IN Bell Tele Co v. McCarty, William D.IN Bell Tele Co v. McCarty, William D.
Case Information
*2 Before B AUER , K ANNE and E VANS , Circuit Judges . K ANNE , Circuit Judge
. This appeal stems from the inter-
connection agreement established between Indiana Bell
Telephone Company, Incorporated d/b/a Ameritech Indiana
(“Ameritech”) and AT&T Communications of Indiana, GP
and TCG Indianapolis (collectively “AT&T”) pursuant to the
Telecommunications Act of 1996 (“Act”).
[1]
Because the
parties could not reach a consensus regarding the content
of the agreement, they submitted it to arbitration before the
Indiana Utility Regulatory Commission (“IURC”).
Ameritech then sought declaratory and injunctive re- lief from the district court. It argued that various provisions established by the IURC through arbitration and incorpo- rated into the approved agreement violated the Act. The district court granted the request for an injunction in part and denied it in part, remanding certain issues to the IURC for further findings. Ameritech, the IURC Commissioners, and AT&T appealed portions of the district court’s order, 3 and those appeals were consolidated for our review. [3] We affirm in part and reverse in part.
I. Background
The Telecommunications Act of 1996 seeks primarily
to promote competition in the previously monopoly-
driven local telephone service market.
See Verizon
Communications, Inc. v. FCC
,
The Act seeks, with regard to its rate-setting and other
features, to “give aspiring competitors every possible in-
centive to enter local retail telephone markets, short of
confiscating the incumbents’ property.”
Id.
at 489. It also
requires incumbents to negotiate an agreement, referred to
as an “interconnection agreement,” with new entrants at
their request.
After a state commission arbitrates the open issues,
the parties submit their interconnection agreement re-
flecting the arbitrated resolutions to the state commission
for approval.
II. Analysis
We turn now to the issues before us on appeal. Each of these issues was contested during the IURC arbitration and decided by the arbitrator, then ordered to become part of the interconnection agreement between the parties. Ameritech argues that the district court erred when it af- firmed (1) the IURC’s decision to award AT&T the “tandem reciprocal compensation rate” rather than the lower “end- office rate;” and (2) the IURC’s determination that Ameritech must splice “dark fiber” for AT&T upon request. As we lay out below, we affirm the district court on both issues appealed by Ameritech.
AT&T appeals three of the district court’s decisions. First, AT&T argues that the district court erred in remanding for further findings the agreement provisions requiring Ameritech to provide AT&T with combinations of network elements that Ameritech ordinarily combines for itself as well as combinations that it ordinarily does not combine for itself. Second, AT&T states that the district court erred in enjoining the portion of the interconnection agreement requiring Ameritech to perform “acceptance testing” before opening a loop circuit requested by AT&T. Third, AT&T contests the district court’s order remanding for further findings the IURC’s decision requiring Ameritech to unbundle packet switching. While we affirm the district court’s remand on issues one (combination of network elements) and three (packet switching), we reverse on issue two, reinstating the IURC’s decision with respect to accep- tance testing.
A. Ameritech’s Appeal
1. Tandem Reciprocal Compensation Rate
One term of the interconnection agreement between
Ameritech and AT&T covers the price to be paid when a
telecommunication (e.g. telephone call, facsimile, modem
dial-up, etc.) originates on the network Ameritech built but
terminates on AT&T’s equipment. Under the Act, not only
can AT&T pay to use certain elements of Ameritech’s vast
telecommunications network, AT&T can build switches of
its own, which Ameritech then must allow to interconnect
with its network. That way, consumers who use AT&T as
their local telephone service provider may call consumers
who use Ameritech as their local telephone service provider.
However, AT&T must pay Ameritech for its costs in allow-
ing the call to travel through its switch and arrive at its
customer’s receiver and vice versa.
See Ill. Bell Tel. Co.
