In re CVPS/Verizon Act 250 Land Use Permit Numbers 7C1252 and 7C0677-2
2009 VT 71 | 980 A.2d 256
No. 07-441
Supreme Court of Vermont
August 6, 2009
Present: Reiber, C.J., Dooley, Skoglund and Burgess, JJ., and Allen, C.J. (Ret.), Specially Assigned
Reversed and remanded.
William H. Sorrell, Attorney General, and Paul R. Brierre, Assistant Attorney General, Montpelier, for Appellee.
William B. Piper and Joslyn L. Wilschek of Primmer Piper Eggleston & Cramer PC, Montpelier, for Amicus Curiae Thirteen of Vermont‘s Municipal Electric Departments.
Victoria J. Brown of Primmer Piper Eggleston & Cramer PC, Burlington, for Amicus Curiae Vermont Electric Cooperative, Inc.
Harriet Ann King of King & King, Waitsfield, for Amicus Curiae Green Mountain Power Corporation.
¶ 1. Skoglund, J. In this appeal, we consider the scope of Act 250 jurisdiction over utility line projects. Central Vermont Public Service Corporation (CVPS) sought an Act 250 permit to extend one of its electrical distribution lines. It appeals from the Environmental Court‘s determination that it must not only obtain a permit pursuant to Act 250 Rule 70,
¶ 2. The record indicates the following. In October 2006, CVPS applied for an Act 250 permit to construct a 2500-foot extension of an electrical distribution line in Danville, Vermont, most of which would be located underground.2 CVPS obtained easements for its line corridor, one of which traversed land subject to an existing Act 250 permit held by a third party (“Barry permit“). The Barry permit approved the creation of three building sites, but it did not authorize further development of the subject property.
¶ 4. In December 2006, the district commission issued two permits — a new Act 250 permit to CVPS and an amended Barry permit that named CVPS as a co-permittee. Both permits stated that the utility line project was subject to Act 250 jurisdiction for two independent reasons: (1) the project met the criteria set forth in Rule 70, and (2) the project constituted a “material change” to the Barry permit under Rule 2(C)(6).
¶ 5. CVPS appealed both permits to the Environmental Court, and the appeals were consolidated. CVPS argued that the district commission erred by finding that a “material change” to an existing development could be an independent trigger for jurisdiction over its utility line project. CVPS also argued that the district commission erred in naming it as a co-permittee in the Barry permit. CVPS moved for summary judgment, and the Land Use Panel of the Natural Resources Board opposed its request. In an August 2007 decision, the court granted summary judgment to the land use panel.
¶ 6. The court first considered the terms of the Barry permit, which addressed the future residential development of a 289-acre parcel of land. The Barry permit had approved three future building sites as identified on a site development plan, but it had not approved the actual subdivision or the construction of these residences. Instead, the permit required an amendment before actual construction or subdivision of any parcels associated with the building sites.
¶ 8. Even if the Barry permit had not expressly required an amendment, the court continued, a permit amendment would nonetheless be required under Rule 34(A), if the extension of the utility line constituted a material or substantial change to the previously-permitted project. In so concluding, the court rejected CVPS‘s assertion that Rule 70 provided a separate regulatory framework for utility projects, to the exclusion of Rule 34(A). It reasoned that Rule 70 simply provided procedures for the processing of applications for new transmission lines, and if the Natural Resources Board had intended to exempt such projects from “amendment jurisdiction” under Rule 34(A), it could have done so. Nonetheless, the court found that it could not determine from the facts provided if the project constituted a material or substantial change to the Barry permit, and thus, summary judgment was not appropriate on this ground. Because the Barry permit itself required an amendment, however, the court found that this conclusion did not change the result.
