delivered the opinion of the court.
This action, brought to recover damages for injuries inflicted by defendant to plaintiff’s underground telephone cable, was tried without a jury, by the circuit court of Winnebago county, resulting in a judgment for the defendant, and the plaintiff appeals.
The evidence disclosed that the plaintiff is a public utility engaged in the telephone business in Eockford, Illinois. On August 16, 1948, the Rockford City Council issued to it an ordinance permit granting to the plaintiff the right to place buried cable in the parkway along Eural Street in the City of Rockford. Pursuant to this authority, plaintiff placed a cable consisting of twelve hundred pairs of individual wires protected by insulation and a jute covering at a depth varying from thirty to thirty-six inches and maintained this cable in good condition.
Defendant is a corporation engaged in construction work of various kinds and has operated in Rockford for many years. In the summer of 1950 it operated six crews and was engaged to do certain work in connection with the laying out of a new addition north of Rural Street in Rockford. Its work, among other things, included the laying out and grading of streets and the installation of a sanitary sewer in Bohm Court, a street lying north of Eural Street. This storm sewer was to run from a manhole south of Rural Street in the parkway along the west curb of Bohm Street and to and across Rural Street. On and prior to September 15, 1950, defendant operated a ditch-digging excavating machine known as a “hoe.” On the evening of September 15, 1950, it moved this hoe to a place near the manhole in Bohm Street and left it there overnight. Previous to this time and during the day of September 15, 1950, the city engineer’s surveying crew of the City of Rockford placed engineering stakes in the parkway along Bohm Street indicating where the trench which defendant was to dig was to be dug, and on the stakes marks were placed indicating the depth at which the excavation was to be made. On September 16, 1950, defendant commenced the excavation, after breaking the cement around the manhole, and had proceeded about six hundred feet, following the grade lines and stakes, when the trench hoe came in contact with plaintiff’s cable and inflicted the damage to recover for which this action was instituted.
The evidence further discloses that the plans for this storm-sewer excavation were drawn by the city engineer of Rockford and during the latter part of July 1950, were handed to Charles Ind, president of defendant company. This plan showed the line of excavation and the depth to which the trench was to be dug but did not show any telephone cable or conduit. It further appears that after the underground cable was installed by appellant in 1948 the parkway was filled and seeded to grass, and there was no evidence on the surface of the ground that would indicate there was any telephone cable below the surface. Emery McKinney, an employee of appellee, operated the trench hoe in making this excavation, and he testified that he noticed nothing which would indicate the location of this telephone cable. Charles G. Ind, Jr., was superintendent on this job for the defendant, but it appears that he died prior to the trial of this action.
The complaint in this cause was filed on March 12, 1952, and consisted of three counts. The first count is based on the theory that the defendant was absolutely liable to the plaintiff and, as amended, alleged that the plaintiff was a public utility and on August 19, 1948, was granted written permission by the City of Rockford, as set forth in Ordinance Permit No. 50, to permanently place buried cables in a described parkway on the south side of Rural Street and in the vicinity of the intersection of Bohm Avenue and Rural Street in the City of Rockford, and that plaintiff, during the year 1949, installed a permanent 1212 pair, 24 gauge, jute-protected cable at the described location at a depth of approximately three and one-half feet under the ground surface. This count then alleged that defendant is a private corporation engaged in construction work and organized under the laws of Illinois; that it became its duty to refrain from using its excavating equipment in a manner which would injure or damage plaintiff’s underground property as aforesaid; that disregarding its duty, defendant, while excavating a storm-sewer trench for and on behalf of the private owner of adjacent property, injured said cable, and as a direct and proximate result thereof, plaintiff sustained damage to the amount of $2,182.28, the actual cost to the plaintiff of repairing said cable.
