In re Atlantic City Electric Co.
The opinion of the court was delivered by
A group of county utility authorities, townships, and private entities, denominated the Rate Intervention Steering Committee
We agree with Administrative Law Judge (ALJ) Gural and the BPU and hold that after the BPU approved a contract for the Atlantic City Electric Company to buy energy at regulated costs, federal law preempted the BPU’s reconsideration due to a reduction of market rates to levels below the original contract rates.
Contracts of Atlantic City Electric to buy electric energy were governed by the rules of the Federal Energy Regulatory Commission (FERC), pursuant to 16 U.S.C.A §§ 791-828c (the Public Utility Regulatory Policies Act of 1978, also referred to as PURPA). PURPA was part of a comprehensive effort to combat a national energy crisis, and was intended to reduce the country’s reliance on oil and gas by increasing the use of more abundant, domestically produced fuels. Hence, PURPA requires that FERC adopt rules requiring public utilities to buy electric energy from qualified cogeneration facilities (QF), also known as non-utility generators of power (NUG). Freehold Cogeneration Assocs., L.P. v. Board of Regulatory Commissioners of New Jersey,
The rules require that “standard rates” be established for purchases of electric power from NUG’s.
Pursuant to PURPA, the BPU set out to establish standard rates for the purchase by utilities of electric energy from NUG’s. Specifically, on May 12, 1981, the BPU conducted a hearing to receive public comment on the issue. The BPU also requested electric utilities to provide data regarding their avoided costs. On October 14,1981, the BPU issued an order establishing a method
In New Jersey, utilities generally increase their rates through base rate proceedings initiated by the filing of a petition. However, electric utilities such as Atlantic City Electric may also seek an annual increase in their rates by petitioning for a modification of their “fuel adjustment clause,” also known as a “levelized energy adjustment clause,” or “LEAC.” Application of Rockland Elec. Co., 231 N.J.Super. 478, 483-84,
widely used and judicially accepted rate-making mechanism used to recover certain components of fuel costs incurred by a utility. Originating during the energy crisis of the 1970’s, energy adjustment clauses are designed to permit a utility to include in rates initial estimates as to future fuel costs and to make subsequent periodic adjustments to reflect actual costs when ascertained.
[Application of Rockland, supra, 231 N.J.Super. at 484,555 A.2d 1140 ].
In sum, a constant LEAC charge is included in a utility’s overall rate tariff “based on estimated prospective 12-month energy costs. This charge is subject to periodic adjustment to reflect actual
In 1987, when Atlantic City Electric sought approval of its proposed agreements with several NUGs, a settlement required Atlantic City Electric to use an agreed standard pricing methodology to set prices when it contracted with a NUG. In 1988, another BPU settlement grandfathered Atlantic City Electric’s NUG contracts, and those contracts did not require re-negotiation until seven years later in 1995, when Atlantic City Electric filed a LEAC petition for the period from June 1, 1995 to May 31, 1996.
RISC opposed the petition, contending that the NUG contracts approved in the 1980s were based on projected energy costs, but those projections proved to be inaccurate in that they were higher than the actual current costs. Thus, it argued that the BPU should reject any recovery by Atlantic City Electric of the contract costs associated with buying energy. RISC asserted that the NUG contracts should be voided, since that would save ratepayers money, regardless of the impact on Atlantic City Electric or the NUGs.
ALJ Gural sustained the proposed LEAC increase for Atlantic City Electric. He rejected the opposition proposal to void the NUG contracts, based on Freehold and a FERC decision, New York State Electric and Gas Corp., 71 FERC ¶ 61,027,
The preemption issue was created by
*364 [T]he Commission shall, after consultation with representatives of State regulatory authorities, electric utilities, owners of cogeneration facilities and owners of small power production facilities ... prescribe rules under which geothermal small power production facilities of not more than 80 megawatts capacity, qualifying cogeneration facilities and qualifying small power production facilities are exempted in whole or part from, the Federal Power Act ... from the Public Utility Holding Company Act ... from State laws and regulations respecting the rates, or respecting the final or organizational regulation, of electric utilities, or from any combination of the foregoing, if the Commission determines such exemption is necessary to encourage cogeneration and small power production.
[Emphasis added].
FERC regulations similarly provided that any NUG shall be exempted from state law or regulation respecting the rates of electric utilities.
In Freehold, supra, a NUG, Freehold Cogeneration Associates, entered into a contract with Jersey Central Power and Light. The agreement between the two entities was approved by the BPU (then the Board of Regulatory Commissioners).
However, as the cost of obtaining electric power decreased, Jersey Central sought to buy out the contract; the NUG rebuffed those efforts. The BPU ordered the parties to renegotiate their power purchase agreement, or alternatively to negotiate a buy-out. If no agreement was reached within thirty days, the BPU would conduct hearings to determine how to proceed. Freehold then sued, seeking a declaratory judgment that the BPU was preempted by PURPA from requiring it to renegotiate its contract with Jersey Central. Id. at 1183.
In addressing the issue, the Third Circuit accepted Freehold’s argument that any attempt to revisit a previously approved NUG contract as a result of changed circumstances deprived the NUG of the “benefits of the bargain.” Id. at 1193. The court held that:
[O]nce the BRC approved the power purchase agreement between Freehold and [Jersey Central] on the ground that the rates were consistent with avoided cost, any action or order by the BRC to reconsider its approval or to deny the passage*365 of those rates to [Jersey Central’s] consumers under purported state authority was preempted by federal law.
[Id. at 1194.]
FERC has also ruled that the pass through of NUG contract costs to ratepayers should not be subject to subsequent disapproval if the contracts were not challenged when approved. See New York State Electric and Gas Corp., supra, 71 FERC ¶61027,
Therefore, the precise argument raised by RISC here has been rejected by both FERC and the Court of Appeals for the Third Circuit. That is, once a NUG contract is executed and the NUG is operating under the contract, neither FERC nor the courts will retroactively invalidate the contract simply because energy costs to the utility become lower in the market than they are under the contract. As did those tribunals, we hold that once a NUG contract is executed and becomes operational, there can be no retroactive invalidation of the contract just because energy rates in the market fall below the contract rates. We reject RISC’s attempt to distinguish its situation from the cited cases by
By affirming the BPU on the basis of federal preemption, we need not address the other claims raised by RISC.
Affirmed.
Notes
Notably, in 1978, when PURPA was enacted, there was little nonutility power generation. By 1995, as the result of PURPA, NUGs provided over one-half of all new generation resources. Southern Calif. Edison Co., 70 FERC 1161,215,
PJM refers to the Pennsylvania-New Jers ey-M aryl a nd interconnection, a pooled power cooperative used by utilities in those three states.