218 Mass. 535 | Mass. | 1914
The plaintiff furnished material in the construction of a bath house which one Mack (doing business under the firm name of Mack and Moore) agreed to build for the city of Boston. Mack was adjudicated a bankrupt on June 6, 1911, and at that time owed the plaintiff $560.75. Subsequently this bill in equity was brought by the plaintiff to procure payment out of $13,351.98 retained by the city when it made to Mack monthly payments on account, and also from a surety company who gave a bond to the city conditioned that Mack should “faithfully furnish and do everything” required of him by the contract between him and the city. The plaintiff’s claim is that both the money retained and the bond given were obtained by the officers of the city in compliance with St. 1909, c. 514, § 23.
In spite of the terms of this order of reference (directing the master to find the facts which were put in issue by the pleadings) the master failed to pass upon the issue raised by the allegation of the city that it had been damaged by a failure on the part of Mack to perform his contract. We assume that the reason for this was a ruling which the master undertook to make (although he had no authority to make it under the order of reference in this case; see Clark v. Seagraves, 186 Mass. 430), to the effect that the city of Boston had no right in this suit to recoup the damages suffered by it in the premises. On the coming in of the master’s report the city filed a cross bill based upon these same damages, and on its motion the case "was recommitted to the master to find the damages suffered by the city. In a supplementary report the master found that the damages suffered by the city by reason of the failure of Mack to comply with the terms of his contract amounted to $4,750. A final decree
From this decree appeals were taken by the surety company and by the city of Boston.
1. We are of opinion that the bond given by the surety company was not given in compliance with St. 1909, c. 514, § 23, and that the surety company cannot be made liable to the plaintiff and the other materialmen.
The main argument on which the plaintiff bases his contention that the bond was given in compliance with the statute is that, by the terms of the contract between the city and Mack, Mack agreed, in case it was ascertained on the final settlement that he was indebted to the city, to pay to the city, within one month after the determination of the amount of it, the balance found to be due. But the terms of the bond are that Mack should “faithfully furnish and do everything therein required of” him. This would seem to mean “faithfully furnish the material and do the work required of him by the contract.” This interpretation of the condition of the bond is reinforced by the terms of Mack’s proposal to the city, which is a part of the contract between him and the city. It is there stated that the city is to pay Mack $64,650, as full payment for doing and completing the work, “including everything furnished or done, and every injury or loss sustained, by the contractor in carrying on the work.” The terms and conditions of the bond correspond to the terms of the proposal, which do not include payment of money by Mack to the city.
The provision made in the contract between Mack and the city for the retention of a portion of the monthly amount then apparently due to Mack, provides in terms that such sums should be deducted and retained {inter alla) “to settle claims for materials or labor furnished for carrying on the contract, notice of which claims, signed and sworn to by the claimants severally, shall have been filed” in the office of the defendant city or with its officers as specified in the contract. It is plain that this
It follows that so much of the decree as holds the defendant surety company liable and directs it to pay the costs to the plaintiff, was wrong.
2. We are also of opinion that so much of the decree was wrong as forbids the city of Boston to recoup its damages.
It is plain as matter of law and under the terms of the contract, that the monthly payments were mere payments on account subject to revision on the final settlement between the parties to the contract. The material portions of the contract are contained, in articles 6 and 7, set forth in full below in a note.
3. It has been suggested by the plaintiff since the argument that he and the other materialmen are entitled to a recovery against the surety company on the ground that the city of Boston
The form of the bill in this case is not to be taken as a precedent. The proper procedure in a case like the case at bar is for one of the materialmen to bring a bill in behalf of himself and all the others, and not for him to bring a bill in his own behalf making the other materialmen parties defendant.
It follows that, so far as the decree establishes the debts due to the plaintiff and to the other materialmen, it should be affirmed," but that it should be reversed (1) so far as it forbids the city’s recouping the damages suffered by it, (2) so far as it fixes the amount which the city is to pay over to the plaintiff and to the other materialmen, and (3) so far as it holds the defendant surety company liable in this suit and directs the surety company to pay to the plaintiff its eosts.-
The decree appealed from must be modified by providing that the city shall forthwith pay over to the plaintiff and to the other
So ordered.
The statute referred to is as follows: “Officers or agents who contract in behalf of any county, city or town for the construction or repair of public buildings or other public works shall obtain sufficient security, by bond or otherwise, for payment by the contractor and sub-contractors for labor per
Edward L. Logan, Esquire.
Made by Jenney, J.
“Article 6. The City by the Architects, after each month during which the Contractor shall have carried on the work prior to the month of completion thereof, shall estimate and allow the value of materials owned, and placed in permanent position on the work, by the Contractor, to the date of estimate and the value of labor done on the work by him [and] shall deduct, for the final settlement under the contract, such sum as the Officer shall direct, not exceeding fifteen per cent of the estimate — such other sum as the Officer shall direct not exceeding the total amount determined by the Architect to be the reasonable expense, loss and damage of the City caused by failure of the Contractor, as determined by the Architect, to conform to and carry out the provisions of the contract and shall deduct such and all sums paid for carrying on the contract, and shall deduct all sums paid for carrying on the contract, and shall deduct and retain until the Officer shall direct the payment thereof, such sum as the Officer shall direct as being required to settle claims for materials or labor furnished for carrying on the contract, notice of which claims, signed and sworn to by the claimants severally, shall have been filed in the office of the City Clerk, or with said Officer, and claims against the City, its agents or employees, relating to the contract. If the total of the sums to be allowed, as aforesaid, exceeds by more than $200 the total of the sum to be deducted, as aforesaid, the City, unless otherwise required by law, shall pay the balance to the Contractor within
“Article 7. The City, by the Architect, within 61 days after the work shall have been completed, in accordance with the contract, as determined by him, shall allow the contract sum of $64,650, and such sum as he shall determine to be the reasonable cost of extra labor furnished under orders and given as authorized in Article 2, plus 10 per cent of such cost, and the reasonable expense, injury or loss, caused by conforming to all other orders so made and given, or by anything for which, as determined by Architects, the City is liable and no other provision is made in this article, but no sum shall be allowed for loss or profits on work taken away; shall deduct and keep such sum as the Architect shall determine to be just for each day any work done for the City either by this contractor, as determined by the Architect, and such sum as he shall determine to be the expense, loss and damage of the City specified in the preceding Article, and the decrease in the total cost of the work caused, as he shall determine, by change or taking away of any part thereof; shall deduct all sums paid for carrying on the contract, and shall deduct and retain until the Officer shall request the payment thereof, such sum as he shall direct as being required to settle the claims specified in preceding Article. If the total of the sum to be allowed, exceeds the total of the sum to be deducted, the City, unless otherwise required by law, shall pay the balance to the Contractor within one month after the determination of the balance shall have been made by the Architect, and if the total of the sums to be deducted exceeds the total of the sum to be allowed, the contractor shall pay the balance to the City within on[e] month after the determination of the balance shall have been made by the Architect; any balance found as hereinbefore provided in this Article shall be deemed the final settlement under the contract.”