¶ 10. On appeal, CVPS argues that the court‘s decision regarding amendment jurisdiction was both unnecessary and unsupported by the rules. We review the Environmental Court‘s summary judgment ruling using the same standard as the Environmental Court. In re Hildebrand, 2007 VT 5, ¶ 9, 181 Vt. 568, 917 A.2d 478 (mem.). Summary judgment is appropriate where there is no genuine issue of material fact and any party is entitled to judgment as a matter of law. Id.;
I. Mootness
¶ 11. Before turning to the merits, we briefly respond to the issue raised by the dissent. The dissent concludes, sua sponte, that this appeal should be dismissed because CVPS no longer has a legal stake in the outcome of this case and there is no meaningful relief that can be afforded CVPS by this Court and, thus, CVPS is seeking an advisory opinion. The dissent misunderstands the issues presented on appeal.
¶ 12. As recounted above, the Environmental Court concluded that, based on the language of the Barry permit, CVPS was subject to the terms of the permit and, consequently, that it must obtain an amendment to the Barry permit before installing its line. It further found that CVPS would be required to seek a permit amendment pursuant to Rule 34 if the extension of the utility line constituted a material or substantial change to the Barry permitted project. These obligations were in addition to the requirement that CVPS obtain an Act 250 permit for its line under Rule 70. These are the decisions appealed to this Court. CVPS argues that Rule 70 provides the sole basis for Act 250 jurisdiction over utility line projects and that it should not be required to seek an amendment for a permit to which it was never a party and under rules that do not control here. CVPS retains a legal stake in the outcome of these proceedings, and this Court can offer it meaningful relief. See In re Constitutionality of House Bill 88, 115 Vt. 524, 529, 64 A.2d 169, 172 (1949) (Vermont Supreme Court is empowered “to determine actual controversies arising between adverse litigants, duly instituted in courts of proper jurisdiction” (quotation omitted)); see also J.L. v. Miller, 174 Vt. 288, 292, 817 A.2d 1, 4 (2002) (“The presence of an actual controversy turns on whether the plaintiff is suffering the threat of actual injury to a protected legal interest, or is merely
¶ 13. Rather than resolve this controversy, the dissent suggests that we strike CVPS‘s name from the Barry permit and vacate the entire Environmental Court decision as “unnecessary dicta.” Post, ¶¶ 33-34. It would seem obvious that striking CVPS‘s name from the Barry permit alone is meaningful relief. Moreover, the Environmental Court‘s entire decision below can hardly be characterized as dicta. Unlike the cases cited by the dissent, the question of whether CVPS was required to be named as a co-permittee on the Barry permit was clearly “in dispute” and it formed “a necessary part of the final disposition of the case to which it pertains.” Wood v. Wood, 135 Vt. 119, 121, 370 A.2d 191, 192 (1977).5 Indeed, it was the sole issue decided by the Environmental Court. The controversy is live and CVPS is entitled to have this Court decide if it must be named as a co-permittee on the Barry permit under the terms of that permit and whether Rule 34(A) applies to it.
II. Act 250 Jurisdiction Over Utility Line Projects
¶ 14. We thus turn to the merits. In reviewing the rules governing Act 250, we apply familiar principles of construction, including a presumption that the drafters of the rules intended “the plain ordinary meaning of the language used.” Comm. to Save the Bishop‘s House, Inc. v. Med. Ctr. Hosp. of Vt., Inc., 137 Vt. 142, 153, 400 A.2d 1015, 1021 (1979);
¶ 15. Generally speaking, Act 250 prohibits parties from subdividing land or commencing “development” without a permit.
¶ 16. Initially, those utility projects that did not require a certificate of public good were governed by “Appendix A,” titled “Power and Communication Lines and Facilities: Permit Requirements.” The stated purpose of Appendix A was to “establish rules and procedures for applications for a permit [under Act 250] by public and private utilities.” Pursuant to these rules, an Act 250 permit was required to
construct, relocate, reconstruct, or extend any transmission facility for any purpose whether above, below, or on ground if the construction of improvements for the right-of-way involves more than one acre . . . if within a
municipality not having permanent zoning and subdivision ordinances or more than ten acres . . . if a municipally owned utility.
Appendix A, Rule A-3; see also Rule A-3(c) (identifying specific exemptions from permit requirement). These rules described the necessary components of a permit application, and set forth requirements concerning the installation of lines.
