The issues in the present case center on the architect’s obligation under his contract
The controversy arises from the construction of a shopping center and office complex. Hunt-Stephens sued Ellisor & Tanner, in its capacity as structural engineer, the general contractor, various subcontractors and material suppliers, and the architects. By agreement Hunt-Stephens substituted Ellisor & Tanner for the original architects in performing certain duties of the architects. Thus, for the purposes of this opinion Ellisor & Tanner becomes the contractual architect on the project. We emphasize that Ellisor & Tanner's work as structural engineer is not at issue in this appeal. The general contractor joined additional subcontractors as third-party defendants. Before trial, Hunt-Stephens settled with all parties other than Ellisor & Tanner. Once the settlement occurred, the sole issues to be tried concerned whether Ellisor & Tanner negligently designed the parking deck and whether Ellisor & Tanner breached its contractual obligations contained in the below-quoted contractual provision. The jury found that the parking deck was not negligently designed, but that Ellisor & Tanner breached its contractual obligations in its substituted role as the architect. The parties agree that the negligence issue is now moot. The jury found that the defects in construction diminished the value of the project by the sum of $41,500.00 and that the general contractor caused ninety-five (95%) percent of these damages and that Ellisor & Tanner (as architects) caused five (5%) of these damages. Both parties filed motions for judgment notwithstanding the verdict. The trial court declined to grant either motion and rendered judgment against Ellisor & Tanner for $2,075.00, five (5%) percent of the damage award.
The general conditions contain paragraph 2.2.4 which is at the heart of the appeal. The first three sentences of the paragraph provide the contractual duties imposed on the architect upon which Hunt-Stephens relies. The reader, however, must note the fourth sentence of the paragraph. The fourth sentence includes the exculpatory language that Ellisor & Tanner insists relieves it of liability as argued under its counter-point. The critical paragraph reads:
The Architect will make periodic visits to the site to familiarize himself generally with the progress and quality of the Work and to determine in general if the Work is proceeding in accordance with the Contract Documents. On the basis of his on-site observations as an architect, he will keep the Owner informed of the progress of the Work, and will endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor. The Architect will not be required to make exhaustive on-site inspections to check the quality and quantity of the Work. The Architect will not be responsible for the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, and he will not be responsible for the contractor’s failure to carry out the Work in accordance with the Contract Documents.
(emphasis added).
At trial, Hunt-Stephens did not seek to impose liability upon Ellisor & Tanner for
The jury’s comparison produced a damage award as follows. Hunt-Stephens sought to recover the diminution in value of the shopping center and office complex. Hunt-Stephens argues that it proved a diminution in value after all remedial work by the general contractor had been completed of between $2,500,000.00 and $3,000,000.00. The remedial work occurred pursuant to the settlement agreement between Hunt-Stephens and the general contractor. Nevertheless, the jury found a diminution in value of $41,500.00. Applying the jury’s five (5%) percent fault assessment against Ellisor & Tanner, the trial court rendered judgment in favor of Hunt-Stephens in the amount of $2,075.00.
At this point, we outline the Hunt-Stephens settlement agreement with parties other than Ellisor & Tanner. In that settlement, Hunt-Stephens settled with parties other than Ellisor & Tanner for $1,200,000.00 and for the general contractor’s promise to remedy the structural defects in controversy. In addition, Hunt-Stephens assumed the defense of Ellisor & Tanner’s cross-actions and agreed to reduce its recovery against Ellisor & Tanner by any amount to which Ellisor & Tanner was found to be entitled against them. In return, those parties promised to keep their personnel available to Hunt-Stephens and agreed not to allow their expert witnesses to testify for Ellisor & Tanner.
Ellisor & Tanner’s Exculpatory Defense
In its sole cross-point, Ellisor & Tanner denies responsibility for the general contractor’s failure to carry out the work in accordance with the contract documents. Ellisor & Tanner makes two points in support of its denial.' First, Ellisor & Tanner notes that the jury found that the general contractor “produced work not of good quality, not free from faults and defects, and not in conformance with the contract documents.” Second, Ellisor & Tanner remarks on the fourth sentence in the above-quoted critical paragraph contained in the general conditions. For convenience, we repeat that language:
The Architect will not be responsible for the construction means, methods, techniques, sequences or procedures, or for the safety precautions and programs in connection with the Work, and he will not be responsible for the Contractor’s failure to carry out the Work in accordance with the Contract Documents.
(emphasis added). This language is paraphrased and reemphasized in another paragraph found in the general conditions:
The Architect will not be responsible for the acts or omissions of the Contractor, any Subcontractors, or any of their agents or employees, or any other persons performing any of the Work.