, 179
F.3d at 568;
Problems in calculating the reciprocal compensation rate arise because, as the FCC has recognized, new entrants design their networks and deploy their switches differently than incumbents due to changes in technology. See In re Implementation of the Local Competition Provisions of the Telecomms. Act of 1996 , 11 FCC Rcd. 15,499, 16,042, ¶ 1090 (Aug. 8, 1996) (“ Local Competition Order ”). Incum- bents, which usually have older networks and thus older technology, typically route calls from new entrants’ cus- tomers either through an “end-office switch” (a computer that directly serves the Ameritech customer being called) or a “tandem switch” (a computer hub that connects end-office switches). If Ameritech routes an AT&T customer’s call directly through Ameritech’s end-office switch, AT&T is charged the “end-office rate.” The end-office rate is a lower rate that compensates Ameritech for the cost of end-office switching alone. But, if Ameritech must route the call through a tandem switch, then AT&T pays Ameritech the higher “tandem rate.” The tandem rate compensates Ameritech for (1) the tandem switching it performs to route the call to the end-office switch; (2) the transport between the tandem switch and the end-office switch; and (3) the end-office switching that delivers the call to the customer. See MCI Telecomms. Corp. , 79 F. Supp. 2d at 790 (E.D. Mich. 1999).
New entrants cannot hope to replicate the incumbents’
network switch for switch but, as stated before, have the
advantage of newer technology. Thus, a new entrant can
typically deploy a single switch in a central location, then
lease various elements from the incumbent in order to
connect the new entrant’s customers to its central switch
and the incumbent’s end-office switches. In this way, the
new entrant is able to serve with one switch a geographic
area that the incumbent would serve with a minimum of
ten-to-fifteen end-office switches. The new entrant’s central
switch and leased transport facilities, therefore, “perform
functions similar to those performed by an [incumbent’s]
tandem switch.”
Local Competition Order
, 11 FCC Rcd. at
16,042, ¶ 1090. Hence, if a new entrant can show that its
one switch “serves a geographic area comparable to the area
served by the [incumbents’] tandem switch,”
The IURC determined that AT&T met the geographic
coverage test established by
Ameritech first challenges the affirmance of the tan-
dem reciprocal compensation rate award on the basis that
the district court applied the wrong standard of review. The
district court found that whether AT&T met the geographic
coverage test established by
We agree with the argument advanced by Ameritech that
the district court should have conducted a de novo review of
the IURC’s interpretation of the regulation in question.
See
,
e.g.
,
MCI Telecomms. Corp.
,
There is precious little case law interpreting
Commission refused to do so.
[8]
Virginia Arbitration Order
,
17 FCC Rcd at 27,044-45, ¶¶ 6, 7;
see also
The Virginia Arbitration Order addresses the precise issue before us—whether the geographic area test outlined in Rule 711(a)(3) requires the new entrant to actually serve, as opposed to merely be capable of serving, the same geographic area as the incumbent. 17 FCC Rcd. at 27,182- 83, ¶ 304. In siding with the new entrants and determining that Rule 711(a)(3) requires that new entrants demonstrate only that they are capable of serving the same geographic area as the incumbent, the WCB stated:
[T]he determination whether a [new entrant’s] switch “serves” a certain geographic area does not require an examination of the competitor’s customer base. . . . The tandem rate rule recognizes that new entrants may adopt network architecture different from those de- ployed by the incumbent; it does not depend upon how successful the [new entrant] has been in capturing a “geographically dispersed” share of the [incumbent’s] customers, a standard that would penalize new en- trants. We agree . . ., therefore, that the requisite comparison under the tandem rate rule is whether the [new entrant’s] switch is capable of serving a geo- graphic area that is comparable to the architecture served by the [incumbent’s] tandem switch.
Id. at 27,186-87, ¶ 309 (emphasis added).
We find the WCB’s pronouncement on this issue not only
persuasive, given the Act’s overarching goal of promoting
competition and the WCB’s expertise in this area, but one
requiring deference as the voice of the FCC interpreting its
own rules.
See Chevron, U.S.A., Inc. v. Natural Res. Def.
Council
,
requiring that the charges, practices, classifications, and reg- ulations of communications common carriers providing in- terstate and foreign services are just and reasonable. . . .
v. Pub. Serv. Comm’n of Utah
,
According to the FCC’s rules on delegation of authority, the WCB literally stepped into the shoes of the FCC when it assumed responsibility of the Virginia arbitration:
(a) The person, panel, or board to which functions are delegated shall, with respect to such functions, have all the jurisdiction, powers, and authority conferred by law upon the Commission, and shall be subject to the same duties and obligations.
(b) . . . any action taken pursuant to delegated authority shall have the same force and effect and shall be made, evidenced, and enforced in the same manner as actions of the Commission.
