The plaintiff, a subcontractor, brought this action to recover damages for the breach of an express contract against the defendant Gary Excavating, Inc., hereinafter Gary, the general contractor for the construction of a sewage system for the town of North Haven. The case was referred to Hon. John B. Thim, state referee, who, exercising the powers of the Superior Court, rendered judgment for the plaintiff. The defendants have appealed from that judgment.
The defendants have assigned error in the referee’s finding of facts without evidence; in his rulings on evidence; in his overruling of their claims of law; and in his сonclusions.
The finding
1
discloses the following pertinent facts: The plaintiff was engaged in the deep-well dewatering business and, in conjunction therewith, sold and rented pumps and associated equipment. In the summer of 1966, the defendant Gary began to prepare its bids to obtain contracts for the installation of sanitary sewers in the town of North Haven. Initially the town of North Haven had divided the sewer project into two segments and contractors were invited to bid on either or both, designated as contracts 100-8 and 100-9. The proposed project called for the sewer pipe to be laid in dry trenches, requiring dewatering of the аrea. Following discussions with Gary, the plaintiff pre
The town of North Haven did not accept any of the submitted bids. Instead it modified the sewer project by redesignating some of the streets on which sewers were to be installed, combined the prеviously proposed contracts into a single contract, labeled it 100-9 and invited bids. Gary’s bid on the new contract 100-9 was accepted by the town.
Gary did not enter into a new subcontract with the plaintiff;. Both parties understood that their
The referee reached the following conclusions: (1) the plaintiff brought the proper cause of action in seeking recovery on the subcontract; (2) the plaintiff fully performed its contractual obligations; (3) the plaintiff was justified in terminating its subcontract with Gary; and (4) the defendants failed to establish the allegations of their special defenses and counterclaim. Judgment was entered for the plaintiff in the amount of $60,000.
Gary’s principal claim is that the referee erred in concluding that the plaintiff had brought the proper cause of action. Gary argues that the subcontrаct of April 18, 1967, relates by its terms to contract proposals 100-8 and 100-9 only, and that when those contracts were not subsequently awarded to Gary, the subcontract became unenforceable and void. Although Gary concedes that the plaintiff performed work on the sewer project, it maintains that the work was not done under contracts 100-8 and 100-9.
“The intention of the parties manifested by their words and acts is essential to determine whether a contract was entered into and what its terms were.
Nutmeg State
Machine[ry]
Corporation
v.
Shuford,
The inclusion of .a reference to contracts 100-8 and 100-9 in the subcontract did not automatically cause its termination when the contract subsequеntly awarded Gary was labeled 100-9. The subcontract required the plaintiff to drill wells and rent equipment when and where Gary directed. The parties agreed to a specific price per vertical foot drilled and to a specific schedule of rental rates for equipment leased. There was no need to consult contracts 100-8 and 100-9 for detailed plans and specifications since the mutual obligations of the parties were contained within the four corners of the subcontract and its addendum. The written words of the parties did not manifest any intent to abandon their subcontract merely because the sеwer project was modified and combined under the single label 100-9. This is not a case, as claimed by Gary, in which “substantial changes” were subsequently made to incomplete documents incorporated into the contract by reference, as in
Randolph Construction Co.
v.
Kings East Corporation,
The subsequent acts of the parties are also evidence of their intent. When the plaintiff began work on the sewer project, it did so under the direction of Gary. The рlaintiff performed according to the terms of the subcontract and rendered monthly bills thereunder. Gary accepted those bills without
The conclusions reached by the trial court are tested by the finding and must stand unless they are legally or logically inconsistent with the facts found or unless they involve the application of some erroneous rule of law material to the case.
Klein
v.
Chatfield,
The referee correctly rejected Gary’s contention that recovery could be had only on an implied contract or in quantum meruit. Since Gary contracted for performance at an agrеed unit price and at an agreed rental for equipment leased, the plaintiff was not required to prove the reasonable value of its services. Where the plaintiff performs according to the contract, he is entitled to recover the
The defendants have assigned error in the finding by the referee that “[t]he total fair and reasonable charges for repairs to leased equipment because of negligence was $2,983.64.” The defendants claim that “there was a total absence of any evidence to justify a finding that the alleged repairs resulted from negligence.” This assignment of error has merit. Wе find no evidence in the appendix to the plaintiff’s brief which would support a finding that the alleged repairs were necessitated by Uary’s negligence. Moreover, there is no claim in the complaint for the cost of repairs to leased equipment damaged by negligence. The referee erred in making this finding and award.
The final assignment of error relating to rulings on evidence has been considered and fоund to lack merit.
There is error only in the amount of damages; the judgment is set aside and the case is remanded with direction to render judgment as on file except as modified in accordance with this opiniоn.
In this opinion the other judges concurred.
Notes
A finding of material fact may be attacked as not supported by the evidence. The validity of such a claim is tested by the evidence printed in the appendices to the brief. Practice Book § 718;
Klein
v.
Chatfield,
“GARY EXCAVATING, INC. GENERAL BUILDING CONTRACTORS 1155 Main Street, Branford, Conn.
Date April 18, 1967
SUBCONTRACT AGREEMENT
WITH Hydro-Hercules Corporation Box 399 RD-2 South Road Bolton, Connecticut 06040
Sanitary Sewers
NAME OF JOB Contracts 100-8 & 100-9
LOCATION North Haven, Connecticut
Subject to the approval of the Engineer and Owner this will be your authority to furnish all labor, equipment and materials (other than gravel) for the installation of wells as required for Contracts 100-8 and 100-9 for the Town of North Haven, Connecticut, at the price of $7.50 per foot, (vertical)
Additional wells required at less than 200 feet spacing will be at the cost of $7.00 per vertical foot.
Pumps will be furnished as required on a rental option basis by Hydro-Hereules. 90% of rental to be applied towаrd cost of equip-
Scheduling of progress is to be determined by our Engineer and will not require any more than three (3) moves by Hydro-Hercules.
Water required for drilling will be furnished by General Contractor.
Monthly payments for work in place. Progress to be in keeping with requiremеnts of General Contractor.
Accepted by: Accepted by:
Russell T. Moonan, Pres. Vincent Giordano, Treas.
Hydro-Hercules Gary Excavating, Inc.”
“PROM HYDRO HERCULES
Re: Sanitary Sewers
Contracts 100-8 & 100-9
Addendum to Subcontract Agreement dated April 18, 1967.
General Contractor will determine well locations and depth, however, this should be in keeping with the Sub-Contractor’s progress so as not to cause delays to the Subcontractor.
Approved
Vincent Giordano
5/3/67”
