These two appeals mark the second and third appearances of cases arising out of a 1982 contract between Georgia Ports Authority (“GPA”) and Pinehurst Corporation (“Pinehurst”) for the construction of a warehouse extension at GPA’s ocean terminal facility. The construction was to be performed by Pinehurst pursuant to plans and specifications prepared by the architectural engineering firm of Hussey, Gay & Bell (“HG&B”). The plans required that the warehouse have a paved floor which was installed by Clay-Ric, Inc. (“Clay-Ric”) under a subcontract between Clay-Ric and Pinehurst. After installation, the floor became wet due to work being performed on the job site by Pinehurst and other subcontractors and did not pass the load test performed by HG&B. At Pinehurst’s direction, Clay-Ric repaved the floor and incurred costs in excess of $40,000. However, Pinehurst did not pay Clay-Ric for the repaving work, and Clay-Ric subsequently filed a four-count complaint against Pinehurst, HG&B and GPA to recover the amounts owed for the repaving work. Clay-Ric contended that the repaving work was beyond the scope of its original contract with Pinehurst and that it performed the repair work because each of the named defendants represented to Clay-Ric that it would be fully compensated for the work. GPA answered the complaint, denying that it had made any such representations to ClayRic, and filed a third-party complaint against Safeco Insurance Company of America based on the payment bond given by Pinehurst pur *505 suant to OCGA § 36-82-101. 1 GPA subsequently amended its complaint to add as a defense the failure of Clay-Ric to satisfy the bonding requirements for public works contracts with a public body and moved for summary judgment. The trial court granted GPA’s motion for summary judgment. In Case Nos. A92A0308 and A92A0365, HG&B and Clay-Ric, respectively, appeal from the grant of summary judgment to GPA.
Case No. A92A0365
1. The crux of Clay-Ric’s complaint against GPA is that GPA directly and through its agents authorized the paving repair work and represented that Clay-Ric would be paid for the work. “The burden is on the party who moves for summary judgment to produce evidence which conclusively negates the essential elements entitling the respondent to recover under any theory that may be drawn fairly from the pleadings and the evidence. [Cit.]”
Dairyland Ins. Co. v. Gay,
2. Clay-Ric also contends that the trial court erred in not finding that GPA is liable under implied contract theories of quantum meruit and unjust enrichment. “Under Georgia law, a materialman or subcontractor may not recover against an owner or general contractor with whom it has no contractual relationship, based on the theory of unjust enrichment or implied contract; rather, it is limited to the statutory remedies provided by Georgia’s lien statute, [OCGA § 44-14-360 et seq.] [Cits.]”
P. P. G. Indus. v. Hayes Constr. Co.,
3. Clay-Ric’s argument that GPA’s acceptance of the repair work without compensating Clay-Ric constitutes an unlawful taking of public property without just and adequate compensation is without merit. “The constitutional provisions prohibiting the state or subdivisions from taking private property for a public purpose without just
*507
and adequate compensation are applicable only when the acts constitute a ‘taking’ of the property within the meaning of the law. [Cits.]”
Bray v. Houston County,
Case No. A92A0308
4. GPA has filed a motion to dismiss this appeal brought by HG&B on the grounds that HG&B lacks standing to appeal the grant of summary judgment to GPA. “ ‘(A) co-defendant does not have any standing to appeal an order granting summary judgment in favor of another defendant when (his) right has not been adversely affected thereby. (Cit.)’ [Cits.]”
Shackelford v. Green,
5. HG&B contends in its sole enumeration of error, that the trial court erred in holding that Clay-Ric’s claims were barred due to ClayRic’s failure to obtain payment and performance bonds because genuine issues of fact remain regarding whether Clay-Ric was a contractor or a subcontractor. Our examination of the trial court’s order reveals no such holding encompassed within that order. “ ‘(I)ssues raised . . . (which are) not . . . encompassed within the final order from which the appeal has been taken, . . . may not. . . (b)e raise(d) (on appeal), either in enumerations of error or through arguments in briefs of counsel. (Cits.) [Cit.]’ [Cit.]”
Costanzo v. Jones,
Judgments affirmed.
Notes
In the first appearance of this case,
Safeco Ins. Co. of America v. Clay-Ric, Inc.,
