¶ 1. This is an appeal from an Environmental Court decision granting site plan, conditional use, subdivision, and Act 250 permits for the development of a large retail Wal-Mart store in the Town of St. Albans. Appellants are comprised of a number of interested individuals and groups opposed to the project. They contend the trial court erred in; (1) approving site plan and conditional use permits despite the alleged conflict of interest of several members of the Town’s development review board; (2) finding that the subdivision is compatible with adjacent land uses; and (3) concluding that the developer may reapply for an Act 250 permit despite an earlier denial. We affirm.
¶ 2. This is the latest skirmish in a long-running dispute over plans to develop a
¶ 3. In December 2005, some eight years after our decision and twelve years after the initial application, the original developer’s successor-in-interest, appellee JLD Properties, filed a new Act 250 permit application to build a larger Wal-Mart store (about 147,000 square feet) on the same site. At roughly the same time, JLD applied to the Town’s development review board (DRB) for site plan, conditional use, and subdivision permits for the project. The DRB granted the zoning permits in April 2008. The District Commission approved the Act 250 application the following month. All of the permits were subsequently appealed to the Environmеntal Court and consolidated for review.
¶ 4. The Environmental Court issued a decision in March 2009, disposing of several pretrial motions. The court rejected appellants’ claim that the doctrine of res judicata barred the new Act 250 application. The court ruled, instead, that the successive-application doctrine controlled, but deferred deciding the matter until disputed factual issues were resolved at trial. The court also addressed appellants’ claim that conflicts of interest among several DRB members required that the case be remanded for a new hearing. The court found that appellants had “good reasons to be concerned that the DRB chair did not review the Wal-Mart application objectively.” Nevertheless, it concluded that, “egregious as [his] statements were,” the proper course was to “complete [the court’s] de novo review of the pending applications.” The court also rejected appellants’ claim that five other DRB members were biased “simply because they [had] voted in favor of an eаrlier application.”
¶ 5. An evidentiary hearing was conducted over several days in June 2009. Following the. submission of additional briefing, the court issued its decision in January 2010, approving the project with conditions. In response to appellants’ motion to alter, the court issued a revised
I.
¶ 6. We begin with the conflict-of-interest claim. It is beyond dispute that “[a] fair trial before an impartial decisionmaker is a basic requirement of due process, applicable to administrative agencies as well as to the courts.”
Sec’y, Agency of Natural Res. v. Upper Valley Reg’l Landfill Corp.,
¶ 7. It is equally settled that “[a]ll questions” regarding a decisionmaker’s impartiality do not necessarily “involve [issues of] constitutional validity.”
Tumey v. Ohio,
¶ 8. Although the disqualification standards are thus generous, and the decisionmaker enjoys a presumption of impartiality,
Ball v. Melsur Corp.,
¶ 9. As noted, only in “the most extreme of cases” is disqualification for bias constitutionally required,
Aetna Life Ins. Co. v. Lavoie,
¶ 10. The separate question of a remedy remains. The trial court concluded that a de novo hearing would cure any harm resulting from the DRB chair’s pаrticipation, and we agree. Although the United States Supreme Court has recognized that there may be circumstances where de novo review is inadequate to cure a due process violation, it has generally been in cases of systemic or “structural” error undermining public confidence in the procedural framework as a whole. See
Johnson v. United States,
¶ 11. The high court employed similar reasoning in
Vasquez v. Hillery,
holding that systematic racial discrimination in the selection of the grand jury “undermines the structural integrity of the criminal tribunal itself’ and thus represented a fundamental flaw
that could not be “purged” by a subsequent fair trial and conviction.
¶ 12. In contrast to errors of a “structural” nature, due process violations resulting from an individual decisionmaker’s personal bias have often been held to be subject to cure on de novo review. For example, in
Kelly v. Board of Education of Mоnticello Independent School District,
the court conceded that the appellant’s prospect of receiving a fair hearing before a school board that had prejudged his case was “more illusory than real.”
¶ 13. We thus find ample support for the trial court’s conclusion that any due process concerns arising from the participation of the DRB chair in the permit proceedings were effectively cured by the subsequent trial de novo in the Environmental Court. This does not, of course, mitigate the egregious lapse of judgment that gave rise to the due prоcess claim in the first instance or excuse such disreputable conduct in the future. Nor can review in the Environmental Court absolve questionable conduct in the ultimate court of public opinion. That is an entirely separate matter, however, from the one we consider here.
¶ 14. As for appellants’ corollary claim concerning the other DRB members, it is sufficient to recall that mere participation in an earlier proceeding does not, without more, demonstrate a disqualifying bias.
Liteky,
II.
