215 F. 334 | 4th Cir. | 1914
This suit was commenced on March 4, 1913, under the act of Congress of August 13, 1894, as amended February 24, 1905, which gives to subcontractors under certain conditions a right of action upon the bond of a contractor for the erec-. tion of a public building. For convenient reference the material parts of this statute are reproduced in the margin.
“By this statute a right of action upon the bond is created in favor of certain creditors of the contractor. The cause of action did not exist before, and is the creature of the statute. The act does not place a limitation upon a cause of action theretofore existing, but creates a new one upon the terms named in the statute. The right of action given to creditors is specifically*337 conditioned upon the fact that no suit shall be brought by the United States within the six months named, for it is only in that event that the creditors shall have a right of action and may bring a suit in the manner provided. The statute thus creates a new liability and gives a special remedy for it, and upon well-settled principles the limitations upon such liability become a part of the right conferred, and compliance with them is made essential to the assertion and benefit of the liability itself. * * * The right to intervene is given in the statute when the action is brought by the United States, and the creditors may have their rights adjudicated in such action. And in the case of an action begun by a creditor in accordance with the statute, the right to file a claim is given to creditors. These rights to intervene and to file a claim, conferred by the statute, presuppose an action duly brought under its terms. In this case the cause of action had not accrued to the creditors who undertook to bring the suit originally. The intervention could not cure this vice in the original suit. * * “ No service was made or attempted to be had upon it, as required by the statute when original actions are begun by creditors. As we read the certificate, the intervention was what, it purported to be—an appearance in the original suit, already brought, and in our view must abide the fate of that suit.”
In the case at bar the facts relating to the commencement of the action are'these: The work required of the contractor appears to have been practically completed some time in June, 1912. The supervising architect so reported in a communication to the secretary of the treasury, under date of August 21, 1913, which contains “a condensed statement of the account,” including contract price, additions, and deductions made from time to time, payments on account, and charges of actual damages for delay, and recommends that authority be given “for the issue and payment of a voucher” in favor of the • contractor for S3,399.01, the balance found due to him. On the same date this statement and recommendation were approved by the assistant secretary of the treasury. Under date of August 23, the contractor was notified of the amount so stated and determined to be due him, and that authority had been given for a voucher in his favor for the ascertained balance, and he acknowledged the same two days later by letter to the supervising architect. The voucher was issued on August 26th, and he signed his approval thereof on or about that date. The check in payment was drawn on the 11th of September, and paid on the following day. This check, as will he seen, was issued and paid less than six months before the suit was commenced, and if that be the date of the “completion and final settlement” of the contract, within the meaning of the statute, the action was prematurely brought and cannot be maintained.
But we are clearly of opinion that the final settlement in this case was effected on or before the 26th of August, when the contractor signed the voucher which bears that date, and in which he certified “that the above bill is correct and just and that payment therefor has not been received.” Surely, nothing then remained to be settled. Indeed, there is no indication in the record that anything had been in dispute between the contractor and the government. There was no disagreement as to the additions to the work for which he was entitled to additional pay, or as to deductions for items not furnished. Under the penalty clause of the contract, the government had the right to make a further and large deduction for delay in completing the
This accords with the construction of the statute by the treasury department, as appears from a regulation which reads as follows:
“The- department treats as the date of final settlement mentioned in said acts the date on which the department approves the basis of settlement under such contract recommended by the supervising architect, and orders payment accordingly.”
We have discovered only two cases under this statute which bear directly upon the point here considered, and both of them give support to the views above expressed. United States v. Winkler (C. C.) 162 Fed. 397; United States v. Bailey (D. C.) 207 Fed. 782. In the latter case, District Judge Bourquin, after reciting the steps taken in the adjustment and settlement of contractors’ accounts, uses the following language: •
“When this is done, and not until then, in respect to government contracts performed, there is final settlement thereof, though further time be necessary for mere ministerial acts, to issue and deliver warrants. In no other wise can there be final settlement of.contract obligations of the United States, and this is the final settlement contemplated by the Act February 24, 1905, aforesaid. And, from the date of said auditor’s settlement and certificate forthwith as the evidence thereof, the limited time within which actions like unto this must be commenced begins to run.”
We are unable to.see any substantial reason why the discretionary power of the court to allow amendments could not be exercised because the time within which the,suit could he begun had then elapsed. The suit was in fact commenced, as we hold, more than six months and less than a year after the final settlement referred to in the statute. At that time a complete cause of action under the act existed in favor of the plaintiffs. By some mistake or inadvertence they failed, as we will assume, to set forth in their complaint all the facts necessary to establish their cause of action, although the omitted facts actually existed. Why should they be deprived of the benefits conferred by this statute, when their action was seasonably brought and the facts entitled them to recover, merely because through some mischance certain of those facts were omitted from their complaint? Why should not the court permit the omissions to be supplied, and upon what sustainable theory-can it be said that the court was powerless to grant relief after the time limited for commencing the action had expired? The amended complaint sets up no new cause of action, and alleges no facts which were not in existence when the suit was begun; it merely supplies omissions and corrects defects in the original complaint. If the suit had been prematurely brought, or brought too late, the court would have been without jurisdiction, because under those circumstances the plaintiffs would not be within the conditions of the statute, and therefore could not avail themselves of its provisions; and no amendment would be of value in that case because there would be nothing to amend, as the Supreme Court says in the recent case above cited. But this suit was commenced within the period allowed by the act, and the right of recovery depends upon the state of facts which existed at that time. It is elementary that an amendment dates back to the beginning of the suit and is designed to cure defects in the statement of the cause of action then existing, and there is abundant precedent for permitting amendments of that character and for that purpose, to the end that errors or mistakes of pleading may not result in a miscarriage of justice. In our judgment the amendments in question were properly allowed under the provisions of sections 954 of the Revised Statutes and the authority of M., K. & T. Ry. v. Wulf, 226 U. S. 576, 33 Sup. Ct. 135, 57 L. Ed. 355.
We agree with the trial court that the incorporation of the Carolina Electric Company and the Electrical Engineering & Contracting Company was sufficiently proved by the certificates received in evidence. There was no dispute as to the fact'or amount of -the contractor’s indebtedness to the former company, and the obligation of the plaintiff in error to pay the same was properly established. The direction to pay the sum found due “to such person as may be authorized by law to receive it” gives adequate protection to the plaintiff in error and appears to be a suitable disposition of the case in that regard.
For the reasons thus briefly stated, the judgment is affirmed.
“If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall, upon application therefor, and furnishing affidavit to the department under the direction of which said work lias been prosecuted that labor or materials for the