To establish its exculpatory defense, Ellisor & Tanner relies on
Moundsview Independent School District No. 621 v. Buetow & Associates,
We decline to follow Moundsview. We conclude that the language said to be exculpatory constitutes nothing other than an agreement that the architect is not the insurer or guarantor of the general contractor’s obligation to carry out the work in accordance with the contract documents. We reach this conclusion because the first three sentences of paragraph 2.2.4 of the general conditions impose a nonconstruction responsibility upon the architect; to wit: to visit, to familiarize, to determine, to inform and to endeavor to guard. In short, to provide information, not to make improvements upon the job site. Therefore, we reason that the fourth sentence of paragraph 2.2.4 and the paragraph paraphrasing it exist to emphasize the architect’s nonconstruction responsibility and to make certain that the architect “will not be responsible for the [general] contractor’s failure to carry out the work in accordance with the contract documents.” In short, the provider of information to the owner does not insure or guarantee the general contractor’s work. It follows, and we so hold, that the contract does not exculpate Ellisor & Tanner from liability for the general contractor’s failure to carry out the work in accordance with the contract documents. We overrule Ellisor & Tanner’s sole cross-point.
The Jury Comparison of the Architect’s Breach of Contract with the General Contractor’s Breach of Contract
Since the contract does not exculpate El-lisor & Tanner from liability to Hunt-Stephens, we reach Hunt-Stephens’ challenge to the trial court’s comparative fault submission, asking the jury to compare Ellisor & Tanner’s breach of contract to observe and to endeavor to guard as against the general contractor’s breach of contract to build in accordance with the contract documents. In its third point of error Hunt-Stephens contends that no evidence supported the submission of comparative causation to the jury and that such submission caused the rendition of an improper verdict and judgment. A reminder of the pertinent jury findings follows.
In answer to special issue number one the jury found that Ellisor & Tanner breached its duties to observe the progress of the work and to endeavor to guard Hunt-Stephens against defects in the work. In answer to special issue number two the jury found that Ellisor & Tanner’s breach was a producing cause of Hunt-Stephens’ damages. Over Hunt-Stephens’ objection to the submission, in answer to special issue number three the jury found that the general contractor’s work was not of good quality, was not free from faults and defects, and was not in conformance with the contract documents. Over Hunt-Stephens’ objection to the submission, the jury found in answer to special issue number four that the general contractor’s failure to produce quality work was the producing cause of Hunt-Stephens’ damages, if any. Over Hunt-Stephens’ objection to the submission, in answer to special issue number seven the jury found that the general contractor’s acts and omissions caused ninety-five (95%) percent of Hunt-Stephens’ injuries and that Ellisor & Tanner’s acts or omissions caused five (5%) percent of Hunt-Stephens’ injuries. Hunt-Stephens complains of the submission of special issue number seven as establishment of the doctrine of “comparative contract fault.” We note that neither party cites any Texas case which permits the jury to compare the general contractor’s breach of contract against the architect’s breach of contract and thereby determine what percentage of the injury is attributable to each breach.
Ellisor & Tanner maintains that (1) the principles enunciated in
Duncan v. Cessna,
An action for breach of warranty is held to sound sometimes in tort and sometimes in contract. There is no intent to include in the coverage of the Act actions that are fully contractual in their gravamen and in which the plaintiff is suing solely because he did not recover what he contracted to receive.
12 U.L.A. at 40. We conclude, therefore, that when the situation is pure contract, the special issues should not include comparative causation. See 5 A. Corbin, Corbin on Contracts §§ 999-1,000 (1964). Professor Corbin states in footnote 21 of section 999:
In the contract field, however, if the acts of others (whether wrongful or not) are contributing factors, those others are not thereby joined with the defendant as having committed the breach of the contract.
At most, Ellisor & Tanner argues that the general contractor “contributed” to Hunt-Stephens’ damages, but was not the “sole” cause. Professor Corbin would hold such a defendant responsible for the total harm suffered even though there were contributing factors to the defendant’s conduct. 5 Corbin on Contracts at § 999. Thus, we conclude that Hunt-Stephens is not required to show the proportionate fault of each wrongdoer, but must show that Elli-sor & Tanner’s breach was a substantial factor. Hunt-Stephens obtained such a finding from the jury in the present case when, in answer to special issue number two, the jury found that Ellisor & Tanner’s breach was a producing cause of Hunt-Stephens’ damages. Hence, we decline to extend Duncan to the present case.
Next, we consider Ellisor & Tanner’s argument that the contract between the parties requires the comparison and resulting reduction in the damage award. Ellisor & Tanner relies upon two writings. From the supplementary general conditions, Ellisor & Tanner points to paragraph 4.18.1 for the proposition that the general contractor agreed to hold harmless and indemnify Ellisor & Tanner from any and all damages, including the jury’s award of $41,500.00. The paragraph reads:
[General] Contractor shall agree and covenant to protect, defend, hold harmlessand indemnify [Hunt-Stephens], and his agents and employees and [Ellisor & Tanner], from and against any and all claims, actions, liabilities, losses and expenses relating to any and all losses or damages, (including, without limiting the foregoing, injury to or death of persons and damage to property) allegedly or actually suffered by any person or persons in allegedly or actually arising out of or incidental to the work, services, inactivities of [General] Contractor or any of its Subcontractors under this Contract, including without limiting the foregoing, all acts and omissions of the Officers, employees, and agents of [General] Contractor and its Subcontractors in connection with any installation, job or work under this Contract or while proceeding to or from the site of any such installation, job or work, whether or not lawful or within the scope of their employment.
