50 A.D.2d 226 | N.Y. App. Div. | 1975
The controversies at bar arise out of the construction of certain additions to and alterations of the facilities of The Mount Sinai Hospital of Hartford, Connecticut. The Mount Sinai Hospital (hereinafter "the Hospital”) entered into an agreement with The Perkins & Will Partnership (hereinafter "the Architect”) on or about July 28, 1965 for certain architectural and other services in connection with this construction. Similarly, on or about October 29, 1968, the Hospital entered into an agreement with Walter Kidde Constructors, Inc. (hereinafter "the General Contractor”) whereby the latter agreed to construct the additions and alterations to the Hospital’s facilities. The Architect utilized as consulting engineers on this project the firms of Syska and Hennessy (hereinafter "the Mechanical Engineers”) and Garfinkel, Marenberg & Associates (hereinafter "the Structural Engineers”). In March, 1972, the General Contractor commenced an arbitration proceeding against the Hospital under the arbitration provision of their agreement. In that proceeding the General Contractor asserts a claim for delay, extras and changes in the sum of $9,645,787. By demand dated April 20, 1973, the Hospital initiated an arbitration proceeding against the Architect, seeking to recover "[s]o much of damages claimed by [the General Contractor], which were the fault of the Architects and their Engineers”. Subsequently, the Hospital’s arbitration proceeding against the Architect, asserting a claim over, was consolidated into the prior arbitration proceeding between the General Contractor and the Hospital. While the determination consolidating these arbitration proceedings was subject to appellate review at the behest of the Architect, the Hospital and the General Contractor engaged in litigating discovery matters. Following appellate imprimatur of the court-directed consolidation, the litigation engaged in by the Hospital and the General Contractor resulted in a court order (March 7, 1975), directing the parties to proceed forthwith to arbitration.
Following this directive and before the selection of any arbitrators, the Architect served a demand for arbitration dated April 24, 1975 on both the Mechanical Engineers and the Structural Engineers. The demand stated as the nature of
Scrutiny of the arbitration provision in the agreements between the Architect and the engineers mandates the conclusion that the Architect’s demand for arbitration against the engineers should have been vacated as no dispute is delineated therein which falls within that portion of the arbitration provision which contains the broad arbitration clause. Patently, the dispute between the Architect and the engineers involves indemnification and is so specified in the demand. This dispute is the subject of the exception to arbitration set forth in paragraph "15” of the agreements between the Archi
The Structural Engineers (a partnership) also contend that the service of the notice of participation was improper as to them in that they dissolved on April 6, 1970, some five years prior to such service. "A partnership is not terminated upon dissolution, but continues until winding up of partnership affairs is completed. After dissolution, a partnership is considered as maintaining a limited existence for the purpose of making good any outstanding engagements, taking and settling accounts, collecting partnership property and the means
The Mechanical Engineers (Syska and Hennessy) similarly were put on notice of the arbitration proceeding involving the Hospital and the Architect and their attention was specifically drawn to the vouching-in provision of their agreement with the Architect. This was effected by the rider to the demand for arbitration. To reiterate, the dispute delineated in the demand for arbitration is solely that involving the Hospital and the Architect. Further, it appears that the Mechanical Engineers knowingly aided the Architect in connection with the latter’s preparation of its defense in the consolidated arbitration involving the Hospital since the inception of the Hospital’s demand against the Architect. Under these circumstances, the rider to the demand served by the Architect on the Mechanical Engineers constitutes, on a pragmatic basis, notice of opportunity to participate in the prior consolidated arbitration proceeding. Such activity on the part of the Mechanical Engineers is in their own best interest in that assuming the Architect defeated the claim of the Hospital, there would no longer be a predicate for a claim over by the Architect against the Mechanical Engineers.
However, the Mechanical Engineers assert that they cooperated with the Architect solély on the basis of the latter’s agreement to relieve the former of possible liability from being vouched into the arbitration or of future arbitration with the Architect. No writing is presented by the engineers evidencing such understanding. The consultant’s agreement between the Architect and the Mechanical Engineers provides in pertinent part: "9. Either party may terminate this agreement upon seven (7) days’ written notice to the other, provided that such termination shall not affect the applicability of any provision of this agreement to any Work Authorization Form which has theretofore been accepted by the Consultant * * * 16 * * * the Consultant may not assign, subcontract or transfer his interest in this agreement or a Work Authorization Form subject to this agreement or his duties thereunder without the written consent of the Architect” (emphasis supplied). In light of section 15-301 of the General Obligations Law, it was incumbent upon the Mechanical Engineers to produce a writing evidencing the alleged understanding be
Parenthetically it is noted that the indemnification aspects of the consultant’s agreements set forth in paragraphs "12” and "15” thereof, do not run afoul of section 5-324 of the General Obligations Law. The indemnification illegalized by said section of the General Obligations Law is one by the owners, contractors, subcontractors or suppliers for the architect’s and the engineers’ negligence and is not addressed to indemnification between the architect and the engineers. Secondly, the proscribed indemnification relates to damages for bodily injury or property damage, whereas in the case at bar, the General Contractor is suing for delay claims, extras and changes which do not appear to be within the ambit of those categories.
Accordingly, the judgment (denominated an order) of the Supreme Court, New York County (Postel, J.), entered July 16, 1975, should be modified, on the law so as: (1) to vacate the demand for arbitration served on the Structural and Mechanical Engineers insofar as arbitration is concerned; (2) to hold that the demand for arbitration with annexed rider served on the Mechanical Engineers in effect constituted notice of opportunity to participate in the arbitration pending against the Architect and as such was timely and valid; and (3) to declare that the notice of opportunity, by letter dated April 30, 1975, to participate in the arbitration pending against the Architect was timely, valid and properly served, and, as so modified, the judgment should be affirmed, without costs and disbursements.
Similarly, the judgment of the Supreme Court, New York County (Postel, J.), entered July 17, 1975, should be modified, on the law, so as to vacate the demand for arbitration and to deny the declaratory relief requested by the petitioner (Garfinkel, Marenberg & Associates) in view of the grant of that relief in the proceeding brought by the Architect as above indicated, and, as so modified, the judgment should be affirmed, without costs and disbursements.
Murphy, J. P., Capozzoli, Lane and Nunez, JJ., concur.
Judgment (denominated an order), Supreme Court, New York County, entered July 16, 1975, unanimously modified, on the law, so as: (1) to vacate the demand for arbitration served
Judgment, Supreme Court, New York County, entered July 17, 1975, unanimously modified, on the law, so as to vacate the demand for arbitration and to deny the declaratory relief requested by the petitioner in view of the grant of that relief in the proceeding brought by the Architect as above indicated, and, as so modified, the judgment is affirmed, without costs and without disbursements.