¶ 17. Effective January 2001, the Environmental Board promulgated a revised set of rules, which eliminated Appendix A, and instead expanded the definition of “development” to include the following:
The construction of improvements for electrical distribution or communication lines and related facilities that are located on rights-of-way, or easements, of more than one acre of land owned or controlled by a person or persons in a municipality without both permanent zoning and subdivisions bylaws. The phrase “construction of improvements” shall include construction, relocation, extension, and reconstruction. . . . In a municipality with both permanent zoning and subdivision bylaws, this jurisdiction will apply if the rights-of-ways or easements involve more than ten acres of land. For the construction of improvements by a municipally-owned utility, regardless of the existence of zoning or subdivision bylaws in the area where improvements will be constructed, this jurisdiction will apply only if the rights-of-way[] or easements involve more than ten acres of land.
Rule 2(A)(12) (2001). The rule described how to calculate acreage for purposes of utility projects and also identified specific exemptions from this jurisdiction. See Rule 2(A)(12)(a), (b) (2001); see also Rule 2(F)(3) (defining “involved land” for purposes of electrical distribution or communication lines and related facilities to include only the acreage identified and calculated as set forth in Rule 2(A)(12)); 2(T) (2001) (defining term “electrical lines, communication lines, and related facilities“). Rule 70, titled “Utility Line Installations and Applications,” described the requirements for installation and the process for permit applications to construct, relocate, reconstruct, or extend any electrical distribution line or related facility. Rule 70 (2001).
(B) Utility Line Jurisdiction. The construction of improvements for electrical distribution, natural gas distribution, or communication lines and related facilities that are located on rights-of-way, or easements, of more than one acre of land owned or controlled by a person or persons in a municipality without both permanent zoning and subdivision bylaws. The phrase “construction of improvements” shall include construction, relocation, extension, and reconstruction. . . . In a municipality with both permanent zoning and subdivision bylaws, this jurisdiction will apply if the rights-of-way[] or easements involve more than ten acres of land. For the construction of improvements by a municipally-owned utility, regardless of the existence of zoning or subdivision bylaws in the area where improvements will be constructed, this jurisdiction will apply only if the rights-of-way[] or easements involve more than ten acres of land.
As in prior rules, the acreage calculation methodology is set forth, and Rule 70(B)(1) states that jurisdiction will apply if a project exceeds the acreage thresholds set forth above. The rule also defines relevant terms and sets forth specific exemptions from jurisdiction under Rule 70, including cases where an electrical distribution line is within a development that has obtained a permit, provided that the line was included in the application for the permit. See Rule 70(B)(1)(a)-(c), 70(B)(2)(a). Additionally, the rule sets forth the necessary components of a permit application for the construction, relocation, reconstruction, or extension of any electrical distribution or communication line or related facility. Rule 70(D).
¶ 19. In addition to Rule 70, two recently enacted statutory provisions also touch on the scope of Act 250 jurisdiction over
¶ 20. In contrast to these utility-specific provisions is Rule 34, titled “New Permit Applications and Permit Amendments: Substantial and Material Change.”8 Rule 34(A) provides that an amendment is required for any “material change” to a permitted development or subdivision, or any administrative change in the terms and conditions of a land use permit.9 As noted above, a “material change” is defined as “any change to a permitted development or subdivision which has a significant impact on any finding, conclusion, term or condition of the project‘s permit and
¶ 21. As set forth above, the Environmental Court concluded that Rule 70 did not provide the exclusive means of obtaining Act 250 jurisdiction over utility line projects. Instead, it found that CVPS must be added as a co-permittee to an existing Act 250 permit because the terms of the Barry permit required an amendment prior to any further development of the subject property. The court also stated that Act 250 jurisdiction would attach to the utility line project under Rule 34 if the project constituted a “material or substantial change” to the Barry permit. The court erred.
