In re the Acquisition of Real Property by Central Hudson Gas & Electric Corp.
Appeal from an order of the Supreme Court (Kavanagh, J.), entered May 21, 1999 in Ulster County, which, in a proceeding pursuant to EDPL article 4, denied respondents’ motion to dismiss the petition.
In May 1991, petitioner applied to the Public Service Commission (hereinafter PSC), pursuant to Public Service Law article VII, for a certificate of environmental compatibility and public need (hereinafter the certificate) authorizing it to reconstruct, replace and upgrade two electric transmission lines that serve Ulster County. In 1994, after approximately 200 information requests, 15 conferences and eight days of
Petitioner sent notification of the PSC decision and the comment process for the EMCP to potentially affected landowners, including respondents. In July 1996, the PSC approved petitioner’s EMCP, with portions of electric lines to be constructed on respondents’ property. In approving the EMCP, the PSC lifted the ban on petitioner’s commencement of condemnation proceedings under the EDPL. Respondents and other landowners thereafter brought a CPLR article 78 proceeding challenging the PSC’s certificate under Public Service Law § 128 which was dismissed as untimely (see, Matter of Powerline Coalition v New York State Pub. Serv. Commn.,
Upon respondents’ refusal of petitioner’s offer to purchase a permanent easement over the affected portion of their property, petitioner commenced this proceeding in February 1999 pursuant to EDPL article 4. Respondents moved to dismiss the application as time barred by EDPL 206 and 401 since more than three years had elapsed since the PSC’s May 23, 1995 order issuing the certificate. Petitioner contended that by the terms of the order, the Public Service Law article VII proceeding was not complete until the EMCP was approved in July 1996. Supreme Court agreed, prompting this appeal.
Pursuant to EDPL 401 (A), petitioner, as the condemnor, is permitted to commence proceedings to acquire property necessary for a proposed public project within three years after the
To the extent that respondents seek to challenge the PSC’s authority, as expressed in the certificate, to postpone the commencement of the limitations period for EDPL proceedings, we find the challenge time barred (see, Matter of Powerline Coalition v New York State Pub. Serv. Commn.,
Cardona, P. J., Spain, Mugglin and Lahtinen, JJ., concur. Ordered that the order is affirmed, without costs.