¶ 1. This appeal stems from the latest litigation involving developer Stowe Highlands and its Resort Planned Unit Development (PUD) in the Town of Stowe. The Stowe Development Review Board (DRB) denied Stowe Highlands’ application to amend the PUD by subdividing and then merging certain lots, including one designated for a hotel. The DRB concluded that the amendment amounted to a change in the permit conditions and that such amendment was not warranted because Stowe Highlands had not demonstrated an unanticipated change in factual circumstances beyond its control. Stowe Highlands appealed this denial to the Environmental Division of the Superior Court, which reversed, concluding that the application required no permit condition change and that denial on that basis was therefore unfounded. One of the PUD lot owners,
¶ 2. The basic facts are undisputed. Applicant is the permittee of a 236-acre Resort PUD. Issues have arisen since the Resort PUD was initially granted, and this Court has entertained several appeals in the matter. See, e.g.,
In re Stowe Highlands Resort PUD to PRD Application,
¶ 3. To understand the immediate question, some background is necessary. The original PUD envisioned a 100-unit hotel on a 34-acre portion of the Resort PUD identified as Parcel 1. In 1993, the PUD was amended and reduced Parcel 1 to 17 acres with a 21-unit hotel. The site plan submitted at that time and the subdivision plat for that portion of the Resort PUD depict an inn on Parcel 1. Parcel 1 has yet to be developed. Currently lots 21-23 are permitted for three single-family residential lots on 7 acres.
¶ 4. In 2010, Stowe Highlands applied to amend the PUD. Stowe Highlands proposed to subdivide Parcel 1 into Lot 1A and Lot IB. Lot IB would be merged with Lots 21, 22, and 23 and then subdivided into 11 new residential lots. Lot 1A, consisting of approximately 12 acres, would continue to be reserved as a future site for the Resort PUD’s 21-unit hotel. 2
¶ 5. The DRB denied the application to amend the subdivision plan. The DRB construed the previous permit as including a condition that Lot 1 would be developed with only a hotel or resort. The DRB found that, by seeking to reduce the land underlying the hotel component of the Resort PUD and to build other structures on the remainder, Stowe Highlands effectively proposed a permit change. The DRB applied the Stowe Club test to evaluate whether to grant such a charige. Under this test, the Board examines whether a permit modification is justified by: changes in factual or regulatory circumstances beyond the permittee’s control, changes in the project’s construction or operation not reasonably foreseeable at the time the permit was issued, or changes in technology.
In re Stowe Club Highlands,
¶ 6. Stowe Highlands appealed to the Environmental Division. 24 V.S.A. § 4471. The court conducted an on-the-record review. The court concluded that the evidence supported neither the DRB’s determination that a Resort PUD permit condition limited Parcel 1 to exclusive development as a hotel, nor its finding that the proposed amendment reduced that hotel element. The court
explained that while the proposal sought to reduce the acreage for the hotel lot so that additional residences could be built, this did not equate to reducing the footprint of the 21-unit hotel as planned. Further, the court concluded that the evidence did not demonstrate
¶ 7. Lot owner Detora and the Town reiterate on appeal 3 that a condition of the Resort PUD approval requires Parcel 1 to be developed solely as a hotel. In support, they point to the recorded plat and site plan, which depict a hotel — and no other structure — on Parcel 1. They also maintain, as below, that there is substantial evidence to support the DRB’s findings that the Stowe Highlands 2010 amendment application proposed to reduce the hotel component of the Resort PUD.
¶ 8. The parties have proceeded with this appeal as if the Environmental Division’s order was a final judgment. In fact, the court’s decision was interlocutory in nature because the court remanded the case back to the DRB to conduct a merits review of the application and to consider whether to impose phasing or engage in conditional use review. See
In re Cliffside Leasing Co.,
¶ 9. Because the Environmental Division conducted an on-the-record appeal, we apply the same standard of review.
In re Stowe Highlands Resort PUD to PRD Application,
¶ 10. Here, the DRB found there was “a condition of a previous approval that the 17-acre Lot 1 will be developed with only a hotel/resort.” The DRB also found that Stowe Highlands’ proposal required a change of this condition since it diminished the planned hotel site and would build something other than the approved hotel on Parcel 1. The Environmental Division disagreed, noting that “nothing in the
¶ 11. The Town and lot owner contend that the evidence supports the DRB findings. Despite no explicit limitation on Parcel 1 development, they posit that the condition arose based on several filings submitted by Stowe Highlands or its predecessor that identified that a hotel would be built on Parcel 1. In addition to the application for conditional use approval of the 21-unit hotel which stated that an inn would be built on Parcel i, the Town and lot owner point to a Parcel 1 site plan depicting the inn, and a recorded subdivision plat showing the hotel on Parcel 1. According to the Town and lot owner, once these plans were approved, and the plat and site plans recorded, their depiction of the hotel only became a permit condition.
¶ 12. Certainly, the requirement that a hotel or inn be built on Parcel 1 is a condition of the permit. This Court previously held that a resort must be part of a Resort PUD.
In re 232511 Investments, Ltd.,
¶ 13. Further, the court was correct that the evidence did not support the DRB’s finding that the hotel called for in the previously approved permit would somehow be reduced via the later application to split its underlying parcel. The application proposed to decrease the lot size for the hotel, but reserved Parcel 1A for the same sized 21-unit hotel as previously permitted. Because the proposed amendment did not require a change in a permit condition, the Stowe Club test was not applicable, and the Environmental Division’s reversal and remand to the DRB for further review of the application was proper.
Affirmed.
Notes
In a prior appeal involving this permit, we concluded that “a resort is a minimum legal requirement of a Resort PUD,” and therefore Stowe Highlands could not alter its plans to entirely eliminate the hotel component and construct solely single-family homes.
In re 232511 Investments,
When the Town filed its notice of appeal, it captioned it as a “cross appeal.” This label is incorrect. Given that the Town’s position is aligned with that of lot owner in seeking to reverse the decision of the Environmental Division, the Town is an appellant in this appeal just like lot owner.
Although the applicable Resort PUD standards provide a mechanism for reserving land as open space, the plat did not so designate the area around the hotel.
