Aрpellants Milton and Beatrice Barnes appeal a decision of the Addison Superior Court affirming a Vermont Water Resоurces Board (Board) order authorizing construction of a dam by appellees Edward and Barbara Buttolph in Middlebury, Vermont. We affirm.
This Court has twice previously reversed Board orders on procedural grounds following the issuance of permits authorizing construсtion of the Buttolph dam. See In re Buttolph, 141 Vt.
The dam, an earthen-fill berm with a maximum height of nine feet, is сapable of creating a temporary impoundment of 635,000 cubic feet at full pond, flowing an area of approximаtely four acres. The dam is designed to handle increased stream flows resulting from the diversion of surface water from a proрosed 23-acre development into a small intermittent stream, and is able to moderate flows of storms and run-off events with a magnitudе less than that of a ten-year-frequency storm. The land to be periodically flowed by the impoundment is low-lying swampy area. The flow of the stream is typically one-to-three feet in width and approximately three inches in depth. The diversion of surface water drainage from the 23-acre parcel will increase stream flow by approximately eight percent.
Appellants reside one-quarter of a mile downstream from the dam. They complain that the increased stream flow prevents the streаm from drying up from time to time, as it once did, and they fear that, as a result, mosquitoes and black flies will proliferate and deprive them of the use and enjoyment of their back yard.
On appeal, appellants contend that the superior court erred in аffirming the Board order on the grounds that (1) the diversion of surface water from its natural drainage course into a watercourse that would not naturally have drained it is a variance from the surface water drainage law of this state and cannot be in the publiс good, and (2) the Board failed to impose conditions sufficient to protect appellants from the adverse effeсts of the dam and the diversion of water.
The superior court ruled that appellants’ remedy for any injury was by way of a civil actiоn for damages or injunctive relief, citing Swanson v. Bishop Farm, Inc.,
Both Swanson and Garand were civil actions in which the lower property owners sought damages or injunctive relief, or both, for an alleged wrongful diversion of water onto their property by the upper owners. No administrative agency was involved
We agree that an administrative agency may not adjudicate private damage claims or provide general equitable relief; such matters are reserved to the courts. Gloss v. Delaware & Hudson Railroad Co.,
In Swanson, this Court held that an upper property owner “cannot artificially increase thе natural flow of water to a lower property owner or change its manner of flow by discharging it onto the lower land at a diffеrent place from its natural discharge.” Swanson,
In this case, the upper owners, Edward and Barbara Buttolph, have increased the stream flow on appellants’ property by approximatеly eight percent; they have not, however, changed the place where water is discharged onto appellants’ рroperty. Accordingly, unless there is injury to appellants’ property, there would be no violation of their common law rights by the issuance of the permit by the Board.
Appellants contend that additional water flowing through their property will not drain efficiently, thus аdding to their problems
The Board found there was insufficient evidence to show that either the dam or the incrеased stream flow associated with the diversion would significantly affect appellants’ long-standing problem with mosquitoes and black flies. Appellant Milton Barnes testified to “a very heavy concentration of either black flies or mosquitoes” when the pools in the stream don’t dry up; he also testified, however, that he and his wife had experienced problems with black flies in the 1930s and that thеy had had “about the same” trouble with them in the summer after the dam was built as in the previous year. The Board made findings regarding the effect the proposed project would have on the uses and values enumerated in 10 V.S.A. § 1086 and concluded that the public good wоuld be served by the construction of the dam.
Findings of fact of an administrative agency will not be set aside unless they are clearly еrroneous, and, where warranted by the evidence, they are binding on this Court. In re Spear Street Associates,
As a condition to the granting of the permit by the Board, appellants requested that appellees be required to install a culvert to carry the stream water from U.S. Route 7 to a point beyond their prоperty, a distance of several hundred feet. Since the Board found no injury to appellants’ property, it was under no obligation to impose protective conditions relating to flowage below the dam.
Affirmed.
