamb did supply the debtor with valuable services that were accepted, used and enjoyed by the debtor. Acceptance of services may consist of work performed for the recipient with the recipient’s knowledge and consent.
Smith v. Pulliam, Inc.,
Case law supports this finding of quantum meruit. Even though the work was never used to construct a building, an architect can recover on a quantum meruit claim for the reasonable value of services that were approved and accepted even though the proposed structure was never erected.
Waller County v. Freelove,
The measure of recovery in a quantum meruit action is the reasonable value of services rendered and materials furnished.
Thomason v. Freberg,
The court allows the claim of Thomas Lamb in the amount of $266,875.00. ' Lamb is directed to submit form of order consistent with this opinion.
Notes
. The court has found that there was a contract for services. The only elements of existence of the contract that the debtor disputes is the meeting of the minds on price and who was to pay Lamb. The court addresses the reasonable price term later in this decision.
. The debtor claims that there are other contracts Lamb sent to other entities. However, none of these contracts were produced at the hearing.
. The statute of frauds is an affirmative defense.
Impossible Electronic Techniques, Inc. v. Wackenhut Protective Systems, Inc.,
. Lamb's standard written contract in Plaintiff's Exhibit # 1 also reflects these phases.
. The design-and-development phase includes the schematic-design phase, the design-document phase, the construction-document phase and the bidding-and-negotiation phase. The only phase of the work that is excluded is the construction phase.
. Lamb does not present any evidence that shows how this oral contract would be any different than the standard written contract. Had he shown that this situation was unique in some way, then the court would have not considered the standard contract.
. This is assuming it takes eight months to complete the design-and-development portion of the contract. The construction of the condominium would have to be accomplished during the four months after the design phase to fall within the one-year limit. It is not necessary to consider the two months because if the condominium cannot be completed in four months, then it certainly cannot be completed in two. This approach requires the court to assume that the design-and-development phase take no more than eight months. If that phase took ten months, then the construction phase would have to be shortened to two months to withstand the statute of frauds.
.The debtor produced the testimony by Eaton to the effect that the architectural work was never used because the building was never built. The debtor uses this evidence to rebut the validity of the claim. In that case, whichever party that has the burden of proof outside of bankruptcy of proving the claim has the burden in bankruptcy.
See Raleigh,