Lead Opinion
Mаgnetic Resonance Plus, Inc. (“MRP”) sued North Georgia Diagnostic Imaging, Ltd. and its managing agent Imaging Systems International, Inc. (collectively “NGDI”) for breach of contract arising out of NGDI’s prematurely terminating its contract with MRP. Following a bench trial, the judge awarded MRP damages equal to MRP’s anticiрated profit on the contract, despite a contract provision prohibiting MRP from recovering “any lost profits.” We hold that the contract provision precluded the award and reverse.
On March 23, 1994, NGDI entered into a three-year contract with MRP for MRP to service and repair NGDI’s magnetic resonance imaging (“MRI”) equipment in Atlanta. After a period of months, NGDI became dissatisfied with MRP’s performance and terminated the contract “effective immediately,” despite a contract provision requiring that NGDI give MRP a 30-day written notice to cure befоre termination. NGDI would not allow MRP back on the premises to service the MRI. Protesting this action, MRP nevertheless offered to rescind a related contract and refund monies paid thereunder if NGDI returned certain equipment, which NGDI did. MRP, however, refused to refund the monies. When MRP sued NGDI for breаch of contract, NGDI counterclaimed for the unrefunded monies.
1. The contract provides: “5.1 LIMITATION OF LIABILITY NEITHER THE CUSTOMER NOR MRP WILL BE LIABLE TO EACH OTHER OR ANY OTHER PARTY FOR ANY LOST PROFITS OR ANY INCIDENTAL, SPECIAL, OR CONSEQUENTIAL DAMAGES RELATING TO THIS AGREEMENT.” NGDI contends that this provision prohibits MRP from recovering the profits it would have received had it been allowed to perform under the contract. Clearly it does.
“The construction of a contract is a question of law for the court.” OCGA § 13-2-1.
Where a party sues on a terminated executory contract, the damages are similar to those recoverable by a contractor suing on a terminated construction contract. See Franklin v. Demico, Inc.,
Following this formula, the trial court reviewed MRP’s evidence concerning the expenses it saved and found MRP did not prove some key variable costs. Relying instead on a letter in which MRP projected its net profit to be between five and ten percent, the trial court concluded that MRP’s “profit would have been $21,584.37, which is 10% of the remaining payments for service (i.e., $215,843.75),” and this became the award to MRP. Because the contract specifically prohibited the recovery of “any lost profits,” this award was error.
MRP claims that the lost profits prohibited by the contract are “profits lost by the rest of [MRP’s] business that arise as a consequence of the other party’s breach of one particular contract, such as the loss of goodwill to the company, the resulting loss of other business contracts or clients, the loss of other business opportunities, and other consequential losses.” Citing Redman Dev. Corp. v. Piedmont Heating &c.,
MRP’s arguments fail. First, the loss of other business opportunities, other profits and goodwill falls squarely within the meaning of consequential losses, which are separately listed in the contract as other kinds of damages and are also prohibited. See OCGA § 13-6-8; American Car Rentals v. Walden Leasing,
Second, even though this contract provision may severely if not completely restrict MRP’s ability to recover for this breach of contract, parties are free to agree to such provisiоns. “Absent a public policy interest, contracting parties are free to contract to waive numerous and substantial rights, including the right to seek recourse in the event of a breach by the other party.” (Citations and punctuation omitted.) Piedmont Arbors Condo. &c. v. BPI Constr. Co.,
Provisions severely restricting remedies act as exculpatory clauses and therefоre “ ‘should be explicit, prominent, clear and
Moreover, the contract also prohibits the recovery of “special damages” relating to the agreement. Special damages arе “those which actually flow from a tortious act.” OCGA § 51-12-2. “[E]ven though the statutory definitions of general and special damages (see OCGA § 51-12-2 (a) and (b)) refer to tortious acts, general and special damages also may be recovered in contract actions if the general and special damages are not remote or consequential (OCGA § 13-6-8) and ‘are such as arise naturally and according to the usual course of things from such breach and such as the parties contemplated, when the contract was made, as the probable result of its breаch.’ OCGA § 13-6-2.” Bill Parker & Assoc. v. Rahr,
The award of $21,584.37 to MRP is vacated. Because the trial court awarded attorney fees based on its award of lost profits to MRP, the attorney fees award to MRP is also vacated.
2. In light of the holding in Division 1, the other enumerations of error, all of which go to the calculation of the damages awarded to
3. On remand, the trial court may not award MRP nominal damages, for MRP did not ask for nominal damages in the pre-trial order nor at trial. See Ackley v. Strickland,
Judgment affirmed in part and reversed in part and remanded with direction.
Notes
Even though the agreement states that it is to be construed in accordance with the laws of the United States and the State of California, no party has pled California law. OCGA § 9-11-43 (c). Nor is there a federal statute on the general construction of contracts. Accordingly, this Court applies the law of the State of Georgia. Avnet, Inc. v. Wyle Laboratories,
The contract in American Car Rentals v. Walden Leasing, supra, defined the only lost profits at issue there as consequential damages. The court in that case did not address whether, absent this limiting definition in the term, “lost profits” would also include direct damages that represent the benefit of the bargаin. See also Hixson-Hopkins Autoplex v. Custom Coaches,
Redman was overruled to the extent it misstated the correct measure of damages. Crankshaw v. Stanley Homes,
Any ambiguity in an exculpatory clause is construed against the drafter. Altama Delta Corp. v. Howell, supra,
Dissenting Opinion
dissenting.
I respectfully dissent. I would affirm the judgment because, in my view, the contract provision prohibiting the recovery of lost profits does not preclude the recovery sought by MRP.
I agree with the majority that the measure of damages applicable for breach of contract in this case is similar to that used when a contractor brings an action for breach of a construction contract. That measure is the unpaid contract price less the amount saved by the contractor as a result of the breach — the contractor’s costs involved in completing the contract. Williams v. Kerns,
Paragraph 5.1 of the contract prohibits only liability for “lost profits or any incidentаl, special, or consequential damages.” The term “lost profits” is a term of art. It has often been used in contracts to mean a particular type of consequential damages. See, e.g., American Car Rentals v. Walden Leasing,
The contract provision in issue here did just that. But the loss of MRP’s “anticipated” or “expected” profit is a direct result of NGDI’s terminating the contract рrematurely. It is therefore recoverable. I would affirm the judgment.
I am authorized to state that Judge Eldridge joins in this dissent.
Crankshaw, supra, overruled Redman Dev. Corp. v. Piedmont Heating &c.,
