176 Wis. 452 | Wis. | 1922
The appellant owns and maintains a dam for the purpose of generating electric power, which dam extends across the Wisconsin river about a mile north of the village of Prairie du Sac. The construction of this dam was commenced in 1910. In 1913 it raised the water five feet; in 1914 about twenty-five feet; in 1915 the water was raised another three feet; in the latter part of 1915 or 1916 it was raised another foot, and in the winter of 1918, or the spring of 1919, it was raised to its present height, so that the total height is now about thirty-three feet.
Petitioners’ lands are located in a valley which drains into the Wisconsin river, the general direction of which is north from the river and about a half mile from the pond created by the dam. The petitioners, who claim damage to their lands by reason of the construction of the dam, instituted these proceedings in the nature of condemnation to have the damage appraised. The petition alleges that
“Although the waters of the mill-pond do not border directly upon the lands of your petitioners, the raising of' the water in the mill-pond has raised the water level and has interfered with the natural surface and underground drainage of petitioners’ lands, and the water having been set back thereon, petitioners’ lands, as a result, have become wet and soggy and unfit for use. That as a result of raising the water level in the vicinity of said mill-pond near the lands of petitioners, the underground drainage is impaired and petitioners’ lands . . . have been rendered wet and soggy and unfit for use, whereas prior to the con*454 struction of said dam and in the ordinary course of nature •said lands were naturally drained and were capable of, and were used for, agricultural purposes.”
The evidence shows that up to the year 1915 petitioners’ lands were dry and suitable for agricultural purposes; that during the period .from 1915 down to the time of the hearing the lands were wet and soggy ^rendering them entirely unfit for agricultural purposes; that this was the condition of the lands during that period is not a matter of dispute. The controversy is as to the reason for the wet condition of the lands.
On the part of the petitioners it is argued that as the lands were dry and tillable prior to the construction of the darn, and their wet and untillable condition has arisen since its construction, the raising of the water by the dam, thus preventing the underground drainage down through the valley to the river, is the cause of their present condition. The defendant introduced evidence to show that below petitioners’ lands an impervious bank of clay, more than thirty feet in depth, extends clear across the valley, which bank is so impervious as to shut off from petitioners’ lands the water from the dam; that this clay bank 'extended below the water level before the dam was put in, and that as the drainage from the upper part of the valley could not percolate through this clay bank it necessarily went under it, and as this was below the water level prior to the raising of the dam, the raising of the dam had no effect upon the underground drainage of the upper part of the valley. Drainage experts testified that because of this fact the ground water curve, instead of being a gradual rise and extending back probably several hundred feet, as would be the case with sand, extends back but a short distance and rises abruptly to the surface. The defendant also -claims that the wet condition of petitioners’ lands is due to abnormal rainfall and not to an interference caused by its dam with the normal drainage from this valley.
“Plaintiffs’ case, as to this feature of it, was based entirely upon theory, speculation, and conjecture. It was their misfortune that definite testimony could not be procured. Recoveries .cannot be allowed that have no' other basis than mere speculation or conjecture. . . . The testimony in this regard is so speculative and conjectural that we are not able to see how, if a verdict had been rendered for the plaintiffs, it should have had any substantial basis to rest upon.”
The conclusion of the trial court, therefore, that the condition of petitioners’ lands was the result of the construction of the dam, cannot be sustained. It occurs to us, however, that if the lands should remain in their wet condition during a continued period of normal rainfall, the deduction might be justified that their wetness was due to the construction and maintenance of the dam. We feel that should this appear 'at any time prior to the running of the statute of limitations the petitioners should be allowed to institute new proceedings for the appraisement of their damages, and we will therefore reverse the order appealed from, with instructions to dismiss the petition, but without prejudice to the right of petitioners to re-institute proceedings at any time within the bar of the statute of limitations.
By the Court. — So ordered.