¶ 22. It is evident that Rule 70, in conjunction with the statutory provisions discussed above, was intended to define the scope of Act 250 jurisdiction over utility line projects. The rules are specific and comprehensive, and they plainly limit Act 250 jurisdiction to those utility line projects that meet certain threshold requirements, i.e., projects that involve the construction of improvements on easements or rights-of-way of more than one acre in municipalities without both permanent zoning and subdivision bylaws, or more than ten acres in municipalities with both permanent zoning and subdivision bylaws. The rule does not contemplate that, despite these specific jurisdictional thresholds, utilities would also be required to obtain amendments to any and all existing Act 250 permits held by third parties wherever their projects would constitute a “material change” to the terms of those permits. This approach would be inconsistent with the spirit and purpose of Rule 70, and it would vastly expand the scope of Act 250 jurisdiction over utilities. It would further expose utilities as co-permittees to liabilities and burdens that could arise, even if
¶ 23. This is not the regulatory approach set forth in the rules, and we reject the notion that the specific conditions contained in the Barry permit can serve to establish Act 250 jurisdiction over a utility in the first instance. While certain utility projects may not be subject to Act 250 review, despite the fact that they arguably constitute a “material change” to existing projects, this is precisely what Rule 70 requires.
¶ 24. We note, moreover, that the Legislature has declared that any unanticipated changes to permitted utility line projects will not be considered “material changes” to such projects but rather will be considered as “new construction.”
¶ 25. There is no reason to require CVPS to obtain two Act 250 permits for the same project and conduct the same environmental evaluation twice. See Bishop‘s House, 137 Vt. at 153, 400 A.2d at 1021 (explaining that the “obvious purpose” of the Act 250 permit requirement is “to subject all ‘development’ to scrutiny at the district environmental commission level to assure that any adverse impacts on the values described in
¶ 26. Our conclusion is consistent with the plain language of Rule 70 and with a narrow construction of the jurisdictional reach of Act 250. As we have explained, Act 250 does “not purport to reach all land use changes within the state, nor to impose the substantial administrative and financial burdens of the Act“; instead, the Legislature intended to reach only those land use changes “where values of state concern are implicated through large scale changes in land utilization.” In re Agency of Admin., 141 Vt. 68, 76, 444 A.2d 1349, 1352 (1982) (citing Bishop‘s House, 137 Vt. at 151, 400 A.2d at 1020)); see also In re Spencer, 152 Vt. 330, 334, 566 A.2d 959, 962 (1989) (noting that “although the purposes of Act 250 are broad, its application is not without limitation“). Rule 70 identifies when that threshold is met for utility companies.10
¶ 27. We are not persuaded otherwise by In re Eustance Act 250 Jurisdictional Opinion, 2009 VT 16, 185 Vt. 447, 970 A.2d 1285, cited by the dissent. The dissent misconstrues our holding in Eustance. In that case, we considered whether certain landowners were required to obtain an amendment to an Act 250 permit that governed their own property in order to make improvements to their property. The case did not involve the question of whether the Legislature intended utility companies to be bound by the terms of existing permits held by third parties.11
Reversed.
¶ 29. Dooley, J., dissenting. The question that the majority answers is moot, and we should dismiss the appeal rather than answer it. The majority decision is an improper advisory opinion. Moreover, the majority has largely ignored the main ground for the Environmental Court decision, and rendered its opinion based on its construction of the alternative rationale of the court. In fact, the primary ground of the Environmental Court was correct, as determined in the recent decision of this Court in In re Eustance Act 250 Jurisdictional Opinion, 2009 VT 16, 185 Vt. 447,
¶ 30. I start with why the majority decision is an improper advisory opinion. CVPS applied for and obtained an Act 250 permit to run an electric line through property because the line was long enough to create Act 250 jurisdiction under Rule 70. Because the line went through land already subject to an Act 250 permit, the district environmental coordinator and the district commission ruled that there were two grounds for Act 250 jurisdiction — the length of the line under Rule 70, and the requirement to amend the preexisting permit covering part of the land over which the line would run. CVPS objects and wants us to decide that the second ground for Act 250 jurisdiction is wrong, even as it acknowledges that the first ground is right. Thus, this is a dispute over reasoning, not result. CVPS has an Act 250 permit, and its land use regulatory requirements will not be affected one iota by the result of this appeal. What CVPS, joined by all the electric utilities in the state, wants is an advisory opinion that it can use in future disputes. We do not have the power to give such an opinion.
