160 Ky. 139 | Ky. Ct. App. | 1914
Opinion of the Court by
Reversing.
In December, 1911, plaintiff, Ernest Seibold, a car repairer, was , struck and injured by a wrench which he charged was negligently permitted to fall upon his head and shoulders by another employe of the defendant on another train. Subsequently he amended his petition and made the other employe a party defendant, and also alleged that the defendants were engaged, and he himself was employed, in interstate commerce at the time of the injury. A jury was empanelled and evidence heard, and what thereafter took place is best shown by the following order entered by the trial court:
“At the conclusion of the testimony for the plaintiff, defendant, Illinois Central Railroad Company, by counsel, moved the court to peremptorily instruct the jury to find a verdict for it, to which the plaintiff objects.
‘ ‘ The court being advised, ordered said motion be and is sustained, to which the plaintiff excepts.
“At the conclusion of the evidence for the plaintiff, the defendant, Illinois Central Railroad Company, moved the court to instruct the jury peremptorily to find a verdict in its behalf, to which motion plaintiff objected, and .after argument and while said motion was under consideration the plaintiff moved the court to withdraw and dismiss without prejudice so much of plaintiff’s action as sought a recovery under the Federal Employers’ Liability Statute, to which withdrawal and dismissal without prejudice the defendant, Illinois Central Railroad Company, objected and the court overruled its objections and sustained plaintiff’s said motion and so much of said- action as seeks recovery under the Federal statute
“Thereupon, the court being advised, sustained defendant’s motion to peremptorily instruct the jury to find a verdict for the defendant, Illinois Central Railroad Company, upon the issues remaining in the case, and instructed the jury accordingly in these words:
“ ‘After a careful consideration of the arguments advanced by counsel, on the state of facts as made by the plaintiff, in his proof here, the court is satisfied that the plaintiff has not sustained the burden which the law places upon him to show certain facts. So much of plaintiff’s action as asserts his right of recovery under the Federal statute has been withdrawn by the plaintiff. As_ the amendment which asserted that right, and which brought in Mr. Ben Flood as a defendant in this case, was filed more than a year after the time the injuries complained of were received, and as the plaintiff has undertaken to withdraw from the consideration of the court and the jury his rights under that statute, it necessarily follows that Mr. Flood, who could not be sued, except within a year’s time, must go out of the case, and the court therefore instructs you peremptorily, for that reason, to find in his favor. As to the right of the plaintiff to recover under the State law, the court, after careful consideration, is satisfied that the plaintiff has not sustained the burden placed upon him by law, and it is. my duty, in view of that fact, to instruct you peremptorily,' also to find in favor of the defendant, the I. C. R. R. Co.’
“To which the plaintiff excepted and after the verdict had been written out by the clerk in these words:
“ ‘We, the jury, under peremptory instructions from the court, find for the defendants, Illinois Central Railroad Company and Ben Flood.’
“And while it was being signed by Herman Ohmann as foreman, and as the clerk was waiting for the foreman’s signature to be completed, the plaintiff moved the court to dismiss the action without prejudice as to •the issues submitted to the jury under above instructions, to which motion the defendant, Illinois Central Railroad Company, objected, and it moved the court to. receive the verdict and to dismiss said action absolutely,,,
“The court, on motion of defendant, Illinois Central Railroad Company, now enters upon the record fully the matters above set forth for use on appeal.
Judgment.
“It is therefore now adjudged in accordance with the motions aforesaid by the plaintiff that his action be dismissed without prejudice and that the defendants, Illinois Central Railroad Company and Ben Flood, each separately recover herein against the plaintiff, Ernest Seibold, its or his costs herein expended, and may have execution therefor.
“To so much of the order and judgment herein entered as denies the motion of the Illinois Central Railroad Company to receive the verdict of the jury, and to dismiss said action absolutely, and as provides for a dismissal of said action without prejudice, upon the motion of the plaintiff, the Illinois Central Railroad Company, objects and excepts and it prays an appeal to the Court of Appeals, which is granted.”
Section 371, Civil Code, provides:
“An action, or any cause of action, may be dismissed without prejudice to a future action.
“1. By the plaintiff, before the final submission of the case to the jury, or to the court, if the trial be by the court.
