This suit wаs originally filed in 1960 by Huntington Corporation against Inwood Construction Company and Trinity Universal Insurance Company in which Huntington sought damages against Inwood Construction Company arising from a breach of a construction contract. Huntington alleged that Inwood did not perform its contract to provide paved parking areas at Texarkana, Texas and Marshall, Texas in accordance with plans and specifications set forth in the “cost plus” contract between the parties. Upon completion of the paving work Huntington paid Inwood the full consideration due under the contract in the amount of $52,383.86. Credits amounting tо $8,042.21 were allowed Inwood by agreement.
This is the third time this case has reached the appellate court. The first appeal was from an order sustaining a plea in abatement which was founded upon an arbitration agreement between the parties. That judgment was reversed by this court. Huntington Corporatiоn v. Inwood Construction Co., et al,
Upon remand the case was tried before a jury and judgment was rendered, based upon the verdict of the jury, in favor of Huntington. This judgment was appealed and submitted to the Texarkana Court of Civil Appeals. That court, in Inwood Construction Co. v. Huntington Corporation,
When the case returned to the trial court Huntington filed its fourth amended original petition in which it alleged a difference in market value between the shopping centers, as constructed and had they been constructed according tо the contract, in the amount of $60,000. The case was submitted to the trial court, without a jury, upon a stipulation that the trial court could consider the transcribed evidence adduced at the original trial, plus other evidence submitted to the trial court. At this second trial Huntington produced an expert witness, John Mugno, who tеstified that the difference in market value, as specified and as delivered, of the shopping center at Texarkana was $20,750. He opined that the difference in value of the Marshall project was $47,250.
The trial court made findings of fact and conclusions of law that (1) the thickness of the flexible base materiаl 'laid by Inwood at the Marshall site was substantially less than the six inches required by the contract; (2) that in at least a portion of the paved area at the Texarkana site neither the flexible base nor the asphaltic concrete, met the specifications of the contract. The court found that the sаmples taken were not sufficient to indicate how much of the paved area at Texarkana was affected by these defects; (3) that failures in the pavement occurred in a number of areas at both sites as early as July, 1960; (4) that some of these failures were the result of defects mentioned in findings (1) and (2) and others were the result of excessive subsurface moisture and excessive traffic by heavy trucks; (5) that Inwood’s performance did not amount to substantial performance of the contract at either site with reference to pavement of the parking areas; (6) that more than half of the paved area at each site was virtually intact after almost ten years of use and that there was no total failure of performance at either site; (7) that Inwood’s partial performance resulted in enhancement of the value of the property at both sites; (8) that Huntington is not entitled to recover the totаl cost of removing and replacing the pavement; (9) that Huntington is entitled to recover the difference between the market value of the shopping center with pavement as specified and the market value of the shopping center with pavement as installed by the defendant in July, 1960; (10) that no market data is available so that the only method of determining the difference in market value is the cost in July, 1960 of the work necessary to bring the pavement to a condition of as nearly as practical equivalent value in terms of serviceability, economy of maintenance and expected life, and if it cannot be made equivalent, then an allowance should be made for increased future maintenance cost discounted for payment and for shortness of expected life; (11) that under the evidence in this case a pavement of substantially equivalent value could have been accomplished in July, 1960 by exсavating and replacing the areas of total failure and applying over the whole area, at both sites, a one-inch overlay of asphaltic concrete. That this finding does not include the areas which were replaced by cement concrete as to which “I find that there was no substantial difference in value between the pavement as specified and the-pavement installed by defendant”; (12) that there is no evidence in the record upon which to determine the cost of the work necessary to bring the pavement to an equivalent value or is there any evidence of increased mаintenance cost or shortened expected life, if remedial work such as the above mentioned had been done. “The only testimony in the record concerning difference of value is that of John Mugno, who based his opinion on the assumption that there was potentially a total failure of the pаvement so that a prudent investor would have removed and replaced all the asphaltic concrete and flexible base. Since I do not find such a total failure, and since I find that a pavement of substantially equivalent value could have been accomplished without complete replacement, I cannot give *807 any weight to- Mr. Mugno’s opinion concerning the difference in value.” (13) That since there was no evidence in the record to establish the difference in value, other than total replacement cost, plaintiff has failed to prove his damages by a preponderance оf the evidence; (14) that plaintiff has established a breach of the contract, but has failed to prove the amount of damages; consequently, judgment is rendered for plaintiff for nominal damages only; (15) judgment is rendered for defendant on its counterclaim in the amount stipulated.
