In re the Arbitration between Hirsch Construction Corp. & Cooper
Lead Opinion
OPINION OF THE COURT
This appeal is from the vacatur of an arbitration award on the ground that the underlying dispute was not subject to arbitration because the agreement to arbitrate was void as part of a "homе improvement” contract entered into before the requisite home improvement contractor’s license had been obtained. Since the lack of a license was never submitted to the arbitrators, the belated proifer of such evidence should have been rejected on the well-settled rule that newly discovered evidence does not constitute a ground for challenging аn arbitration award. Nor should the court have gone beyond the face of the award on a fact-finding mission and analysis and substituted its own view of the merits in determining that the award was against public policy.
In a written agreement dated June 23, 1988, Hirsch Construction Corp. (HCC), a small construction company, contracted with respondents, Brian and Karen Cooper, to perform the construction work in the renovation of their townhouse at 123 East 91st Street in Manhattan. The contract, which called for HCC to be paid the cost of its work up to a guaranteed maximum of $478,000, inclusive of a contractor’s fee of $70,000, plus the agreed-upon price of any change orders, contained a clause providing for the arbitration of "[a]ll claims, disputes and other matters in question” between HCC and respondents аrising out of or relating to the contract documents or the breach thereof.
In June 1989 HCC served on respondents a demand for arbitration of all contract disputes between the parties, seеk
The parties thereafter moved and cross-moved respectively to confirm and vacate the award; respondents sought vaсatur solely on the ground that the arbitrators committed " 'misconduct’ ” by refusing their request to recall Henry Jessup, respondents’ architect, as a witness. On November 1, 1990, four months after the issuance of the award, respondents’ attorney wrote to the court advising that he had just learned that HCC did not have a home improvement contractor’s license at the time the June 23, 1988 contract was signed. He argued thаt, since Administrative Code of the City of New York § 20-387 requires home improvement contractors to be licensed prior to soliciting, obtaining or performing a home improvement contract, the agrеement violated the public policy against enforcing illegal contracts and the award should therefore be vacated. HCC’s principals submitted affidavits setting forth the details of its home improvement contractor’s license application, including the fact that HCC was not approved for such license until August 30, 1988. The court granted confirmation, rejecting the misconduct claim and, with respеct to the licensing issue, following the rule that " '[Njewly discovered evidence is not a competent ground for vacating an arbitrator’s award” (quoting, Levine v Klein,
In a May 1, 1991 "interim order,” the court granted reargument, holding that from the face of the award the issue of licensing was "so inextricably intertwined as necessarily to entail a potential facial conflict” with the public policy with respect thereto. Pursuant to the court’s invitation, HCC submitted additional material, which showed that the arbitrators had evidence before them from which they could have concluded that the home improvement licensing provisions did not apply to the transactions underlying the award. In particular, evidence was presented showing that in early December 1988, more than three months after HCC obtained its license,
The court vаcated the award, holding that "given that the arbitration was pursuant to an arbitration provision in a void contract, the arbitration must fall”. It also found that HCC had independent claims that survive the lack of license defense and could be pursued in a plenary action. This appeal followed. We reverse and confirm the award.
There is a well-settled rule prohibiting challenges to arbitral awаrds on the basis of newly discovered evidence. (Matter of Central Gen. Hosp. v Hanover Ins. Co.,
Thus, since the lack of a license was newly discovered evidence which was not before the arbitrators, the award cannot be challenged on this basis and the public policy argument that home improvement contractors must be licensed, which relies on this evidence, must fail. This is not to say, as does оur concurring colleague, that we are favoring one public policy, i.e., upholding arbitration awards, over another, that home improvement contractors be licensed. Suffice to sаy, these two distinct public policies are not in competition in this case for the simple reason that the licensure issue was not before the arbitrators.
A case more illustrative than this of the wisdоm of the rule prohibiting judicial vacatur of arbitration awards on the basis of newly discovered evidence could hardly be imagined. The IAS court’s acceptance of new evidence led to further litigation as to the applicability of the home improvement contractor licensing provision to the underlying transaction, whether
Nor, contrary to respondents’ argument, do we discern any exception to the rule barring newly discovered evidence challenges to arbitral awards where such evidence bears on a public policy defense. Indeed, no judicial support for such an exception has been cited. While a challenge to the arbitrability of an issue оn public policy grounds may be made for the first time on a motion to vacate the award (Hirsch v Hirsch,
Moreover, as we recently held in a case involving the same contractor, the courts will not vacate an arbitration on public policy grounds where, as here, there "is nothing on the face of the award to indicate that it violates the public policy against recovery by unlicensed home improvement contractors.” (Matter of Hirsch Constr. Corp. [Anderson],
Even if there was evidence before the arbitrators that HCC did not have a license at the time the parties entered into the original contrаct, HCC would not necessarily be barred from recovery, since it alleges that its claims relate to work performed after it obtained a license. (See, Todisco v Econopouly,
Accordingly, the order/judgment (one papеr) of the Supreme Court, New York County (Diane A. Lebedeff, J.), entered
Concurrence Opinion
I disagree with the majority’s conclusion that the public policy in favor of upholding arbitration awards whenever possible takes precedеnce over the public policy that a home improvement contractor must be licensed. Moreover, "a challenge to the arbitrability of an issue on public policy grounds may be made either on an application for a stay of arbitration * * * or * * * on a motion to vacate the award” (Hirsch v Hirsch,
Rosenberger, Ellerin and Kassal, JJ., concur with Sullivan, J. P.; Milonas, J., concurs in a separate opinion.
Order and judgment (one paper) of the Supreme Court, New York County, entered November 27, 1991, reversed, on the law, without costs or disbursements, and petitioner’s motion to confirm the award granted and respondents’ cross motion to vacate the award denied.