¶ 31. CVPS has acknowledged in this Court that it has an Act 250 permit, that it does not contest the requirement for such a permit or its terms, and that no regulatory responsibility imposed upon it is at stake in this appeal. Thus, from its inception this appeal sought nothing more than an advisory opinion on the validity of the second and alternative basis of jurisdiction found by the district commission — “advisory” because a decision that is not absolutely necessary to resolve a legal issue is nothing more than that, simply “solicited legal advice in anticipation of issues.” Wood v. Wood, 135 Vt. 119, 120, 370 A.2d 191, 192 (1977) (reaffirming the limits on this Court‘s jurisdiction, “[t]he most basic [of which] is the prohibition against advisory opinions“). The majority candidly admits that Rule 70 provides jurisdiction over the line extension project. See ante, ¶ 10. Because of that acknowledgement, this is now an appeal with no consequences at stake. CVPS‘s land use regulatory requirements will not be affected by the decision of this Court. This appeal is truly moot.
¶ 32. It is one of the fundamental principles of our judicial system that we do not issue advisory opinions. See In re Constitutionality of House Bill 88, 115 Vt. 524, 529, 64 A.2d 169,
¶ 33. We have faced the situation in this case in the past and recognized that it would be beyond our power to render the advisory opinion sought. For example, in Chittenden South Education Ass‘n v. Hinesburg School District, 147 Vt. 286, 514 A.2d 1065 (1986), the cross-appellant teachers’ union sought review of a part of the rationale of the Vermont Labor Relations Board decision under which it had prevailed. Noting that “[o]ur determination would not entitle the Association to any further relief, nor would it change the relief afforded,” we held that we would not “pass on the merits of this issue because it requires this Court to render an advisory opinion prohibited by this State‘s Constitution.” Id. at 294, 514 A.2d at 1071. We did so even though we recognized “the importance of the question posed,” apparently the reason for the majority‘s advisory opinion in this case. Id. Our power is not created because the challenged alternative rationale for Act 250 jurisdiction may have future consequences. See Baker v. Town of Goshen, 169 Vt. 145, 152, 730 A.2d 592, 597 (1999). In any event, if the Court wants to be sure that there are no consequences from the Environmental Court‘s alternative grounds for Act 250 jurisdiction, it could vacate the decision as unnecessary dicta as discussed below. See In re Pilgrim P‘ship, 153 Vt. 594, 598, 572 A.2d 909, 911 (1990) (striking permit condition where it was “not necessary” to the decision and mere “dicta“).
¶ 34. In short, under established precedents of this Court, we do not have the power to issue a 100% dicta, advisory opinion in this case. The majority‘s response to this barrier to its jurisdiction is inexplicable to me. It says that “this Court can offer . . . meaningful relief,” but fails to specify how. Ante, ¶ 12. All of its discussion after that generalization is about who is named as a
¶ 35. The majority is caught up in the fact that CVPS was required to have two permits. The record demonstrates, however, that the second permit adds nothing to CVPS‘s regulatory responsibilities. The second permit is actually an amendment to the Barry permit “issued for record-keeping to document that the tract is also subject to . . . [the CVPS permit], for a utility line project.” CVPS had a valid objection to the amendment because it suggested that CVPS was a co-applicant with respect to the whole Barry permit development project. The Environmental Court solved the objection by making CVPS a co-applicant only with respect to the utility line easement, exactly its status under the Rule 70 permit. Thus, since CVPS is an applicant with respect to the utility line, there is no consequence to it being designated a co-applicant with respect to the same utility line. The majority has blown an amendment done for record-keeping purposes out of proportion.
¶ 36. If the majority believes that the Barry permit will “impose potentially unrelated permit conditions upon CVPS,” ante, ¶ 25, the remedy should be to strike the Barry permit amendment, leaving CVPS subject to the same responsibilities under its Rule 70 permit. The majority states that such an action would be “meaningful relief.” Ante, ¶ 13. Since the amendment was done for record-keeping purposes and not to impose additional risks or obligations on CVPS, its deletion is of little consequence to any party. The remedy is not to render an advisory opinion on an issue that is of no consequence to CVPS, except as an advance determination for some future dispute.
