141 P. 1099 | Idaho | 1914
The complaint in this case is almost identical with the one in Idaho Irr. Co. v. Dill, recently decided by this court (25 Ida. 711, 139 Pac. 714), and the action is of the same nature. In that case the question presented was whether the lower court erred in sustaining a demurrer to the complaint upon the ground that the United States was a necessary party to the action, and upon that question this court reversed the court below.
By stipulation of counsel it was agreed that the contract which the plaintiff corporation made with the defendant in
The defendant Pew,- the original purchaser, had assigned all his interest under the contract to the defendant Cornell, who alone appeared and demurred to the complaint. The lower court overruled the demurrer. Defendant elected to stand thereon and declined to plead further. The demurrer alleged that the complaint did not state facts sufficient to constitute a cause of action, and particularly in (1) that the plaintiff has not alleged that the irrigation system, which by the terms of the contracts set up in the complaint it agreed to construct, has been completed; (2) that the plaintiff has not alleged that the amounts sued upon and for which a lien is claimed are “the actual cost of reclamation (of the land described in the complaint) and reasonable interest thereon from the date of reclamation until disposed of to (an) actual settler (s) ”; (3) “that no valid lien can be created under existing law against either land or water, as is attempted to be done under the allegations of the complaint herein. ’ ’
A similar question arose on rehearing in the recent case of Childs, v. Neitzel, ante, p. 116, 141 Pac. 77, in which the contract with the settler also contemplated the payment for water rights by annual instalments, and the court said:
“We did not mean to hold in the original opinion that the annual instalments provided for by said water contracts did not become due and payable until the entire system was completed; but when the system was so far completed as to make water permanently available for any particular user for all*276 seasons, the instalments* agreed to be paid by the user would become due and payable in accordance with the terms of the contract. Then he has no reason to complain of lack of water for other land owners, because he has water available for the irrigation of his land.”
There are practical reasons which Congress doubtless had under consideration when by the 1896 amendment to the Carey Act it specified the character of completion necessary in order to obtain patent, with reference to “a particular tract or tracts of such lands, ’ ’ instead of making it apply to all the lands embraced in the project. For instance, a Carey Act project may include several distinct segregations or units of land to be reclaimed, but all of which are covered by the one contract with the state. The entire completion of such a system may extend over a compáratively long period. An ample supply of water may be permanently furnished to one or more of these units for years before other portions of the system are finished. It would manifestly be a great financial burden upon the enterprise to exact from its promoters the condition that no deferred payments should be collected nor liens securing them attach until all lands on all the tracts embraced in the project were permanently supplied with water. Such a requirement, besides being unnecessary to protect a settler who was already in possession of what he had contracted for, would obviously increase the cost of the enterprise to the settler by making the investment less attractive to the capitalist, who would require a higher rate of interest, or its equivalent, to compensate him for the increased risk.
This court has already held in Idaho Irr. Co. v. Dill, supra, that “Under the provisions of section 1629, Rev. Codes, any company or association furnishing water for any tract of land is given a first and prior lien on the water right and the land upon which said water is used for all deferred payments for the water right, and upon default of any deferred payments the lienholder may foreclose the same in accordance with the terms and conditions of the contract for the purchase of the water right.”
Counsel for appellant contends in his brief that “so far as the state lien is broader than the lien allowed by the national law it is invalid,, for by sec. 1613 Rev. Codes, our legislature accepts the conditions of the Carey Act. The national law is paramount. The state is' not authorized to create any lien against either land or water except for ‘the actual and necessary expenses of reclamation and reasonable interest thereon.’ ” This contention may be conceded in the main, but subject to an important qualification. The national Carey Act authorizes a lien only against the land. It apparently recognizes the right of the state to control the disposition of its public waters. The state statute authorizes a lien against both the land and water, as it has a right to do, and to this extent is broader in its lien conferring provisions. But so far as the land itself is concerned, the lien of course must be subject to the limitations of the congressional act.
After the recitals of the settlers’ contract with the company the first article of the agreement begins as follows: “This agreement is made in accordance with the provisions of said contract between the state of Idaho and the company, which, together with the laws of the state of Idaho, under which this agreement is made, shall be regarded as defining the rights of the respective parties. ’ ’
In making that contract the settler assents to the estimate authorized by the state as to the cost of reclamation. Can
Suppose, on the other hand, that the estimated cost is largely exceeded by the actual cost of construction, as is said to often be the ease. Could it for a moment be maintained that the construction company would be entitled, under authority of the national act, to a lien sufficient to cover that increased “actual cost,” in the face of the contract which it had made ?
In concluding our consideration of this part of the case, it may be pointed out that the amendment of 1896 to the federal Carey Act does not create the lien. It in effect ratifies the previous creation of the lien by the state statute (Act of 1895, Sess. Laws 1895, p. 227; see. 1629, Rev. Codes), but contains a condition not contained in the provisions of our statute. However, since the cause of action arises under our statute we do not think it strictly necessary for the complaint to allege that the requirement of the federal statute has been complied with, that is to say, that the amount of the lien claimed represents “the actual cost and necessary expenses of reclamation,” etc. But it occurs to us that it would certainly be good practice to, insert such an allegation in any complaint for the foreclosure of a Carey Act lien.
The judgment of the lower court is affirmed. Costs awarded in favor of respondent.