¶ 1. This matter arose out of a zoning permit issued by the Town of Castleton to appellee Dr. Roshan Sivagnanam for improvements to his camp on Lake Bomoseen. Appellant Carolyn Hignite, who owns a camp adjacent to Dr. Sivagnanam’s, appealed the permit to the Town’s zoning board of adjustment, and Dr. Sivagnanam appealed a subsequently issued notice of violation. The Board dismissed Hignite’s appeal as untimely, and granted Dr. Sivagnanam’s appeal, dismissing the notice of violation. Hignite appealed the decisions to the environmental court. The court granted Dr. Sivagnanam’s motion to dismiss, and entered a final judgment in his favor. Hignite contends the court erred in: (1) finding that her appeal of the *563 permit was time barred; and (2) failing to address issues relating to the notice of violation. We agree with the second contention, and therefore reverse and remand.
Background and Procedural History
¶ 2. The record discloses the following. On September 11, 2000, the Town’s zoning administrator received from Dr. Sivagnanam an application for a permit to perform certain work on his camp, including the construction of two decks facing the lake. Hignite, who owns a lakefront camp adjacent to Dr. Sivagnanam, alleges in her affidavit that she visited the zoning administrator’s office on September 14 to review the application, informed the administrator that it contained inaccurate information, and was told to put her objections in writing. The zoning administrator issued the permit that same day. Hignite claims that the administrator failed to inform her that the permit had issued, and failed to post the permit in a public place for fifteen days following issuance, as required by 24 V.S.A. § 4443(b)(2). *
¶ 3. On October 13, the administrator received Hignite’s letter outlining her belief that the distances from the proposed decks to her property line were a few feet less than Dr. Sivagnanam had represented in his application, and violated the setback requirements of the Town’s zoning ordinance. The administrator responded to Hignite in a letter on the same day, indicating that the permit had issued, explaining that “[i]t appears you would be in a position to appeal my decision on the permit” to the zoning board of adjustment (Board), and stating that Hignite would be given a hearing before the Board where “you will be permitted to state your ease.” Hignite filed her appeal on October 18.
¶ 4. The Board discussed the matter several times over the next year, but did not act on Hignite’s appeal. In late August 2001, Hignite’s attorney wrote the zoning administrator, asserting that Dr. Sivagnanam’s new decks exceeded 300 square feet and violated the setback requirements of the zoning ordinance. The ordinance contains a provision that no zoning permit is required, nor are setbacks applicable to, newly constructed decks not over 300 square feet or three feet above the level of the ground story. Several days later, the zoning administrator issued a notice of violation to Dr. Sivagnanam, stating that he was in violation of the zoning ordinance due to the “Construction of a structure and improvements without a permit, to the extent those improvements and any other modifications are not specifically approved. The structure erected being a building or addition to a building.”
¶ 5. Dr. Sivagnanam appealed the notice of violation to the Board, arguing that it failed to state with specificity the nature of the alleged violation, in violation of his constitutional right to due process, and that to the extent it involved the decks the permit was final and the appeal filed by Hignite was untimely under 24 V.S.A. § 4464(a). The statute provides that an appeal from a decision of the zoning administrator to the Board must be filed within fifteen days of the administrator’s decision. Hignite’s October 18 appeal of the administrator’s September 14 decision was unquestionably out of time.
¶ 6. On January 15, 2002, the Board issued separate findings of fact and conclusions of law on the two appeals. The Board denied Hignite’s appeal of the permit, concluding that it was untimely under § 4464. The Board granted Dr. *564 Sivagnanam’s appeal of the notice of violation, concluding that no permit was necessary under the zoning exemption. Hignite then filed a pro se notice of appeal with the environmental court, stating that she “wish[ed] to appeal ... the decision of the Castleton Zoning Board of Adjustment dated January 15, 2002 with regard to the application of Dr. Roshan Sivagnanam.”
¶ 7. Dr. Sivagnanam, in response, moved to dismiss the appeal or, in the alternative, for summary judgment on the ground that Hignite’s untimely appeal to the Board had deprived the court of jurisdiction. See
Town of Charlotte v. Richmond,
Discussion
¶ 8. The question whether the Town’s alleged failure to provide the statutorily required constructive notice should alow Hignite to proceed with her appeal raises an interesting and unsettled issue. Although we have consistently held that the failure to appeal a zoning decision to the board of adjustment bars a subsequent challenge “even when the decision is alleged to have been void ab initio,”
City of S. Burlington v. Dep’t of Corr.,
V 9. We need not, however, resolve that issue here, for the claims that Hignite apparently hoped to raise with respect to the granting of the permit were essentially comparable to those underlying the subsequent notice of violation issued by the zoning administrator, which was properly before the Board and the trial court. See
In re Charlotte Farm & Mills,
¶ 10. Although properly appealed and brought to the court’s attention in both the motion to alter or amend and the motion for reconsideration, the notice-of-violation issue was never addressed by the trial court. "Whatever the meaning of the court’s broad rejection of “[a]ll other arguments” in its order denying the motion for reconsideration, it does not represent an adequate decision on the merits for purposes of appellate review. See
New England P’ship v. Rutland City Sch. Dist.,
The judgment is reversed, and the case is remanded for further proceedings consistent with the views expressed herein.
Notes
Dr. Sivagnanam asserts, to the contrary, that the administrator complied with the statute by posting the permit for the requisite fifteen-day period. As explained below, our disposition of the appeal renders this factual dispute immaterial.