¶ 37. Unfortunately, the advisory nature of the majority opinion continues into its discussion of the merits. The Environmental Court gave two grounds for its decision; the first does provide Act 250 jurisdiction, the latter might provide such jurisdiction. The primary ground for the decision is that the Barry permit by its explicit terms requires an amendment to enable CVPS to run a line through the Barry property. The alternative ground was tentative: Act 250 amendment jurisdiction under Rule 34 might also require an amendment of the Barry permit if CVPS‘s project constituted a material or substantial change, a determination the court could not make on the sparse record. Thus, the court
¶ 38. This is a second reason why the appeal of the amendment jurisdiction issue is moot. Having found jurisdiction because of the permit condition, the Environmental Court‘s decision on amendment jurisdiction was wholly unnecessary and of no effect. In the recent case of Eustance, 2009 VT 16, the Environmental Court was also confronted with the choice of basing Act 250 jurisdiction on a preexisting permit condition or on amendment jurisdiction under Rule 34. In that case, unlike this one, the Environmental Court understood that the first ground rendered it unnecessary to reach the second, a position we clearly understood and endorsed in observing that it “would be inappropriate for us to reach” the issue of amendment jurisdiction since it was rendered “moot.” Id. ¶ 24. The majority is ignoring that determination of Eustance here. If the issue of Rule 34 jurisdiction was moot in Eustance, as we held, it is moot here for the same reason.
¶ 39. Although I believe that we should not address the merits of the issue raised by CVPS and resolved in the majority opinion, I also believe that the majority‘s decision is wrong on the merits. It barely mentions the primary rationale for the Environmental Court decision, which is based on
¶ 41. We are left then with the wholly unsupported proposition that the commission cannot adopt a condition that will affect utility activity or enforce a neutral condition, like that involved here, against a utility line extension project. Nothing in Act 250 or Rule 70(b) implementing Act 250 gives utilities a blanket exemption from valid permit conditions. The majority cites nothing to support such a result. It is no answer that the preexisting permit did not bind CVPS because CVPS assumed the obligation of the permit by purchasing its easement over the Barrys’ property.13 Whatever may be the rule when the utility activity does not violate an explicit permit condition, the subject of virtually all of
¶ 42. Indeed, we reached precisely this conclusion, in analogous circumstances, in our very recent decision in Eustance. The question there was whether subsequent agricultural development within a previously permitted subdivision was exempt from Act 250 jurisdiction under the farming exemption of
¶ 43. I do not see how it is possible to harmonize our holding in Eustance with the majority holding here.14 If a prior permit condition controlled there, irrespective of whether the farming exemption applied, it must control here irrespective of the preemptive scope of Rule 70. There is no evidence of legislative intent to override existing permit conditions in either case. Indeed, if we were to judge this question entirely on legislative intent, the
¶ 44. While our holding in Eustance obviously speaks for itself, I cannot ignore the majority‘s statement that we “did not expressly hold . . . that ‘a prior permit condition controlled . . . irrespective of whether the farming exemption applied.‘” Ante, ¶ 27 n.11. We expressly held exactly that. We observed that the Eustances had conceded the trial court‘s “conclusion that the express language of the permit condition required them to obtain a permit amendment irrespective of whether their construction activity would have been exempt as related to farming,” and we stated plainly that this was a reasonable conclusion “which we would affirm even if there were no concession.” 2009 VT 16, ¶ 22 (emphasis added). If this was not a clear holding that the permit condition controlled irrespective of the farming exemption, I do not know what is. The majority also asserts that Eustance is somehow distinguishable because there the original permit holder sought approval whereas here it is CVPS, not the Barrys. This argument overlooks the fact that CVPS is the grantee of an easement across the property, and the Barry permit expressly provides that it “shall run with the land and the land uses herein permitted, and will be binding upon and enforceable against the Permittees and all assigns and successors in interest.”
