Hurtt v. Sanders Bros. Mfg. Co.

99 Ill. App. 665 | Ill. App. Ct. | 1902

Mr. Justice Brown

delivered the opinion of the court.

On July 21,1898, Mrs. S. H. Hurtt, appellant, entered into a written contract with appellee Peter D. Pish, to erect for her a residence in the city of Pontiac, for the sum of $2,765, “ subject to additions and deductions,” as provided in the contract.

The contract also provides that the building shall be completed on or before Hovember 1, 1898, if possession of the premises is given to Pish on or before July 25, 1898, and provides for a certain extension of time in the event of the happening of either of certain contingencies therein mentioned that might delay the work. There is no proof that any of these contingencies occurred.

It also provides that all payments shall be upon the architect’s certificates (to be made every two weeks), the contractor to receive eighty per cent of the estimate, the owner to retain twenty per cent of the contract price until completion and acceptance of the building, final payment to be made within five days after fulfillment of contract.

After beginning work Rish prosecuted it very indifferently, and when November 1, 1898, arrived, the building was not finished, and finally work ceased entirely.

January 14, 1899, notice was served upen' Rish by Mrs. Hurtt that she would enter upon the premises at the expiration of five days and proceed to finish the work at his expense, unless he himself did so. The building was at this time habitable, and she arranged with Rish that she might occupy it, but stipulated in writing that her occupancy should not be construed as an acceptance of the building or as a fulfillment by Rish of his contract. Some work was done or materials gotten in February, but work was again stopped, and finally, on April 14-, 1899, Mrs. Hurtt served notice upon Rish that if he did not go on with the work within five days she would herself take charge and complete the building. Rish ignored this notice and entirely disregarded his contract, whereupon Mrs. Hurtt did take charge of the building, and under the direction of R. A. Young, as architect, it was finished about June 1, 1899.

Appellees, Sanders Bros. Mfg. Co., W. L. Craig & Co., Henry R. Davies and George S. Thompson were severally sub-contractors of appellee Rish, Sanders Bros. Mfg. Co. having taken the contract for the mill work, interior finish and certain plate glass, Craig & Co. the contract for nearly all other materials, Davies the contract for the construction of the brick and stone work, and Thompson the contract for the galvanized iron and tin work, certain hardware and the nails. These several contracts were oral.

It is impossible to determine, from either the pleadings or the testimony, just when some of the materials were furnished and when certain of the work was done.

Appellee Thompson instituted this proceeding by filing a petition to enforce a lien in the Circuit Court of Livingston County on July 10, 1899, and made Mrs. Hurtt, Rish, Craig & Co. and Sanders Bros. Mfg. Co., parties defendant. Davies subsequently became a party by intervening petition. Mrs. Hurtt filed an answer to the original and intervening or cross-petition admitting ownership of the lot on which the building was erected and that she made a written contract with Eish July 21, 1898, and denied that the building was erected and completed according to the terms of the contract, averred the notice to Eish heretofore referred to, and stated that she was obliged to and did take charge of the work and complete the building, and in so 'doing she necessarily expended all the money not theretofore paid to Eish, to be coming to him upon the contract, except the sum of $134.05 now in her hands, subject to the order of the court.

The case being brought to issue, was referred to the master in chancery to take proofs and report his conclusions. After hearing the testimony offered by the various parties the master reported that none of the complainants were entitled to a mechanic’s lien, but that the amount in the hands of Mrs. Hurtt (erroneously reported to be $185.99) should be distributed among the various creditors in proportion to the amount of their respective claims. Exceptions were filed to the master’s report by the various claimants. The court sustained certain exceptions to the master’s report and entered a decree finding that Thompson and Davies were not entitled to liens and decreed liens in favor of Sanders Bros. Mfg. Co. and W. L. Craig & Co. for $191.02 and $112.16, respectively. Mrs. Hurtt brings the case to this, court by appeal and assigns various errors; and Sanders Bros. Mfg. Co. and W. L. Craig & Co. assign cross-errors, alleging that larger sums should have been awarded to them respectively. We hold that the master correctly found that none of the parties were entitled to mechanics’ liens and that the action of the trial court in sustaining exceptions to such findings is erroneous.

Section 22 of the act of 1895 gives sub-contractors a lien. Section 25 permits the sub-contractor, at any time after making his contract with the contractor, and requires him, within sixty days after the completion thereof, to serve a written notice of his claim on the owner or his agent, etc. The claim, becomes a lien from the date of the service of such notice. By section 34 the four months within which he must commence his suit to enforce his sub-contractor’s lien is determined by the time when final payment is shown to be due by said notice. By section 25 such notice must state his claim, the amount due and to become due thereunder, and when it became or will become due. The form of notice prescribed by such section shows that the date when the payment became due or is to become due is to be stated.

The notice served by Sanders Bros. Mfg. Co. states that they furnished material under two contracts with Kish. It states the first contract was made on or about September 1, 1898, and that the other was made subsequently and that payment was to be made on delivery of the material. It does not state when the material was to be delivered nor that there was any fixed time when it should be delivered. It does not state when the payments were to be made. It states that there is now due from Kish a certain sum, but it does not say when it became due or when the material was delivered. It clearly does not comply with the statute.

The notice served by "W. L. Craig & Co. is still more defective. They notify the owner that they were employed by the contractor to furnish material for the building and have furnished material to a certain amount and that a certain portion thereof remains unpaid. They do not state whether this was furnished under one or many contracts and do not state when the money became due; nor whether it is due or not. The respective petitions of these parties set up these notices and expressly claim a lien by virtue thereof under the mechanics’ lien law of the State.

They argue no notice was necessary. Section 25 provides notice shall not be necessary where the sworn statement of the contractor provided for by section 5, or of the sub-contractor provided for by section 23, shall serve to «■ive the owner true notice of the amount due and to whom O due. Section 5 provides that a sworn statement from a contractor shall not be necessary if the contractor has given the owner a bond for the benefit of those having liens. In this case such a bond was given. It is argued section 25 should be construed as if it read also that notice should not be necessary by the sub-contractor to the owner if the bond had been given under section 5. We have no authority to read such provision into section 25, nor do we think anything of that kind is meant. The meaning is that if the sworn statement of the contractor gave the owner a true notice of the amount due and to whom due, it should be unnecessary for the sub-contractor to give notice to the owner merely to repeat those facts. But the giving of the bond did not convey to the owner any information as to the sub-contractors and the amounts due them. Decree reversed and remanded.

midpage