Although we recognize that actions decided by delega-
tion of authority are subject to review by the FCC under
Ameritech does not make the alternative argument that even if the IURC applied the test appropriately, which we have found it did, the evidence presented by AT&T fails to establish that its switches have the ability to serve the same areas served by the Ameritech tandem switches. Indeed, Ameritech concedes that AT&T provided evidence supporting the IURC’s findings on this issue. (See, e.g., App. Opening Br. p. 20.) Because the IURC correctly in- terpreted the geographic coverage test established in Rule 711(a)(3), and because Ameritech does not contest the IURC’s findings of fact showing that AT&T met the test, the district court’s decision upholding the IURC’s determination that AT&T is entitled to the tandem reciprocal compensa- tion rate was correct.
2. Dark Fiber
“Dark fiber” is excess cable laid in anticipation of future
use, but not currently connected to electronics, or “lit,”
enabling it to carry telecommunications signals.
In re
Implementation of the Local Competition Provisions of the
Telecommunications Act of 1996
, 15 FCC Rcd. 3696, 3776,
¶ 174 (Nov. 5, 1999) (“
UNE Remand Order
”). The act of
connecting dark fiber to electronics so that it can carry a
signal is called “splicing.” Ameritech conceded in one of its
several
We require incumbent LECs to make routine network modifications to unbundled transmission facilities used by requesting carriers where the requested transmis- sion facility has already been constructed. By “routine network modifications” we mean that incumbent LECs must perform those activities that incumbent LECs regularly undertake for their own customers. ***
15 By way of illustration, we find that loop modification functions that the incumbent LECs routinely perform for their own customers, and therefore must perform for competitors, include, but are not limited to, rearrange- ment or splicing of cable . . . .
2003 FCC L EXIS 4697 at *1025, 1027-28, ¶¶ 632, 634.
Ameritech appropriately observed in its
B. AT&T’s Appeal
1. New Combinations of Network Elements
Before the IURC and in its opening brief before the dis-
trict court, Ameritech argued that
Iowa Utilities Board v.
FCC
,
The Supreme Court’s decision in
Verizon Communications
Inc. v. FCC
,
As a threshold matter, AT&T argues Ameritech has
waived its right to rely on the Supreme Court’s decision
in
Verizon
. Even though
Verizon
was not decided until
midway through briefing before the district court, AT&T
argues that Ameritech should have anticipated its holding
and presented alternative arguments before the IURC
and the district court, instead of relying exclusively on
IUB
III
, the relevant portion of which
Verizon
subsequently
reversed. Because it did not make its
Verizon
-based argu-
ments before the IURC, AT&T contends Ameritech was
prohibited from doing so when it sought review from the
district court.
See
,
e.g.
,
Southwestern Bell Tel. Co. v. Pub.
Util. Comm’n of Tex.
,
“[W]here the Supreme Court decides a relevant case while litigation is pending . . . omission of an argument based on the Supreme Court’s reasoning does not amount to a waiver . . . .” Old Ben Coal Co. v. Dir., Office of Worker’s Comp. Programs , 62 F.3d 1003, 1007 (7th Cir. 1995) (quotation omitted). This is especially true where, as here, once Ameritech discovered that Verizon foreclosed the previous arguments made before the IURC with respect to combina- tions at issue in the interconnection agreement, it requested only that the district court remand the relevant sections of the interconnection agreement to the IURC for reconsidera- tion in light of Verizon . See id. (“Moreover, waiver is a flexible doctrine, too, so that when all the claimant asks for is a remand to permit the agency to consider an intervening decision—a decision the agency couldn’t have considered earlier—the doctrine does not stand in the way.” (quotation omitted)).
AT&T next argues that remand is unnecessary as the
IURC’s decision accurately tracks
Verizon
. Again, we disa-
gree.
Verizon
reinstated the combination rules invalidated
in
IUB III
,
On its face Rule 315(c) contains only two limitations to an incumbent’s duty to perform combinations of unbundled network elements—technical feasibility and discriminatory impact. It states:
(c) Upon request, an incumbent LEC shall perform the functions necessary to combine unbundled network ele- ments in any manner, even if those elements are not ordinarily combined in the incumbent LEC’s network, provided that such combination: (1) Is technically feasible; and (2) Would not undermine the ability of other car- riers to obtain access to unbundled network ele- ments or to interconnect with the incumbent LEC’s network.
