In a suit to enforce a mechanic’s or materialman’s lien, the first point made for appellees in support of the. decree appealed from is, that the suit was barred, not at the time it was originally brought, but at the time the bill was amended bringing in the principal contractor as a necessary defendant. That the principal contractor is a necessary party we decided in Augir v. Warder, 68 W. Va. 752, and the decree was reversed. But when the ease came up again, on the point here presented, we decided that such amendment does not prejudice the owner of the property, and that the suit is not barred because at the time of the amendment six months had then elapsed. So we overrule the point. Augir v. Warder, 74 W. Va. 103, 81 S. E. 708.
The next point we will notice is, that no itemized account, giving dates, &c., was filed with the owner within thirty five days from the completion of the contract, as required by section 3, chapter 75, serial section 3844, Code 1913. The argument advanced in support of this point is that as the account filed, at the heading, is dated April 30, 1906, and the first item is dated August 31, the year not being indicated opposite or above the item, it must be assumed that the days and months opposite the items in the account follow the dat
Another point is that the account filed includes items furnished within a period exceeding nine months from the date of the notice to the ovmer, contrary to section 3, chapter 75, of the Code. That section also says that failure to so notify him, as therein provided ‘ ‘ shall release the owner from all responsibility, and his property from all lien for any item therein done or furnished prior to the said, notice.” The items in this account, as shown, began August 31, 1905, and the last item for labor and material is dated May 31, 1906. Notice to
But the last point to be noticed, and the one most strongly urged in support of the decree, is, that the items of the account, cover two separate and distinct contracts, the first with Armentrout, as principal contractor, the other, beginning with the items charged as of May 21, 1906, furnished pursuant to a new contract made directly with the owner, and that the latter cannot be tacked to the former, to avoid the limitations of the statute, or extend the time for filing with the owner the notice required thereby. The authorities cited for the proposition are 27 Cyc. 144; Lane v. Jones, 79 Ala. 156, and Worthen v. Cleaveland, 129 Mass. 570. We do not think these authorities applicable to the facts in this case. They apply to cases where labor and material are actually furnished under separate and distinct contracts, and not to cases like this, where labor and material, though furnished at different times, are furnished under a continuous contract, the several parts constituting a complete whole, and done in execution of such contract. We had this exact point for decision in the recent case of Thorn v. Barringer, 73 W. Va. 618, 81 S. E. 846, and denied the application of the principle of those cases to the case then in hand. In that case the owner of the property made a contract with a materialman for material to construct a house. Pending its completion, and after much material had been furnished, the owner sold the property, the contract of sale providing for the completion of the house by him, and for some small addition to it. The pur
To this proposition we cannot give our approval. On May 14, 1906, the superintendent of the owner company under the new management wrote plaintiff: “Relative to plumbing, etc., in the J. A. McGuffin house of which you were speaking last week, we want this .work completed as originally intended. Please advise when you expect to begin work on it.” To this letter plaintiff replied: “Yours of the 14th inst at hand instructing us to complete the plumbing Etc. in the J. A. McGuffin house as originally intended. Will send our men there tomorrow after noon on No. 2.” To further give color to their theory of a new contract, counsel refer to the fact that the items in the account antedating May 21, were endorsed “O. K.” by Armentrout the contractor, but who did not so endorse the items subsequent to that date, for the reason given by Cole, president of the plaintiff company, that Armentrout could .only “O. K.” the account up to the time the Harvey Coal and Coke Company and others took charge of the work. There is also some evidence tending to show that after that time there were some changes in the price of the labor performed. We do not think these facts very material, or such as to change the character of the plaintiff’s contract, as a continuous one. In all that plaintiff did it was simply executing its original contract, which was to furnish all material and labor, do’the work and add to the cost ten per cent, for profit. Thorn v. Barringer, supra, practically decides that a contract so executed constitutes a continuous contract, entitling the contractor to a lien as under the original. We think this is the
We are, therefore, of opinion to reverse the decree and remand the cause for further proceedings to he had in accordance with the principles herein enumerated, and further according to the rules governing courts of equity.
Reversed and Remanded.