“2. By the court—
“a. If the plaintiff fail to appear at the trial.
“b. For the want of necessary parties.
“c. On the application of a defendant, if there he others whom the plaintiff fails to prosecute with diligence.
“d. For disobedience by the plaintiff of an order coneering the proceedings in the action.
“In all other cases, upon the trial of the action, the ¿decision must be upon the merits.”
“If the jury had left their seats for their room for a deliberation, it is clear that there would have been a ‘final submission.’
“In the case at bar the jury was not allowed to go to a room. On their part there was to be no deliberation. Plaintiff’s counsel heard the reasons given by the court why in his opinion no case had been made. He then heard the direction to one of the jurors to sign the verdict. He saw the foreman walk forward to sign, and then, when the foreman was signing, for the first time suggested a purpose to dismiss. And in the case at bar I can see no difference whatever between what in fact was going on and if the jury had among themselves in the jury box, or in a room, had directed the foreman to sign and he was in the act of signing when the dismissal was moved. * * *
“I fail to see what more there was to be done in the case at bar, except for the jury or someone for them to announce the verdict they were directed to return; and, that being so, I believe the case had been finally submitted when the motion to dismiss was made. It was then too late.”
In the case of Dobkins v. Dittmers (N. J.), 69 Atl., 1013, the court, after argument on a motion for a directed verdict, sustained the motion and instructed the jury to find for the defendant, whereupon plaintiff moved for a non-suit. The court held that the motion for non-suit came too late. In the course of the opinion, the court said:
“The common law right of a plaintiff to submit to a voluntary non-suit at any time before the final rendition of the verdict has been contracted by the 160th section of.
“On the facts submitted in the present case the situation is the same, in contemplation of law, as if the jury, after receiving the charge of the court, had conferred together without leaving the box, and announced to the court that they had agreed upon their verdict. The jury have gone from the bar, within the meaning of that phrase in the statute, when they have actually entered upon the consideration of their verdict, whether such action takes place within the precincts of the court room or in some other place provided for their use. Under the practice prevailing at common law the plaintiff was enabled to take advantage of knowledge acquired by him as to the result of the deliberation of the jury by permitting them to render their verdict in case it was in his favor, and preventing them from doing so in case it was adverse to him. Undoubtedly, one of the purposes of the Legislature in the curtailing of this power was to prevent a plaintiff from depriving a defendant of the benefit of a verdict which had been found in his favor. To hold he may still do so, unless the members actually walk out of the presence of the court before agreeing upon their verdict, is to emasculate the' statute.”
In the case under consideration the court had sustained the motion for a peremptory. The following verdict had been written out: “We, the jury, under peremptory instructions from the court, find for the defendants, Illinois Central Railroad Company and Ben Flood.” One of the members of the jury had been directed to act as foreman and sign the verdict. We therefore conclude that there had been a final submission of the case to the jury within the meaning of the code.
But counsel for plaintiffs insist that the code provision simply limits the time within which the plaintiff may as a matter of right dismiss the action without prejudice, and does not prevent the trial court from exercising a reasonable discretion in the matter. It is true that the Kansas and Arkansas courts so hold. Dickerman v. Crane, 57 Pac., 305; Ashmead v. Ashmead, 23 Kas., 262 ; St. Louis, S. W. R. Co. v. White Sewing Machine Co., 69 Ark., 431, 64 S. W., 964. The foregoing cases proceed upon the idea that counsel for the plaintiff may, through
“It is too late after submission to enter such a motion.”
Manifestly, if it is too late after submission to enter such a motion, the trial court is without discretion to entertain or pass on such a motion. This view does not conflict with the rule announced in the case of Williamson v. Am. Reserve Bond Co.’s Receiver, 140 Ky., 215, and Wilhelm’s Ex’r. v. Bains, 147 Ky., 832. In each of those cases there had been a premature submission, and we held that the trial court did not abuse its discretion in allowing the submission set aside, and the action dismissed without prejudice. It follows that the trial court should have sustained the motion of defendants to receive the verdict of the jury, and to dismiss the action absolutely.
Judgment reversed and cause remanded with directions to dismiss the petition.