204 A.D. 332 | N.Y. App. Div. | 1923
The record on this appeal is not in very satisfactory shape. There was no formal submission of the matter to arbitration as provided in the former Code of Civil Procedure (§ 2366), made applicable by the Arbitration Law (§8), but the parties, owner and contractor, respectively, appointed the arbitrators who in turn selected the umpire, and the arbitration proceeded based upon the provisions of article XII of the contract. The plain meaning of that instrument is that in case of disagreement between the owner and contractor in relation to matters of payment the dispute should be referred to arbitrators. The matters of payment referred to are naturally the payments due from the owner to the contractor, and that was the matter which was submitted to the arbitrators. The contractor had commenced an action against the owner to recover damages for breach of the contract, and while the pleadings in that action are not printed, it is evident from the opening statement of the counsel for the contractor to the arbitrators, “ The complaint, of course, as Mr. Porter suggested, is a statement of the claim,” that the entire demand of the contractor was submitted. If the owner had any defense or counterclaim against the contractor for defective work or for overcharge under the provision for ten per cent profit, this was the time and place to present it. The suggestion that the arbitrators should take up a part only of the dispute and leave the parties to a lawsuit over the balance, is opposed to the obvious intention of the parties evidenced in the contract and to the very principle of arbitration. It was to avoid litigation that arbitration was agreed upon. It is true as claimed by appellant that arbitrators must not go beyond the limit of the questions submitted to them, and that parties must not be deprived of their constitutional rights to redress in the courts in the absence of agreement to forego such rights (Dodds v. Hakes, 114 N. Y. 260; Matter of General Silk Importing Co., Inc., 200 App. Div. 786; affd., 234 N. Y. 513), but in the case at bar the parties agreed to submit the dispute as to the amount due to arbitration. The fact that certain subjects were specifically mentioned as matters to be submitted does not justify the conclusion that all others were intended to be excluded. The contract should receive a reasonable construction with a view to accomplish the purpose obviously intended by the parties. (Locke v. Filley, 14 Hun, 139.) Such an agreement for arbitration is to be given effect, in the most liberal sense, as accomplishing a complete and final settlement of all existing controversies. (Matter of
The order appealed from should be modified in so far as it disallows the award of the arbitrators of the sum of $4,012.50 credited to the owner appellant in paragraph 12th of the award, and the sum of $1,163.92 in paragraph 13th of said award, which sums aggregating $5,176.42 should be allowed to the owner appellant as awarded by the arbitrators. The item $2,100 allowed to the owner appellant in paragraph 14th of the award should be disallowed and the order as
Present —Kelly, P. J., Rich, Jay cox, Manning and Kapper, JJ.
Order and judgment modified in accordance with opinion, and as so'modified unanimously affirmed, without costs. Settle order upon notice.