Ims, P.C. v. Aida Alvarez, Administrator, United States Small Business AdministrationIms, P.C. v. Aida Alvarez, Administrator, United States Small Business Administration
IMS, P.C. (“IMS”), а corporation that provides architectural and engineering services, brought an action in the United States District Court for the District of Columbia to challenge the refusal by the Small Business Administration (“SBA”) to revise IMS’s participation term in the SBA’s section 8(a) program for socially and economically disadvantaged businesses. IMS’s dispute with the SBA arose after the passage of the Business Opportunity Development Reform Act of 1988, Pub.L. No. 100-656, 102 Stat. 38.53 (codified as amendеd at
The district court held that the SBA’s decision to include the January 1987 сontract in the section 8(a) program did not violate the agency’s regulations and dismissed the suit for failing to state a valid claim and, in the alternative, entered summary judgment on behalf of the SBA.
See IMS, P.C. v. Lader,
No. 96-23 (D.D.C. Feb. 12, 1996) (unpublished bench opinion) (“Bench Op.”). Because we find that IMS has failed to establish that the SBA violated
I. Background
In Deсember 1985, IMS was accepted into the Small Business Administration’s section
In late August 1986, th'e Engineering Department of the VA Medical Center in Bat>via, New York selected IMS to perform a small project. IMS claims, and the SBA offers no evidence to disprove, that IMS was chosen to perform the project after the VA orally solicited several small disadvantaged businesses to submit proposals. The Medical Center was apparently unaware that IMS was a section 8(а) program participant when it selected the company for the project. Accordingly, it was not until after the solicitation and selection of IMS that the project was designated a section 8(a) project.
In November 1988, Congress enacted the BODR Act, which modified the program term for section 8(a) program participants. The final rules implementing the changes required by the Act provided that program participants as of September 1, 1988, would be given a revised program term of “the greater of nine years from the date of the Participant’s first contract pursuant to section 8(a) or the Participant’s Fixed Program Participation Term (FPPT) expiration date, including any extension thereof, plus 18 months.”
In a letter dated December 14, 1988, the SBA informed Iqbal Singh, the president of IMS, that the BODR Act provided IMS with a revised term of participation in the section 8(a) program of nine years from IMS’s first contract under the program, which the SBA had determined to be IMS’s January 1987 contract with the VA. The letter requested that Mr. Singh sign and return the letter, which he did without objection.
Between 1989 and 1994, IMS contacted the SBA several times in an effort to change its program term. IMS claimed then, as it does now, that the VA contract was not the proper starting point of IMS’s section 8(a) program term because the contract was brought into the program only after the VA had engaged in a public solicitation for offers and selected IMS. The SBA maintained in each of its responses that it had found no basis for IMS’s contention that the VA contract was inappropriately brought into the program.
In August 1995, IMS submitted additional materials to the SBA in support of its continuing request to change its program term. 2 The SBA’s District Counsel, -Mollie Gaughan, reviewed the material presented by IMS and concluded that “[t]here is no evidence in the contract file to support the premise that solicitation was previously published” and, therefore, “the program participation date was properly established.” Memorandum from Mollie B. Gaughan, District Counsel, to Michael McHale, Deputy Administrator Minority Enterprise Development (Oct. 4, 1995). In response to Ms. Gaughan’s memorandum, the SBA’s Acting Deputy Associate Administrator, Michael McHale, wrote a memorandum in which he outlined his decision to reject IMS’s request to extend its program term. In his memorаndum, he noted: “The documentation provided by your office indicates that proper offer acceptance procedure was followed in taking the requirement into the 8(a) program.” Memorandum from Michael P. McHale, Acting Deputy Associate Administrator, to Millie B. Gaughan, District Counsel (Oct. 31, 1995). On November 1, 1995, Franklin Sciortino, SBA’s District Director for Buffalo, New York, wrote to Mr. Singh at IMS advising him that the Central Office had denied IMS’s request for a new participation term еxpiration date. See Letter from Frank J. Sciortino, District Director, to Iqbal Singh, President, IMS, P.C. (Nov. 1,1995).
In January 1996, IMS filed a complaint seeking judicial review of the SBA’s refusal to amend its section 8(a) program term and requesting injunctive relief to prevent the expiration of its term. On February 12,
II. Analysis
A. SBA’s Interpretation of the Regulations
IMS claims that SBA’s acceptance of the 1987 VA contrаct into' the section 8(a) program violated the SBA’s own rules and regulations, and therefore IMS’s term expiration dates based upon that contract must be set aside by this court. In particular, IMS alleges that the SBA’s decision to accept the contract into the section 8(a) program was contrary to its own regulation precluding acceptance of a contract that was previously the subject of a public solicitation.
See
This court has previously noted that it is a “well-settled rule that an agency’s failure to follow its own regulations is fatal to the deviant action.”
Mine Reclamation Corp. v. Federal Energy Regulatory Comm’n,
(8) SBA will not accept for 8(a) award proposed procurements not previously in the section 8(a) program if any' of the following circumstances exist:
(i) Public solicitation has already been issued for the procurement as a small business set-aside in the form of an Invitation for Bid (IFB), Request for Proposal (RFP) or a Request for Quotation (RFQ). Providence of a general intent to set аside, such as Procurement Information Notices (PIN’s), annual procurement forecasts or past procurements by set aside, is insufficient reasons [sic] to preclude the procurement from 8(a) consideration.