Based upon these findings and conclusions the trial court rendered judgment in favor of Huntington and against Inwood for the sum of $10.00 and judgment in favor of Inwood against Huntington in the sum of $8,042, the stipulated offsets.
In its first seven points appellant assails the trial court’s findings to the effect that there is no evidence to establish the difference in value and that appellant has failed to prove the amount of damages is contrary to the overwhelming weight and preponderance of the evidence. It also attacks the trial court’s award of $10.00 as nominal damages as being contrary to the overwhelming weight and preponderance of the evidence and manifestly too small.
In our judicial review of the “insufficient evidence” points here presented we are governed by well established rules which have been announced by our Supreme Court in In re King’s Estate,
In support of these points appellant places great reliance upon such cases as Southwest Battery Corp. v. Owen,
But this was not аll of the evidence tendered to the court on the question of measure of damages. By stipulation the parties agreed that all of the testimony which had been introduced in the first trial of the case could be considered by the court in the instant trial. This prior testimony, covering seven volumes of statement of facts, contains a great volume of data and information, both pro and con, which was available to the court in considering the answer to the question of the measure of damages. Even had the trial court accepted the testimony of Mugno the record presented is in direct conflict in that the witness Guisinger, an expert for appellees, testified that after applying the legally sanctioned approaches to estimating market value he concluded that there was no difference in market value of either the Texar-kana or Marshall sites. The court obviously gave considerable weight to this оpinion testimony.
It would unduly lengthen this opinion to enumerate the various factors related by the host of witnesses who testified in this case which might be considered by the trial court in estimating market value. We have concluded, based upon a review of the record, that it cannot be said that the finding of the trial court relative to the failure of appellant to establish its damages is contrary to the great weight and preponderance of the evidence.
We are also unable to agree with appellant’s contention that the award of $10.00 as nominal damages is manifestly too small. Appellant relies upon Rulе 328, Vernon’s Texas Rules of Civil Procedure, which provides that new trials may be granted when the damages are manifestly too small or too large. The basis of this rule is the cardinal principle of law that the injured party, when entitled to recover, shall have adequate compensation for the injuries suffered. Clark v. Spurdis,
In its Points 8, 9, 10, 11, 12, 13 and 14 appellant attacks the court’s various findings, Nos. 2, 4, 8, 9, 10, 11, 12, 13 and 14, as being contrary to the overwhelming weight and preponderance of the evidence. These findings enumerated above, have been carefully analyzed in the light of the record presented and we find that there is some evidence of probative value to sustain each one of them. While there is a conflict in the evidence, we cannot say that the findings are so contrary to the great weight and preponderance of the evidence as to be manifestly wrong.
Appellant’s comрlaint contained in its fifteenth point of error and directed to the trial court’s finding of fact No. 4 is likewise without merit and is overruled. This finding has to do with the fact that some of the defects in the paving construction were shown to have been the result of excessive subsurface moisture, which was. unanticipated by either pаrty to the contract, as well as by excessive traffic by heavy trucks. The record reveals that *809 these two causative factors were discovered or developed subsequent to the completion of the contract. It would serve no useful purpose to review the volume of evidence introduсed concerning these factors of causation. Neither do we think it necessary to do so for the simple reason that the finding under attack is not the determinative or controlling finding upon which the judgment is based. Again we emphasize that the crucial question in this case is whether appellant assumed its burden of prоving its damages which have been found to be the difference in market value of the project as constructed and its value had it been constructed in accordance with the contract. The trial court’s finding to the effect that appellant did not meet this burden is supported by the evidence.
We find no reversible error reflected in any of appellant’s points of error and they are accordingly overruled.
The judgment of the trial court is affirmed.
