¶ 1. Verizon Wireless appeals the Environmental Court’s decision to remand this case to the zoning board of adjustment (ZBA). The Environmental Court asked the ZBA to consider whether St. Mary’s Church needs a conditional use permit before changing its parking arrangements to accommodate Verizon Wireless’s small-scale telecommunications facility. We reverse the Environmental Court’s decision and dismiss the case.
¶ 2. This case arises out of a proposed project to mount wireless cell phone antennas in the towers of St. Mary Star of the Sea Catholic Church in Newport, Vermont. From the beginning, this plan met with resistance from certain neighbors. The neighbors lost the first case, in which they challenged the zoning permit Verizon Wireless received to implement the project. In re Curtis,
¶ 3. Verizon Wireless contends that the neighbors are precluded by res judicata from bringing this claim because it should have been raised in their first appeal of the zoning permit. The preclusion question, Verizon Wireless argues, is a jurisdictional one, and therefore this Court should review it de novo. Torni of Charlotte v. Richmond,
¶ 4. The neighbors argue that this is merely a question of ordinance interpretation, and the Court should not disturb the Environmental Court’s interpretation unless it was clearly erroneous, arbitrary, or capricious. In re Nott,
¶ 5. The history of this case has been thoroughly explained both in our recent decision, Curtis,
¶ 6. While the appeal was pending, the neighbors raised two other concerns in separate dockets, one before the Environmental Board, and the other in a new docket before the Environmental Court. The first was an Act 250 concern, which this Court has since resolved. In re Ochs,
¶ 7. The Environmental Court consolidated both the site plan review and the conditional use dockets in its Decision and Order on Motions to Remand. The Environmental Court classified parking at St. Mary’s as “non-conforming.” Section 501 distinguishes structures that do not comply with the bylaws from uses that do not comply, and §§ 402 and 403 specify different permitting procedures for the two different types of nonconformity. Nowhere in the decision did the court specify whether parking at St. Mary’s was a nonconforming use or a noncomplying structure. Instead, the Environmental Court remanded the case to the zoning board of adjustment to determine whether a conditional use permit was necessary. This appeal followed.
¶ 8. Verizon Wireless contends that the Environmental Court should not have considered the question at all because the neighbors failed to raise it in their first appeal, and thus res judicata applies. To apply res judicata there must be a final decision on the merits, and the neighbors must have had the opportunity to fully litigate the claim they now raise. In this case, the Environmental Court’s final judgment approving the zoning permit and our ruling finding no site plan review necessary both constitute final decisions on the merits of the permit. Thus, to determine whether res judicata applies to
¶ 9. Courts have long recognized that “‘[p]ublic policy dictates that there be an end of litigation; that those who have contested an issue shall be bound by the result of the contest, and that matters once tried shall be considered forever settled as between the parties.’” Federated Dep’t Stores, Inc. v. Moitie,
¶ 10. This is a bylaw compliance claim. It deals with whether the alterations to the church’s structure inquire a conditional use permit. Section 605 of the bylaw requires the administrative officer to consider whether conditional use approval is necessary before issuing a zoning permit. The time to raise this issue was as soon as the allegedly nonconforming alterations were apparent. All the alterations at issue here should have been evident on October 1, 2003, when Verizon proposed the new position for the equipment shelter at the neighbors’ request. Because the neighbors asked for the relocation, they had actual notice of the change. At this late stage, a site plan review has already been conducted and a zoning permit has already been granted and appealed. The neighbors lost their chance to raise the conditional use issue when they decided not to raise it in the first appeal.
¶ 11. Once we conclude that the cause of action is the same, we must examine whether the conflict arises between the same parties. Bidgood,
¶ 12. For these reasons, the Environmental Court’s decision remanding the project for a conditional use permit was in error. Since no site plan review has been found necessary, and the zoning permit has already been granted and appealed, the appropriate course of action is for this Court to reverse the Environmental Court’s decision and dismiss the case.
The Environmental Court’s decision is reversed, and the case is dismissed.