¶ 45. Finally, I emphasize that there are very real and substantial consequences from the majority decision, even though there are no consequences for the line extension in this case. The facts of this case do, however, provide a good background to understand those consequences. The Barry permit covers 289 acres, of which the majority is a mapped deer yard. Because of this significant attribute of the land, the first version of the permit prohibited any development or subdivision until the effect on the deer yard was resolved. Condition 3 of the permit stated:
Permittees agree that no further development of the tract shall be allowed unless it can be demonstrated that such development will not further impact on the potential of the tract to continue to serve as a protected deer yard or unless it is demonstrated that the tract itself is no longer appropriate, necessary or functional as a deer yard. In any event, no further development of the parcel shall be allowed without the concurrence of the Department of Fish and Wildlife, Agency of Natural Resources and the District Environmental Commission.
The site also contains a Class 2 wetland area, prime agricultural soils and a brook. With respect to the brook, the amended permit that covers the CVPS line also imposes special requirements. The Act 250 application shows that the line is placed underground to minimize the effect on wildlife habitat and that special precautions were taken to minimize impacts on the stream or wetlands and protect the agricultural lands.
¶ 46. This background is important because what CVPS seeks from the appeal, and has received from the majority decision, is the right for line extensions less than 2200 feet long15 to go anywhere CVPS wants, and to be constructed in any way CVPS wants, irrespective of the impact on wildlife habitat, wetlands, streams or agricultural soils. That is, CVPS seeks the right not to protect the deer yard, and to not protect the stream and the wetland, even in a circumstance where the district commission has found that the need for protection is so great that it imposed a special protection condition even before a development proposal was submitted.16 Of course, we do not know how CVPS will use its new authority now that it is free from regulation and does not have to comply with Act 250 conditions applicable to any other land developer, but its seeking of this advisory opinion, with amicus briefs from the other utilities in Vermont, does not suggest that we are dealing only with a matter of principle.
¶ 48. In closing, I reiterate the numerous reasons for which I cannot join the majority decision. First and foremost, this case is moot; we should dismiss the appeal. When it unnecessarily reaches the merits, the majority decision fails to address the actual rationale of the trial court, reversing the trial court‘s decision without responding to its analysis. The trial court‘s analysis was correct, as shown by a very recent decision of this Court, Eustance, that supports the trial court‘s analysis and is dead against the majority‘s decision. The majority‘s attempt to distinguish Eustance is clearly wrong; there is no distinction. I dissent.
¶ 49. Allen, C.J. (Ret.), dissenting. While I concur with Part I of the majority that this case is not moot, I dissent because Eustance is controlling and cannot be distinguished.
Notes
In situations in which the construction of improvements for any combination of electrical distribution and communications lines and subsidiary facilities, standing alone, constitutes a development subject to the jurisdiction of the board or district commission under this chapter, subsequent construction of improvements for any combination of electrical distribution and communications lines and subsidiary facilities not identified or reasonably identifiable at the time construction commences, standing alone, shall be considered new construction of improvements and shall not be considered a material or substantial change to that previously permitted development.
We advanced a second reason why the landowners were required to obtain an Act 250 permit amendment: the existing Act 250 permit expressly stated that “[a]ny sale [or] further construction . . . is specifically not approved without an amendment.” Id. ¶ 19 (brackets omitted). The Environmental Court had relied on this condition to conclude that an amendment was required, and the landowners did not argue otherwise on appeal. We thus concluded that the landowners had conceded that an amendment was required by the terms of the permit, although we noted in dicta that this was a reasonable construction of the permit that we would otherwise affirm. We did not expressly hold, as the dissent argues, that “a prior permit condition controlled . . . irrespective of whether the farming exemption applied.” Post, ¶ 43. Indeed, we engaged in no extended discussion of the farming exemption with respect to the applicability of the terms of the existing permit. Additionally, it was the landowners in Eustance who were responsible for obtaining a permit amendment. It is not apparent from this record that the holders of the Barry permit participated in the proceedings below. The Environmental Court did not order them to take any action, and they are not parties to this appeal. In any event, and more importantly, our decision in Eustance does not involve the same considerations as those at issue in the instant case, nor does its reasoning compel us to ignore the plain intent of the Legislature that Rule 70 provide the sole basis for Act 250 jurisdiction over utility line projects.