Count two was in trespass quare clausum, fregit and charged, among other things, that the defendant, with force and arms, on September 16, 1950, entered the close of the plaintiff and there operated a digging machine so as to cut and damage plaintiff’s cable to the plaintiff’s damage. The third count charged the defendant with negligence and, as amended, re-alleged the installation of this cable by the plaintiff, as set forth in the other counts. This count then averred that the plaintiff was at all times in the exercise of due care and caution for the safety of its property and charged that on September 16, 1950, defendant was engaged in excavating a storm-sewer trench at the described location; that it thereupon became the duty of defendant to refrain from negligently injuring plaintiff’s property; that defendant disregarded that duty and carelessly, negligently, and improperly operated its excavating machine over the area of plaintiff’s cable after having knowledge of its presence, or without having ascertained from the office of the city engineer of Rockford the location of said cable, or without having ascertained from the local office of the plaintiff the location of said cable after having been notified by plaintiff in writing so to do, or that defendant failed to inspect the area to be excavated in order to determine the existence of said cable. This count then concludes that as a direct and proximate result of said negligent conduct on the part of the defendant, defendant, while excavating at the described location, operated its digging machine so as to damage the cable of the plaintiff.
The trial court sustained defendant’s motion to dismiss counts one and two, and defendant filed an answer to count three and two affirmative defenses. The answer of the defendant to count three was a general denial of the allegations of that count. In the first affirmative defense, the defendant alleged that in doing the excavation work it did, defendant had permission to do so by the City of Rockford and that the city furnished defendant with a plat of the area upon which no underground cable or conduit was shown and that the excavation was made within stakes placed by the city officials. The second affirmative defense alleged a release of liability by reason of a credit memorandum and set forth that after September 16, 1950, the president of defendant company was repeatedly billed by the plaintiff in the amount of $2,182.28, said bill purporting to be based on a claim of the plaintiff for expenses incurred in making repairs to this damaged cable; that on March 21, 1952, defendant received through the mail a credit memorandum issued by the plaintiff by which plaintiff credited the account of the defendant with the amount of $2,182.28. Plaintiff replied to these affirmative defenses denying the allegations of the first affirmative defense, and, as to the second affirmative defense, plaintiff averred that the credit memorandum was sent because of a mistake. Upon the issues thus made by the allegations of count three (the negligence count) and the answer thereto, a trial was had before the court without a jury. At the conclusion of the trial, the court found the defendant guilty of negligence in failing to ascertain the location of plaintiff’s cable. The court also found that it was the duty of the plaintiff to inform defendant of the existence and location of its conduit and cable and also the duty of the plaintiff to check the records in the city engineer’s office in order to determine whether a permit had been granted defendant to excavate at the place where plaintiff’s conduit and cable were located. Failing to do this, the trial court concluded that plaintiff was guilty of contributory negligence which precluded a recovery and rendered the judgment which plaintiff seeks to reverse.
Counsel for both parties state that neither the Supreme nor any of the Appellate Courts of this State have heretofore considered the extent of liability of one, who, in excavating, damages the installations of another lawfully placed there prior to the excavation. Counsel for appellee insists that the only case directly in point is Socony-Vacuum Oil Co., Inc. v. Bailey,
In New York Steam Co. v. Foundation Co.,
Frontier Telephone Co. v. Hepp,
Frontier Telephone Co. v. Hepp, supra, was cited and quoted from with approval by the Supreme Court of New Jersey in Public Service Ry. Co. v. Mooney, 99 N. J. L. 58,
United Elec. Light Co. v. Deliso Const. Co.,
Cincinnati & Suburban Bell Tel. Co. v. Eadler,
In Allegheny County Light Co. v. Booth,
Edison Illuminating Co. v. Misch,
In Bell Telephone Co. of Pennsylvania v. Baltimore & O. R. Co.,
The finding of the trial court that plaintiff was guilty of contributory negligence which precluded a recovery in the instant case because the plaintiff was charged with knowledge that sewers were being dug, excavations made and streets repaired and that therefore it was the duty of the plaintiff to let defendant know where its underground cables were located is not sustained by the authorities. The weight of the evidence in our opinion discloses that plaintiff was in the exercise of due care for the safety of its own property. Counsel for appellee insists that the facts in the several cases referred to herein are distinguishable from the facts in the instant case in that in some of the cases the right of the plaintiff to use the underground portion of a street or parkway was spoken of as a franchise, a license or a grant while the interest which a public utility has in a public street by reason of a grant from a municipality in Illinois is a license. The argument made is not persuasive. The utility takes from the municipality a possessory or proprietary interest which is protected from invasion or damage by subsequent users. This is illustrated in Milwaukee Elec. Railway & Light Co. v. City of Milwaukee,
Under the authorities, it was the duty of the defendant to inform itself of the location of plaintiff’s property, and the plaintiff cannot be held contributorily negligent as a legal proposition because it did not seek out the defendant and inform it where its conduit and cables were located, nor was it the duty of the plaintiff to check the records of the municipality to ascertain, to whom permission had been given to excavate at the place where plaintiff had buried its conduits and cables.
