195 F. 465 | 2d Cir. | 1912
There were separate contracts, and the only question here is when the work under each was finally performed or materials finally furnished. More specifically the question whether something that was done at the several localities where the work was performed, <on dates subsequent to the doing of the work called for, was or was not, in each instance, a “last item of work performed or materials furnished” under the contract, or was something additional. Unless the claimant can establish that these final items were a part of what ■each contract called for, its claim of lien was properly dismissed.
The Brooklyn Heights Railroad Company undertook to reconstruct a portion of its roadbed which necessitated the construction of two sets of bridges. One set is referred to in the record as “railroad bridges,” which carried the railroad over the street or avenue. The other set is referred .to as “highway bridges,” which carried the street -or avenue over the railroad. The railroad company contracted with the bankrupt corporation for the construction of solid floors upon •both sets of bridges. The bankrupt made a written contract for the waterproofing of the floors of the railroad bridges. The contract is an -elaborate one embodying many of the clauses giving specifications, etc., which were in the contract between the railroad and the bankrupt. Among these are the clauses usually found, in construction contracts providing'that the work shall be done to the satisfaction of the engineer in charge, who is made the sole judge of the quality and -quantities'of materials supplied and work executed and of the interpretation of the specifications and provisions of the contract, the production of his certificate being made a condition precedent to the right to receive any money under the contract.
The contract after detailing the method of laying flooring with felt,' bricks, and hot waterproofing material provides that the last “course of bricks shall be laid flat in the compound, and all joints poured full
The claimant fully completed the work called for under its contract for waterproofing the concrete on June 17, 1908. 'No complaint was ever made of this, no overhauling or retouching was ever called for. No notice of lien for this work was filed until more than 90 days after June 17, 1908, and therefore no lien was secured therefor.
Although no formal contract for the blocks was executed, the evidence shows that both parties were familiar with the provisions of the contract between the railroad company and' the bankrupt for building the bridges. There can be no doubt that both of them understood that the wood blocks which the one was to order and the other was to furnish should conform to the specifications as to size, material, character, etc., which that contract called for. The evidence shows that a large number of them did not so conform, and in our opinion, until proper specification blocks were delivered in their place, the contract of the claimant was not fully completed. That being so, this delivery on November 23, 1908, was a “last item of materials furnished,” and, since a notice of lien in proper form was filed within 90 days after that date, the statutory lien was secured.
The order of the District Court should be modified so as to provide for the payment of the amount secured by this lien, and in all other respects such order is affirmed.