18 P.2d 124 | Kan. | 1933
The opinion of the court was delivered by
The action was one by taxpayers to enjoin the city of La Cygne from charging property specially benefited with assessments, and from charging property generally with taxes, to pay for a street improvement. Injunction was denied, and plaintiffs appeal.
The street in question is Market street. It extends from the west side to the east side of the city, and became a connecting link of the highway, construction of which was considered by this court in State, ex rel., v. Linn County, 113 Kan. 203 (1923), 213 Pac. 1062, and State, ex rel., v. Linn County Comm’rs, 120 Kan. 356 (1926), 243 Pac. 539.
In 1928 the director of the state highway commission and representatives of the city met with the Linn county commissioners, and Linn county pledged assistance in completing the highway. In April, 1930, the highway commission authorized construction of an 18-foot concrete pavement through the city on Market street. This action was taken with the understanding the city would pay one-half of the cost, and the remainder would be paid from federal aid. The action was also taken to fulfill the obligation of Linn county to the city, existing previous to the highway act of 1929. The state highway engineer was instructed to procure a reallotment of federal aid, which had previously been withdrawn.
On May 5, 1930, residents of the city, claiming to be a majority
On July 18 plans and specifications of work were filed with the city clerk by the highway commission, a contract between the city and the highway commission for the entire improvement was authorized, and the.highway commission let a contract for construction of the improvement to a construction company. The contractor commenced work on August 1. The contract between the city and the highway commission was signed on August 7, and contained the following provision:
“Whereas, the parties hereto desire to divide the cost of' the improvement of said street,
“Now, Therefore, It is agreed by and between the parties hereto
“That said city street be improved in the following manner: Grading, curbing, guttering, drainage, structures, and surfacing with a concrete pavement and chats.
“That the improvement of said street, including the preparation of plans, letting of contracts, and payment of contractor, or for labor and material, shall be under the supervision and control of party of the first part.
“That the cost of such improvement, including construction, engineering, grading, drainage structures, curb and gutter, concrete paving, and chat surfacing, shall be divided as follows: The part to be paid by party of the first part to be computed on the basis of fifty per cent (50%) of the cost of a concrete slab eighteen feet wide, and fifty per cent of the total cost of all excavation, borrow, drainage structures, and guide posts, and remainder of the cost of such improvement to be paid by party of the second part.”
On August 21 the taxpayers’ action was commenced. Legality of everything which had been done and would be done was assailed in the petition, but no application was made for an order to stop construction of the improvement. The street was graded, curbed and guttered, the 18-foot concrete pavement was laid, and the remainder of the street was paved with chats. On January 23, 1931, the city made final settlement with the highway commission. On February 16, 1931, an ordinance was passed providing for is
When the lot owners’ petition was filed to improve the portions of the street lying each side of the 18-foot concrete pavement, plaintiffs filed a protest. The protest was nugatory, and the mayor and council disregarded it. Protest is allowable only when an improvement proceeding is initiated by the mayor and council, and not when initiated by property owners. Besides that, plaintiffs did not own sufficient real estate to give them standing to protest. On October 20, 1930, plaintiffs moved for a.restraining order and temporary injunction to prevent levy of special assessments, and a temporary order was issued. On October 27 a hearing was had, the restraining order was set aside, and a temporary injunction was denied. As indicated, plaintiffs did nothing toward preventing the doing of work which would give rise to necessity for levying taxes and special assessments. The attitude of plaintiffs was stated in the petition as follows:
“Plaintiffs further state that they have no desire to interfere with or prevent the state highway commission from constructing an eighteen-foot concrete slab along Market street, which has been designated as a connecting link in the state highway system.
“Plaintiffs allege that the contract or contracts made by the state highway commission with its codefendants, the J. A. Tobin Construction Company and J. A. Tobin, are divisible, and that said J. A. Tobin Construction Company or J. A. Tobin may, so far as these plaintiffs are concerned, carry on and complete the eighteen-foot slab, and that the state highway commission may and should, as provided by law, pay the cost thereof from the state highway fund provided for the construction of state highways. That said contract or contracts being divisible, this court should enter an order as hereinabove set out, merely restraining and enjoining the city from paying any portion of the costs of said eighteen-foot improvement, or from issuing its bonds for that purpose, or from levying any special assessments against the abutting property therefor, and also for the curbing and guttering of Market street, or paving, chatting, graveling, or otherwise improving the portion thereof between said concrete slab and said contemplated curb and gutter.”
The objection to improvement of the portion of the street not occupied by the 18-foot concrete pavement was that the property owners’ petition was insufficient to give the mayor and council authority to proceed. At the trial it was shown the petition was in fact defective. It lacked the necessary number of signatures, and the court so found. The mayor and council, however, had found
The district court held enactment of ordinance No. 425 sufficiently complied with the statute of 1927. Plaintiffs contend the ordinance was an original ordinance levying special assessments, and was not a curative ordinance making a relevy pursuant to the statute. This is true, but all that was necessary was for the mayor and council to repass and republish the identical ordinance, in effect a mere formality.' Plaintiffs were in a court of equity, and it was the province of equity to regard that as done which ought to be done.
With respect to the 18-foot concrete pavement, plaintiffs say the city had no authority to contract with the highway commission to pay half the cost and had no authority to carry out the contract. As indicated, plaintiffs did not desire to interfere with construction of the pavement. They just did not want it to be paid for, when finished, under the particular arrangement which the city had made and which the highway commission was actively proceeding to carry out, when the suit was commenced on August 21.
From the beginning the paving of Market street was one comprehensive project. All the plaintiffs, except two, signed the ineffectual protest against action on the petition to curb, gutter and pave “the intervening portion between the pavement to be laid by the state of Kansas” and the curb line. At the session of the mayor and council at which the protest was disregarded and the ordinance was passed providing for construction of the improvement, the resolution was passed to issue bonds to pay 50 per cent of the cost of the paving to be laid by the state. These proceedings were pleaded
“The plaintiffs in the taxpayers’ suit did not exercise a high degree of diligence, since they let the work proceed when a temporary restraining order to be had for the asking would have brought it summarily to a stop.” (Ritchie v. City of Wichita, 99 Kan. 663, 669, 163 Pac. 176.)
The result of the foregoing is that whether or not the city had authority to make and fulfill the contract with the highway commission, under elementary principles of equity these taxpayers forfeited right to complain.
The judgment of the district court is affirmed.