Furthermore, Rector Egeland, plaintiff’s district plant engineer who was in charge of underground cable installations of the plaintiff testified that a couple of weeks before September 16, 1950 he observed defendant’s crew working north of the intersection of Bohm and Rural Streets and Egeland inquired of defendant’s foreman to what extent defendant planned to excavate and was told by the foreman that the excavations would not go south past the middle of Rural Street and that the storm sewer would go north from Rural Street into the subdivision. It is true Egeland did not remember the name of the foreman but his testimony is that he told the foreman at that time that the plaintiff had a cable on the south side of Rural Street. Mr. Egeland further testified that prior to September 16, 1950 he had had approximately fifty conversations with Mr. Ind, president of defendant, about excavations made by defendant through or near the underground installations of plaintiff. He further testified that in June 1948 plaintiff sent a letter to Mr. Chas. Ind and to all contractors in the Rockford area requesting the contractors to notify the plaintiff of any contemplated work which might bring them in contact with plaintiff’s plant and suggesting that such contractors examine underground locality maps or plats which were on file in its offices and in various public offices showing the locations of plaintiff’s installations and suggesting that reference he made to these plats during excavations. This letter further stated that the telephone company maintained a twenty-four hour service, where this information could he secured and stating that a telephone call, giving the telephone numbers, was all that was necessary and that the telephone company would arrange to have a representative locate its underground plant on the ground and furnish such assistance as is necessary in order to assure that no damage is done. Mr. Ind, president of defendant company, testified he did not receive this letter but did recall that he had contacted the telephone company about various jobs at different times but not about the instant one. Mr. Ind further testified that prior to September 16, 1950 he had never seen a plat showing the underground installations of plaintiff but that he “had heard of the existence of plats showing the phone cables, which plats were filed with the Sanitary District Office, the City Engineer’s Office, the Water Office, the County Superintendant of Highways and the Rockford Township Superintendent of Highways. I don’t know exactly” continued this witness, “when I first knew of their existence. I don’t think I knew anything to speak of about any plats before September 1950.” Then, referring to the location where this cable of the plaintiff was damaged, Mr. Ind testified: “I checked the locality thoroughly before I started on the job. We always check the terrain or the street as to what objects would be in the way. We do not always check for telephone or electrical underground installations. ... I don’t remember whether I called the telephone company about the possibility of any cable being in that particular street but I did call them about jobs we had in process. We generally, before we started a job, called the telephone company both before and after 1950.”
During the trial, an engineer employed by the city, John Frankenberg, testified on behalf of the plaintiff and was asked if from July to September 1950, there was in the office of the city engineer records showing the underground installations of appellant. Upon an objection being interposed, the court inquired the purpose of the offered testimony. Counsel for the plaintiff then stated that a copy of the plat showing such installations was on file in the city engineer’s office and that one of the issues was whether defendant, had failed to ascertain the existence of this underground cable. Thereupon, the court said: “Suppose it was. That doesn’t bind Ind unless he saw it. This man made a print and he didn’t include the telephone cable. That is not Ind’s fault. That is the engineer’s fault. You mean to tell me the City Engineer isn’t under any duty to notify and give information about cables, sewers, waterpipes, and things like that when an excavator goes in and asks for a plat?” To which counsel for the plaintiff responded: “No. The excavator determines the existence of the utility installations, the telephone installation from the telephone company and the city engineer’s office gives information merely on the sewer and water. I would like to put it in the case to show that is the case.” The court then said: “That isn’t the case. If he didn’t put it in there, that is his shortcoming. If you can connect Ind up with some particular plat that was in the office of the city engineer, that he looked at or was called to his attention, that is a different proposition but not with this plat.”