Id. IMS contends that this regulation prohibits the SBA from accepting into the section 8(a) program any contract for which a public solicitation has been issued. The company claims that the SBA violated this regulation when it admitted IMS’s 1987 contraсt with the VA into the section 8(a) program because the VA had issued an oral, solicitation that was the functional equivalent of a Request for Quotation and had selected IMS to perform the contract before the contract was accepted in the section 8(a) program. For this reason, IMS argues, its participation term in the section 8(a) program cannot be based on this contract.
The SBA presents a more restrictive reading оf the regulation. Under its interpretation, which is entitled to substantial deference,
see Lyng v. Payne,
We find the SBA’s interpretation of
Because the SBA’s more restrictive interpretation of
B. The Arbitrary and Capricious Claim,
In its motion for summary judgment, IMS contended that the SBA’s failure to correct IMS’s program term was arbitrary, capricious, and contrary to law. The company claimed that the SBA had not examined the relevant data or articulated a satisfactory explanation for its action. It further alleged that there was no rational connection between the facts and the choice SBA made. In response, in its motion to dismiss, or in the alternative, cross motion for summary judgment, the SBA claimed thаt its refusal to change IMS’s term in the section' 8(a) program was based upon a rational evaluation of the facts and therefore was not arbitrary, capricious, or contrary to law. It noted that the SBA had notified IMS of its revised program term in 1986 and that IMS had acknowledged that decision without objection. The SBA further claimed that when IMS raised objections to its program term several years later, SBA officials carefully reviewed IMS’s factual allegations but concluded that they were inconsistent with specific documents in the SBA’s files.
5
The
Because we affirm thе district court’s ruling that the SBA did not violate
C. The Supplemental Affidavits
IMS submitted four affidavits to the district court in support of its Request for a Temporary Restraining Order and its Motion for Summary Judgment. 7 IMS claimed that the affidavits, while not contained in the agency record, merely elabоrated on information that was in the record and should therefore be permitted. The district court granted SBA’s motion to strike the affidavits. We affirm the district court’s decision.
It is a widely accepted principle of administrative law that the courts base their review of an agency’s actions on the materials that were before the agency at the time its decision was made.
See Puerto Rico Higher Educ. Assistance Corp. v. Riley,
Both parties agree that the affidavits submitted by IMS were not available to the SBA at the time it made its decision regarding IMS’s participation term. IMS claims, however, that the district court should have considered the affidavits as part of the administrative record because they merely elaborated on details already included in the record. In addition, IMS argues that “even if the affidavits constituted extraneous evidence, they still should have been considered by the Court under various exceptions which permit supplementation of the administrative record.” Appellant’s Brief at 23.
We find no legal support for IMS’s assertions. Even if IMS were correct in its claim that information that elaborates on details already in the record could be considered by the court, the affidavits in question could not be considered because they provide significant new information about thе circumstances surrounding the 1987 contract that is not available in the administrative record. Moreover, the affidavits do not appear to fall within any of the accepted exceptions to the principle that the court cannot consider information that falls outside the agency record. As the district court concluded, IMS has not demonstrated that the-agency failed to examine all relevant factors or to adequately exрlain its grounds for decision, or that the agency acted in bad faith or engaged in improper behavior in reaching its decision. This is not a case where the agency failed “to explain administrative action [so] as to frustrate effective judicial review.”
Pitts,
The affidavits contain information that should have been submitted to the agency before this disрute reached the courts. To-allow the affidavits to be considered now would be to permit
ex post
supplementation of the record, which is not consistent with the prevailing standards of agency review.
See AT&T Info. Sys. v. General Serv. Admin.,
III. Conclusion
For the foregoing reasons, we hold that IMS has failed to establish thát the SBA’s acceptance of IMS’s 1987 contract with the VA into the section 8(a) program violated federal regulations. We also hold that the district court properly excluded the supplemental affidavits that the appellant filed in support of its claims on the basis that they were not part of the administrative record. The district court’s decision granting the SBA’s motion for summary judgment is therefore
Affirmed.
Notes
. The district court clearly relied on materials outside the pleadings in ruling on the motion to dismiss.
See
Bench Op. ("I don’t see any history developed that that really is not what they meant and not how they practiced. That’s been argued, but I don't see that in the administrative record. I don’t see any interpretations or opinions offered that that's not what it means.”). Under
. The materials included affidavits from Mr. Singh and VA employee Janet Kline describing how the VA had conducted the procurement that led to the contract with IMS in 1987.
. This court rejects the SBA’s contention that under
. Because we find that the SBA’s reading of
. The SBA’s memorandum of points and authorities in support of its motion cited three separate reviews of IMS’s request by SBA officials. One review was conducted in September 1995 by Betty Perno, the Assistant Director for the 8(a)
. See Memorandum from Mollie B. Gaughan, .District Counsel, to Michael McHale, Deputy Administrator Minority Enterprise Development (Oct. 4, 1995), at 3.
. The affidavits were: (1) Affidavit of Iqbal M. Singh (Jan. 5, 1996) (with attachments); (2) Supplemental Affidavit of Iqbal M. Singh (Jan. 17, 1996) (with attachments); (3) Affidavit of Janet Kline (with attachment) (Jan. 17, 1996); (4) Statement of Albert Iamicelli, a VA employee familiar with the 1987 contract (Jan. 16, 1996).