Illinois Surety Co. v. United States Ex Rel. PeelerIllinois Surety Co. v. United States Ex Rel. Peeler
delivered the opinion of the court.
This action was brought by sub-contractors under the Act of August 13, 1894 (c. 280, 28 Stat. 278), as amended by the
Act
of February 24, 1905 (c. 778, 33 Stat. 811), in the name of the United States to recover upon, a contractor’s bond. The contract was for the construction of a post-office building in Aiken, South Carolina (Act. of March 30, 1908, c. 228, 35 Stat. 526,. 528), and the Illinois Surety Company (plaintiff in error) was the surety. The summons and complaint were filed on March 4, 1913. Motion to dismiss was made on September 22, 1913, upon the ground that the complaint did not allege that there had been a completion arid final settlement of. the qontract between the contractor and the United States; or that there had been such, completion and settlement more than six months, and within one. year, prior to the commencément óf the action.
That the building was completed, and on August 21, 1912, the Treasury Department “stated and determined the final balance” to be paid the contractor under the contract at.the sum of $3,999.01; that this “adjustment and determination” was communicated to the contractor; that on August .26, 1912, a voucher of that date was prepared by the Department showing the balance, as above stated, to which the contractor appended his signature certifying the amount to be correct, and that on that day there was a definite acceptance by the cpntractor of the adjustment; that on September 11, 1912, a check for the above-mentioned sum was made out by the disbursing clerk of the Department, payable to the order of the contractor, who thereafter collected it; that upon the request of the relator (the Faith Granite Company) the Secretary of the Treasury, on January 16, 1913, furnished to it a certified copy of the contract and bond and that on the sixth day of March, 1913, . . . the present action was instituted by the filing . . . and by service of summons and complaint on defendant Surety Company.” It also appeared that no action had been instituted by the United States upon the bond within the six months allowed by the statute.
1. The statute provides, p. 812: “If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall, upon application therefor, and furnishing affidavit ... be furnished with a certified copy of said contract and bond,, upon which he or they shall have a right of action, and shall be, and are hereby, authorized to bring suit in the name* of the United States . . . against said contractor and his sureties, and to prosecute the same to final judgment ,and execution;
Provided,
That . . . it shall not be commenced until after the complete performance of said contract and final settlement thereof, and shall be commenced within one year after the performance and final settlement of said contract, and not later.” In
Texas Cement Co.
v.
McCord,
1
233 U. S, 157, we said that this act created a new right of action upon terms named; and hence that an action brought by. creditors before six months had expired from the time of the ‘completion and final settlement of the contract’ coüld not be sustained. In the present case, the plaintiff in error insists that there 'was no final settlement within the meaning of the statute prior to the issue of the check
It was evidently the’ purpose of the Act of 1905 to remedy the defect in the Act of 1894 by assuring to the United Státes adequate opportunity to enforce its demand against the contractor’s surety and priority with respect to such demand.
Mankin
v.
Ludowici-Celadon Co.,
The pivotal words are not ‘final payment,’ but ‘final
We should not say, of course, that instances may not be found in' which the word ‘settlement’ has been used in acts of Congress in other senses, or in the sense of ‘payment.’ • But it is apparent that the word ‘settlement’ in connection with public contracts and accounts, which are the subject of prescribed scrutiny for the purpose of ascertaining the rights and obligations of the United States, has a well defined meaning as denoting the appropriate administrative determination with respect to the amount due. We think that the words ‘final settlement’ in the Act of 1905 had reference to" the time of this determination when, so far as the Government was concerned, the amount which it was finally bound to pay or entitled to receive was fixed administratively by the proper authority. It is manifestly of the utmost importance that there should be no uncertainty in the time from which the six months’ period runs. The time of the final administrative determination of the ámount due is a definite time fixed by public record and readily ascertained. As an administrative matter, it does not depend upon the consent or agreement of the other party' to the contract or account. The authority to make it may not be suspended,- or held in abeyance, by refusal to agree. Whether the amount so'fixed is due, in law and fact, undoubtedly remains a question to be adjudicated, if properly raised in judicial proceedings, but this does not affect the running of the time for bringing action under the Statutory provision. ■
In the present case, the construction of the building was in charge of the Secretary of the Treasury and under the general supervision of the Supervising Architect. The Secretary of the Treasury was authorized to remit the whole or any part of the stipulated liquidated damages as in his discretion might be just and equitable, Act of
We conclude that the action was . not brought prematurely.
2.. With respect to the amendment of -the complaint, it is apparent that-as there was an existing right of action under the statute at th.e time the suit was brought, the case was not within the decision, in
Texas Cement Co.
v.
McCord, supra.
No new or different cause of action was alleged in the amended complaint. . The court merely permitted the defective statement of the existing right to .be corrected by the addition of appropriate allegations,
3. It is contended that the' right given by the statute to the described creditors is of an equitable nature, and that the court erred in permitting recovery at law. The objection in the present case is merely technical, as the parties Stipulated to waive trial by jury and the case was heard and decided by the district judge upon facts'-about which there is no dispute. . The question has not been raised heretofore in this court, but it has been assumed in many cases that the action to be brought under the statute upon the contractor’s bond, whether the action were .instituted by the United States
(United States
v.
Congress Construction Co.,
222 U. Sr 199) or by creditors in the name of the United States, was an action at law.
United States Fidelity Co.
v.
Struthers Wells Co.,
The statute provides that the bond shall have “the additional obligation that such contractor' or contractors shall promptly make payments to all persons supplying him or them with labor , and materials in the prosecution of the work provided for in. such contract.” In this-respect, the provision is substantially the same as that contained in the Act of 1894, and the obligation in'favor of the materialmen and laborers has been held to bé a distinct obligation.
Guaranty Co.
v.
Pressed Brick Co.,
It should be added that a different situation would arise if the surety, availing itself of the statutory privilege, should pay into court the full amount of its liability, to wit, the penalty on the bond, for distribution. In that case the legal obligation of the surety would be discharged by the express terms of the statute and the proceeding would be simply for the distribution of a fund in court.
4. The plaintiff in error contends that the court erred in giving judgment in favor of the Carolina Electrical Company. The record shows that among those named as the persons instituting the action was the “Electrical
In this, we think the court, érred. The Carolina Electrical Company was not one.of the plaintiffs and there was no intervention on its behalf. The trial court in its findings, sets forth the-interventions of.certain other parties' and states that no morb interventions appear to have been filed in the cause. (It is true, of course, that the real, party in interest who is entitled to enforce the cause of action may be substituted' as plaintiff. See
McDonald
v.
Nebraska,
101 Fed. Rep. 171, 178. But the present case is not one of misnomer, or of a nominal plaintiff for whom the real party in interest is substituted, or indeed of any proper substitution. The plaintiff, the- Electrical" En
The judgment is modified by- striking out the provision in favor of the Carolina Electrical Company, and as thus modified is affirmed.
Judgment affirmed.
Notes
The statute is set forth in full in the margin of the opinion in the ease cited.