The record does disclose that there was on file in the city engineer’s office of the City of Bockford on and for a long time prior to September 16,1950 a plat showing the location of plaintiff’s underground cables: that when new installations were made, a new plat or map was prepared and filed in the office of the city engineer and the previous plat or map withdrawn. The plat which defendant used in making the excavations it did for the storm sewer on September 16, 1950 was prepared by the office of the city engineer of Rockford for Rosenquist and Schanacker owners of the subdivision by whom defendant was employed and this plat shows that this storm sewer which defendant was excavating was an integral part of the construction work defendant was doing for the subdividers in connection with the laying out of their subdivision.
In the instant case defendant had a right to excavate where it did in constructing a storm sewer for its employer. Plaintiff, at that time, enjoyed a possessory or proprietary interest, granted it by the city in the portion of the street where defendant was excavating. The permit from the city gave defendant no right to interfere with this interest and when its excavating hoe struck and damaged plaintiff’s cable defendant committed a trespass for which it became liable.
It is finally insisted by appellee that plaintiff’s claim was extinguished by the credit memorandum sent defendant by the plaintiff on March 18, 1952. What the record discloses is that shortly after September 16, 1950, plaintiff sent a bill to the defendant for the expense incurred in repairing its damaged cable. One of these bills was dated April 23, 1951 another was dated May 8, 1951, and another August 7, 1951. These bills were on plaintiff’s Form No. 4157A, refer to bill No. PU. 4081 and are addressed to Mr. Charles G. Ind, Point Avenue, Rockford, Illinois, and are substantially as follows: “Expense incurred in making the necessary repairs to our equipment on or about September 16, 1950, in parkway on Rural Street at intersection of Bohm Avenue, Rockford, Illinois, as the result of being struck by equipment belonging to you. Material (1212 pair cables, sleeves and solder) $294.54. Labor, (815 hours) excavating, removing damaged cables, placing splicing and testing new cables, back filling $1752.36. Motor vehicle service, (135% hours) $135.38. Total. $2182.28.” On March 18, 1952, the plaintiff sent to the defendant a credit memorandum reciting: “We credit your account with the following: To cancel our bill PU. 4081, dated April 23, 1951, for the cost of repairing and replacing a section of our company’s 1212 pair buried cable at Rural Street and Bohm Avenue, Rockford, Illinois, which was damaged by your workmen while excavating for sewer work on September 16, 1950. Work completed September 26, 1950. Total $2182.28.”
Philip L. O’Brien testified in connection with this phase of the case to the effect that he had been employed by the plaintiff for 39 years and at the time he testified he was disbursement accounting supervisor of the plaintiff and supervised the preparation of bills for work performed in the area including Rockford. He outlined the bookkeeping and accounting procedures of the plaintiff, and stated that this credit memorandum was prepared in his office: that there was a mistake in connection with this bill and that it was not intended by the company that this credit memorandum should be sent to the defendant. He further testified that the defendant never paid the plaintiff any portion of the amount due the plaintiff aggregating $2,182.28 as evidenced by the invoices sent by the plaintiff to the defendant and that this amount is currently carried on the books of the plaintiff as an indebtedness from the defendant to the plaintiff. This witness explained in detail what the credit memorandum was intended to do and that delivery of it by mail to the defendant was unintentional and made through a clerical error. Defendant admits it never paid to the plaintiff or any one else any portion of this bill and is unable to explain why it was ever sent by the plaintiff to the defendant.
The trial court stated that this memorandum operated as a release of defendant’s indebtedness to the plaintiff. Whether an instrument is an effective release depends upon the intention of the parties. (Parmelee v. Lawrence,
Under the authorities cited and the evidence found in this record the trial court erred in not rendering judgment in favor of the plaintiff and for this error the judgment of the circuit court is reversed and the cause remanded.
Reversed and remanded.