In sum, what we have are rules that say an incumbent shall, for payment, “perform the functions necessary,”47 C.F.R. §§ 51.315(c) and (d) (1997), to combine net- work elements to put a competing carrier on an equal footing with the incumbent when the requesting carrier is unable to combine, First Report and Order ¶ 294, when it would not place the incumbent at a disadvan- tage in operating its own network, and when it would not place other competing carriers at a competitive disadvantage,47 C.F.R. § 51.315(c)(2) .
Id. at 538. In so doing, the Supreme Court more clearly delineated under what circumstances an incumbent can be required to combine unbundled network elements.
When the IURC approved the interconnection agreement between the parties, it did not have the benefit of the Supreme Court’s Verizon opinion. Of the limitations in- corporated by Verizon into Rule 315(c), AT&T admits that the interconnection agreement fails to reflect any finding by the IURC that Ameritech must provide combination of unbundled network elements because AT&T cannot do them itself. AT&T posits that such a limitation should be read into the agreement based on certain findings by the IURC in the arbitration order and based on testimony accepted by the IURC in making those findings. We decline *20 20
to do so. The interconnection agreement as approved is in- consistent with the Act as interpreted in Verizon , and should be remanded to the IURC for reconsideration. 2. Acceptance testing
AT&T next argues that the district court’s finding that Ameritech need not perform “acceptance testing” at AT&T’s request because it results in providing AT&T with a network superior in quality to Ameritech’s own in dero- gation of the Act. Acceptance testing involves Ameritech’s field technician conducting a noise and frequency response test prior to opening a loop circuit requested by AT&T. The purpose of the acceptance test is to ensure the line is error- free, resulting in better quality and reliability for custom- ers.
Ameritech argued before the IURC that because it doesn’t
provide acceptance testing for its own retail customers, it
shouldn’t have to provide it for AT&T. The IURC ordered
Ameritech to perform acceptance testing anyway, finding it
to be in the public interest because it could reduce the need
for later line maintenance, would ensure reliable, quality
service to customers, and would promote competition. In
doing so, the IURC acknowledged that such a requirement
made Ameritech provide AT&T with better service than it
provides for its own customers and that the Eighth Circuit
voided the FCC rule requiring incumbents to provide
superior quality networks to new entrants.
See IURC
Arbitration Order
, No. 40571-INT-03, p. 76 (Nov. 20, 2000);
IUB I
,
Therefore, while the FCC is limited to promulgating rules that are not contrary to the plain meaning of the Act, as a state commission we must only prescribe reg- ulations that are consistent with the Act. States can “raise the bar” of the telecommunications providers[’] standards, provided the bar does not conflict with the Act.
Id. at 77-78 (emphasis in original).
The district court disagreed with the IURC’s interpre-
tation of the power granted to it under the Act in this
instance and reversed the acceptance testing requirement
as being in conflict with the Act, relying upon
IUB III
’s
statement that “[s]uperior quality requirements ‘violate the
plain language of the Act.’ ” (Dist. Ct. Op. at 16) (quoting
IUB III
,
Prior to the passage of the Act, the states had primary
regulatory control over local telecommunications markets.
Ill. Bell. Tel. Co.
,
Nothing in this part precludes a State from imposing requirements on a telecommunications carrier for in- trastate services that are necessary to further competi- tion in the provision of telephone exchange service or exchange access, as long as the State’s requirements are not inconsistent with this part or the Commission’s regulations to implement this part.
In prescribing and enforcing regulations to implement the requirements of this section, the Commission shall not preclude the enforcement of any regulation, order, or policy of a State Commission that— (A) establishes access and interconnection obliga- tions of local exchange carriers; (B) is consistent with the requirements of this sec- tion; and
(C) does not substantially prevent implementation of the requirements of this section and the pur- poses of this part.
Based on the plain language of the Act, it’s clear the IURC had independent authority preserved under the Act to impose acceptance testing requirements on Ameritech by way of the interconnection agreement. As the IURC found, the requirement promoted competition and enhanced service quality for Indiana consumers and thus was consis- tent with the Act. Cf. Ill. Bell Tel. Co. , 179 F.3d at 574 (noting that deference to state commission decisions is not improper considering the “important role” left to them by the Act in the field of interconnection agreements).
Ameritech argued, and the district court found, that re-
gardless of any independent state authority that may have
survived the Act, the IURC’s imposition of acceptance test-
ing is barred by the logic of the Eighth Circuit’s decisions
relating to the now void FCC “superior quality” regulation.
