23 Haw. 606 | Haw. | 1917
OPINION OF THE COURT BY
This is an action against the principal and surety on a builder’s bond, in which there was a verdict for the plaintiff against the principal but in favor of the surety. The plaintiff brings exceptions.
There was evidence to the effect that on October 24, 1910, Mrs. Hustace made a contract with Davis for the furnishing of the materials and labor for and the erection on her premises at Waikiki, Honolulu, of a two-story residence, according to plans and specifications, for the sum of $7116; that the contractor gave a bond in the sum of $3558, with the defendant Bicknell as surety, conditioned for the performance on his part of the covenants, conditions and agreements contained in the contract, and that he would pay for all material used and labor employed in the performance of the contract and save Mrs. Hustace harmless from all liens, suits, damage, etc. In this action the plaintiff claimed the sum of $1952.48, which was made up as follows: Davis was credited with the sum called for by the contract, $7116; extras accruing from changes ordered by Mrs. Hustace, $456.74; and an extra charge allowed for a concrete floor not
Counsel for the defendant Bicknell contends that upon the evidence the surety on the bond was released from liability and that a motion for a directed verdict in favor of the surety, which was made when both parties had closed their evidence, ought to have been granted, and that, if so, any errors that may have occurred in the instructions given the jury were harmless and need not be discussed. The several grounds on which the motion for the. directed verdict in favor of the surety was based will be considered in connection with the evidence bearing thereon. The first ground was as follows: “That the owner without the consent of the surety and in the absence of a written order of the architect therefor, altered the building contract of October 24, 1910, by ordering and causing to be performed certain substantial extras upon the building subject to the contract,' contrary to the provisions of Article 3 of said building contract.” Article 3 of the contract provided that “No altera
The trial court declined to give all but one of the instructions requested by the plaintiff and charged the jury of its own motion. The plaintiff excepted generally to “the court’s giving of its instructions — his written instructions.” Such a general exception could be sustained only in the event that the instructions were bad throughout. Territory
In his brief counsel for the appellant contends that plaintiff’s requested instructions Nos. 7, 8; 9 and 10 were erroneously refused. By number 7 the court was asked to instruct the'jury that’the judgments rendered in the lien cases of Lewers & Cooke, Ltd., and Lucas Bros, are conclusive upon the defendants in this case. An inspection of the records in those cases which were put in evidence shows that the plaintiffs claimed the value of materials furnished for the construction of a building by Davis upon the premises of Mrs. Hustace, but it did not appear upon the face of either record that the building for which the materials were furnished was the one which was erected under the contract of October 24, 1910. There was evidence in this case from which the jury were authorized to find as a fact that those materials were used in the construction of the building under this contract. But the instruction went too far in saying that the judgments were “conclusive” — which we take to mean conclusive as matter of law — since it was necessary to supplement the records with évidence identifying the contract referred' to in them with the contract for the performance of' which thé' defendant Bicknell was surety. The instruction in the form requested Vas properly refused. By numbers 8, 9 and 10 the court was requested to instruct the jury that “you may include in'your verdict” the cash payments made to the contractor, the amounts paid to material-men upon the orders of the contractor, and the amdunt of the costs and expenses incurred by the plaintiff in connection with the lien cases. The requested instructions were defective and properly refused. The sum of the different amounts referred to in the instructions was many times the amount claimed in the action. Probably what was meant to be stated was that in ascertaining the balance diie
There was, however, one instruction requested by the plaintiff, bearing upon the liability of the surety, which contained a correct statement and which ought to have been given to the jury. It was as follows:
“5. I charge you that the provision in the contract that no alterations shall be made in the work except by written order of the architect does not preclude the making of alterations without such written order, that provision being principally for the protection of the owner against the claim of the contractor that alterations were made with the owner’s consent, when in fact such consent was not. obtained, and alterations so made with the consent and approval of the owner and architect will be held to be done under the contract.”
That instrúction was accurate, applicable and material to the point it referred to and was not included in the charge given by the court. The refusal to give it constituted error. Nawelo v. von Hamm-Young Co., 20 Haw. 644.
■ The exceptions to the refusal to give plaintiff’s requested instruction number 5, and those to the verdict and the ruling denying the motion for a new trial are sustained, and a new trial is granted.