¶ 15. We turn to appellants’ assertion that the trial court erred in analyzing the Act 250 permit application under the successive-application doctrine. Citing the statute and rule governing reconsideration of Act 250 applications, appellants maintain that the Legislature “has provided that reconsideration is the
sole
remedy for reapplying for an Act 250 permit that has been denied.” (Emphasis added.) The
¶ 16. The trial court here thus correctly concluded that the new Act 250 application was not automatically barred by the failure to apply for reconsideration, but rather was governed by the successive-application doctrine. This conclusion was sound. As the court accurately observed, the doctrine’s ability to strike the proper balance between finality and flexibility in municipal zoning decisions applies with equal force to the planning and environmental concerns underlying Act 250. See
In re Dunkin Donuts S.P. Approval,
¶ 17. Assuming the doctrine applies, appellants alternatively contend the evidence fails to support the court’s finding thаt circumstances had changed sufficiently in the last twelve years to
permit the new Act 250 application. In assessing the court’s finding that the developer demonstrated the requisite change of circumstances to support its new application, our review is limited. The trial court
¶ 18. In reaching its decision here, the trial court relied principally on engineering and economic analyses showing that much of the potential secondary commercial growth that concerned the Board in 1993 had already occurred during the intervening years. Included in “this conglomeration of commercial developments within a mile-and-a-half radius of the proposed project site,” the court found, were fifty-one new commercial enterprises, including fast-food restaurants, bank offices, automobile sales and service centers, and large retailers such as supermarkets and home supply centers. This extensive commercial development was facilitated, in turn, by the City’s specific designation of the area as a “growth center” and extension of sewer lines. The court also found that the Board’s original concern with the project’s potential effect on other large discount stores in the area, specifically an Ames, Woolworths, and Ben Franklin store, was obviated by the fact that all three had since closed, so that — in fact — there was now evidence of need for a local discount store such as Wal-Mart. As thus summarized by the trial court, the evidence showed that “commercial growth is now encouraged for this area and that the proposed Wal-Mart will fill a void that now exists in the local discount retail market.” Additionally, the court found that the Board’s original concerns about the project’s impact on population growth and its effect on educational services had largely evaporated because of declining school enrollment over the years, and that other potentially adverse economic impacts had been minimized or negated by the developer’s pledge of financial investments and other benefits to the local municipalities. Accordingly, the trial court found “a significant change in the circumstances that led to the denial of the prior Wal-Mart development proposal” sufficient to permit the new Act 250 application.
¶ 19. Appellants contend the trial court relied on flawed or insufficient evidence, or ignored conflicting evidence, in reaching this conclusion. In this respect, they claim that there was no evidence showing how the loss of three large discount stores had affected commercial growth in the area, thus undermining the trial court’s finding that the fifty-one new stores represented substantial commercial growth and negated the Board’s original concern about secondary growth. The record evidence disclosed, however, that even with the loss of the three major discount stores the total square footage of stores in the area had more than doubled since 1993, thus amply supporting the court’s finding of significant new commercial expansion. Appellants also fault the trial court for failing to address the difference in square footage between the original and current Wal-Mart store proposals, but the record shows all of the expert analyses on which the court relied took account of the expanded proposal. Apрellants additionally criticize the developer’s secondary-growth analysis for failing to consider the project’s impact on the development or expansion of shopping centers. The developer’s expert economist specifically testified, however, that his secondary-growth study included the potential expansion or addition of shopping malls
¶ 20. Appellants further allege flaws in the econоmic model used by JLD’s expert to demonstrate little or no secondary-growth associated with other Wal-Mart stores in Vermont and the region. As noted, however, the evidence showed — and the trial court found — that “significant expansion in commercial development” in the area surrounding the St. Albans site had already occurred such that secondary growth was no longer a concern; thus, any evidence concerning secondary growth specifically related to Wal-Marts in other areas was largely superfluous. In essence, the triаl court here found the substantial evidence adduced by JLD relating to secondary growth and its associated social and economic impacts to be more compelling and persuasive than the countervailing evidence adduced by appellants. Under the applicable standard of review, therefore, we have no basis to disturb the court’s findings, or reverse its conclusion that signifi cant changes over the past twelve to fifteen years validated the new Act 250 application.
III.
¶ 21. Lastly, appellants contend thе trial court erred in finding that the project was “compatible with adjacent uses (especially agricultural)” under the Town’s subdivision requirements. Town of St. Albans Zoning Bylaws and Subdivision Regulations §220(3) (2006). In its initial decision, the trial court found that “[n]o adjoining property hosts agricultural uses,” observing in this regard that the nearest agricultural operation is the Hudak farm, which it described as located in a “separate zoning district in the Town of Swanton” and physically separated from the project by Stevens Brook, a 55-acre buffer along Stevens Brook that the developer had pledged to preserve, and many adjacent commercial uses. In response to appellants’ motion to alter, the court revised its decision to acknowledge that a portion of the Hudak farm is, in fact, located within the Town of St. Albans and the zoning district of the proposed Wal-Mart site and that Stevens Brook does not separate the project from a portion of the Hudak farm. The court further acknowledged that it had mistakenly referred to “adjoining” rather than “adjacent” property at sevеral points in its original decision, and that — as appellants argued — adjacent could have a slightly broader meaning than adjoining, encompassing properties that are not only contiguous but also nearby or close but not necessarily touching. See Webster’s II New Riverside University Dictionary 78 (1984) (defining adjacent as “close to” or “nearby”);
Vermont Marble Co. v. Eastman,
¶ 22. In reaffirming its decision, however, the court here underscored its earlier undisputed findings that numerous uses separate the Hudak farm operations west of Route 7 from the project site, including a town highway known as Jewett Avenue, Stevens Brook, a woodland, and a host of commercial properties and uses, including “the commercial developments known as Cobb Auto, Senesac Auto Body, Champlain Commons store complex, Progressive Auto Sales, and a storage and distribution facility.” The trial court thus concluded that even substituting “adjacent” for “adjoining” the Hudak farm was not аn adjacent property requiring a specific compatability analysis under the ordinance.
¶ 23. Appellants claim that the court erred in concluding that the terms “adjacent”
Affirmed.
Notes
This section provides, in pertinent part, that the District Commission must consider “the growth in population experienced by the town and region” and whether the proposed development “would significantly affect their existing and potential financial capacity to reasonably accommodate” the expected growth. 10 V.S.A. § 6086(a)(9)(A).
Appellants also suggest that the Environmental Board order denying the original Wal-Mart application in this case provided that the developer’s sole recourse was to apply for reconsideration. On the contrary, the order merely stated that “to be eligible for the procedure under 10 V.S.A. § 6087(c) and Rule 31(B), an applicant must correct the deficiencies in the prior denial.” Nothing in the order or in the other Board decisions cited by appellants suggest that reconsideration is the exclusive means of reapplying for an Act 250 permit.