According to the Act, incumbents must provide intercon-
nection to new entrants “that is
at least equal
in quality” to
that enjoyed by the
incumbent
itself.
As already explained, the roles—and the authority—of the state commissions and the FCC are distinct under the Act. Hence, we do not agree with the premise advanced by Ameritech that because the FCC may not implement a blanket regulation requiring superior quality, the IURC may not require acceptance testing when, after individual- ized review, it finds it to be in the public interest and a means of promoting competition in Indiana. The Eighth Circuit’s prohibition of superior quality mandates applied only to the FCC in its role as federal regulator, not to the IURC in its role as state regulator. We find that the IURC’s imposition of the acceptance testing requirement does not conflict with the spirit and purpose of the Act and is an appropriate use of the state law authority left to it under the Act.
Further, the IURC’s requirement that Ameritech provide
acceptance testing does not “violate” the plain meaning
of the Act, since the Act states that the quality provided
by the incumbent must be “at least equal.”
Because the IURC acted under authority preserved by the Act and required Ameritech to provide superior quality access allowed under the Act, the district court’s determina- tion otherwise must be reversed.
3. Packet Switching
As we have discussed, the Act is dynamic legislation, subject to ever-evolving interpretation based on FCC and court pronouncements. The parties’ dispute with regard to the IURC’s “packet switching” unbundling requirement highlights the fluidity of the law, resulting in our affirm- ance of the learned district judge’s remand order on this issue, but on different grounds.
The IURC considered “packet switching,” a type of net-
work element, to be one that must be made available by
Ameritech to AT&T on an unbundled basis. According to
the FCC regulations in effect at the time the parties entered
into the interconnection agreement, packet switching
unbundling was required only when four specific conditions
were met.
The FCC regulation in question,
We find, on a national basis, that competitors are not impaired without access to packet switching, including routers and DSLAMs. Accordingly, we decline to un- bundle packet switching as a stand-alone network ele- ment. We further find that the Commission’s limited exception to its packet-switching unbundling exemption is no longer necessary.
Triennial Review Order , 2003 FCC LEXIS 4697, at *888, ¶ 537. The FCC based its determination on evidence that competitors regularly deployed their own packet switches without significant barriers, making unbundled access to the incumbents’ unnecessary. Id. at *889-92, ¶¶ 538-39.
In spite of the Order , AT&T continues to argue that states still maintain authority to order the unbundling of packet switching and that, in any event, we are obligated to apply the law as it existed at the time of the agreement. As to the latter point, AT&T makes much of the Order ’s refusal to unilaterally change all interconnection agreements to comply with the new unbundling requirements. The FCC defers instead to telecommunications providers’ intercon- nection agreement provisions establishing procedures for dealing with changes in the law; where the providers have not negotiated the procedure to follow when the law changes, the FCC directs providers to the default provisions of the Act regarding the same. Id. at *1112-13, ¶ 701. By favoring change through the interactive process espoused by the Act, we do not understand the FCC to advocate a bar to this court’s ability to apply the law as it currently stands. Further, we are obligated to do so:
Because the role of the federal courts is to determine whether the agreements comply with the Act . . ., we conclude that we must ensure that the interconnection agreements comply with current FCC regulations, regardless of whether those regulations were in effect when the [state commission] approved the agreements.
See Jennings
,
As to AT&T’s insistence that the Triennial Review Order does not preempt the state’s authority under state law to order packet switching unbundling, we find that the Order does not entirely foreclose this argument. The Order expli- citly states: “We do not agree with incumbent LECs that argue that the states are preempted from regulating in this area as a matter of law.” Triennial Review Order , 2003 FCC LEXIS 4697, at *305, ¶ 192.
Therefore, we affirm the district court’s remand of this
issue to the IURC. We note, however, that the IURC’s
further findings should be guided by the
Triennial Review
Order
, not the now invalid
That said, we observe that only in very limited circum- stances, which we cannot now imagine, will a state be able to craft a packet switching unbundling requirement that will comply with the Act. As stated by the FCC:
If a decision pursuant to state law were to require
the unbundling of a network element for which the
Commission has either found no impairment—and thus
has found that unbundling that element would conflict
with the limits in
Id. at *311, ¶ 195.
III. Conclusion
We A FFIRM the district court’s determinations as to tandem reciprocal compensation rates, dark fiber, new combinations of network elements, and packet switching on the grounds, and with the caveats, discussed above. We R EVERSE the district court’s determination on acceptance testing, reinstating that provision of the interconnection agreement as a valid exercise of state authority preserved under the Act.
A true Copy:
Teste:
________________________________ Clerk of the United States Court of Appeals for the Seventh Circuit USCA-02-C-0072—3-5-04
Notes
[1] The Telecommunications Act of 1996, Pub. L. 104-104, 110 Stat. 56 (1996) is codified as amended in scattered sections of Title 47, United States Code.
[2] The IURC actually arbitrated two agreements—one between AT&T Communications of Indiana, GP and Ameritech and the other between TCG Indianapolis and Ameritech. Both agreements are identical in all material respects and are challenged on identical grounds. For simplicity’s sake, we will follow the parties’ and district court’s lead and refer to the agreements at issue in the singular.
[3] The IURC Commissioners, although named in the underlying complaint for declaratory and injunctive relief and appealing separately here, provided no briefing or oral argument separate from AT&T’s. References in this opinion to AT&T as a party should also be understood to include the Commissioners.
[4] In the parlance of the Act, incumbent local telephone service
providers are called “incumbent local exchange carriers,” abbre-
viated “ILECs” or “incumbent LECs.”
[5] Similarly, new market entrants are commonly referred to as
“competing local exchange carriers,” abbreviated “CLECs” or
“competing LECs
.
”
See MCI Telecomms. Corp.
,
[6] Local exchange networks consist of local loops (the cables that connect telephones to switches), switches (computers that direct calls to their destinations), and transport facilities (equipment that directs calls between switches). Id. at 771.
[7] Rule 711(a)(3) reads in full: Where the switch of a carrier other than an incumbent LEC serves a geographic area comparable to the area served by the incumbent LEC’s tandem switch, the appropriate rate for the carrier other than an incumbent LEC is the incumbent LEC’s tandem interconnection rate.
[8] In refusing to arbitrate the providers’ interconnection agree- ment disputes, the Virginia State Corporation Commission stated that it could not apply federal standards as required by the Act in arbitrating interconnection agreements without potentially waiving its Eleventh Amendment sovereign immunity, which it did not have the authority to do. Virginia Arbitration Order , 17 FCC Rcd. at 27,045, ¶ 6.
[9] According to
[10] We note that on August 16, 2002, Verizon filed a petition seeking reconsideration of portions of the Virginia Arbitration Order , including the interpretation of Rule 711(a)(3). See Verizon’s Petition for Clarification and Reconsideration of July 17, 2002 Memorandum Opinion and Order , p. 23, available at http://gullfoss2.fcc.gov/prod/ecfs/ retrieve.cgi?native_or_pdf=pdf &id_ document= 6513288259. However, the FCC has not yet ruled on the petition, and the Virginia Arbitration Order remains in effect.
[11]
See In re Review of the
[12] As this case was going to press, the D.C. Circuit decided U.S. Telecom Assoc. v. FCC , F.3d ___, 2004 U.S. App. LEXIS 3960 (D.C. Cir. Mar. 2, 2004), which reviewed the legality of certain provi- sions of the Triennial Review Order , including the network modi- fication requirements cited above. The D.C. Circuit expressly upheld the Order ’s requirement that incumbents provide new entrants with routine network modifications that incumbents regularly undertake for their own customers, such as splicing dark fiber. Id . at ___, *58-59.
[13] After the FCC promulgated its initial regulations under the Act
in 1996, several parties filed petitions for review of those reg-
ulations in several different federal circuits. Under the Hobbs Act,
the Federal Courts of Appeals have exclusive jurisdiction over
challenges to FCC regulations.
See
[14] Other limitations delineated by the Supreme Court appear on the face of the interconnection agreement provisions in issue or are otherwise satisfied. For example, subsection 9.3.3 of the interconnection agreement addressing the combination of ele- ments not ordinarily combined specifically states that Ameritech shall perform the functions necessary to combine its network elements, but only if technically feasible and non-discriminatory. Although subsection 9.3.3 does not specifically mention payment for the combination efforts, that issue is clearly addressed else- where in the interconnection agreement. We also note that Ameritech argues that subsection 9.3.2.1 of the interconnection agreement addressing combinations of ele- ments ordinarily combined has also been called into question under Verizon . We leave it to the IURC to determine in the first instance whether this section comports with the Act as inter- preted by the Supreme Court.