From the Hunt-Stephens settlement agreement with the general contractors, Ellisor & Tanner refers to the language in which Hunt-Stephens agreed:
[T]o assume the defense of each of such settling Defendants in the course of [Hunt-Stephens’] continued prosecution of its claims and causes of action against [Ellisor & Tanner] ... in the trial and/or appeal of such case(s). [Hunt-Stephens] further agrees, for the consideration expressed herein, that in the event and to the extent that at the conclusion of the trial of such case(s), [Ellisor & Tanner] ... [is] found to be entitled to any contribution or indemnity from or against any one or more of the Settling Defendants, [Hunt-Stephens] shall reduce the amount of its recovery as against [Ellisor & Tanner] ... to eliminate and release that part of any award of damages as to which any such right of contribution or indemnity, if any, is found to exist, so that the final effect is that no claim for contribution or indemnity shall continue to exist in favor of [Ellisor & Tanner], ...
Ellisor & Tanner argues that these two provisions from separate contracts entitle Ellisor & Tanner to contractual indemnity from the general contractor and that the case was tried on that basis. Thus, Ellisor & Tanner asserts that the jury verdict was a jury verdict in favor pf Ellisor & Tanner and against the general contractor. Hence, Ellisor & Tanner insists that the jury’s verdict is the precise situation contemplated in Hunt-Stephens’ settlement agreement with the general contractor. Therefore, Ellisor & Tanner maintains that the jury’s verdict accomplished the result intended by the settlement agreement, which was to reduce Hunt-Stephens’ recovery against Ellisor & Tanner by the percentage of causation allocated to the general contractor. We disagree. Again we observe the separate and independent contract obligations to Hunt-Stephens of both the general contractor and Ellisor & Tanner. Each breached its obligations. Ellisor
&
Tanner breached its obligation to observe the progress of the work and to endeavor to guard Hunt-Stephens against defects in the work. The general contractor breached its obligation to do quality work in conformance with the contract documents free from faults and defects. Again, we note that Ellisor & Tanner’s obligation was non-construction; the general contractor’s obligation was construction. In this connection, we emphasize that paragraph 4.18.1 of the supplementary general conditions applies to damages arising from the general contractor’s construction work, not to damages arising from Ellisor & Tanner’s non-construction work. Consequently, we conclude that paragraph 4.18.1 fails to indemnify Ellisor & Tanner for the damages Hunt-Stephens claims to arise from Ellisor & Tanner’s breach of its obligation to observe the progress of the work and to endeavor to guard Hunt-Stephens against defects in the work. Indeed, to interpret paragraph 4.18.1 and the settlement agreement as Ellisor & Tanner would have us do produces an illogical result. Ellisor
&
Tanner’s interpretation allows Ellisor & Tanner to collect over $100,000.00 in fees for purporting to observe the progress of the work and for purporting to endeavor to
For the above reasons, we conclude that neither the principles enunciated in Duncan nor the contract between the parties dictate the comparison and resulting reduction in the damage award. We conclude further, therefore, that there was no evidence to support the submission of comparative causation to the jury and that such submission caused the rendition of an improper verdict and judgment. Consequently, the trial court erred in submitting comparative causation to the jury. We sustain Hunt-Stephens’ third point of error. Although we sustain Hunt-Stephens’ third point of error, we must address an issue raised by Ellisor & Tanner in its response to Hunt-Stephens’ third point of error. We turn now to that issue.
Anticipating that Duncan does not apply to permit the comparison and resulting reduction in the damage award, Ellisor & Tanner asserts that it should receive a credit against Hunt-Stephens’ judgment. Ellisor & Tanner reasons that Hunt-Stephens obtained a double recovery. In one instance, Hunt-Stephens recovered a $2,075.00 judgment. In the second, Hunt-Stephens received $1,200,000.00 in cash under the prior settlement and the repair of the defects in the construction. Thus, Elli-sor & Tanner insists that the credit it should receive erases the $2,075.00 judgment against it. We disagree. The trial court’s judgment for $2,075.00 or the $41,-500.00 judgment we render rests upon this issue:
What sum of money, if any, if paid now in cash will fully compensate [Hunt-Stephens] for any permanent diminution in market value of [the shopping center and office complex] which was caused by the acts or omissions of the defendants), despite the completion of all reasonable repair procedures?
(emphasis added). We treat the reference to “defendant(s)” as meaning Ellisor & Tanner since at trial it was the only defendant. Therefore, the jury compensated Hunt-Stephens only for the separate wrong done Hunt-Stephens by Ellisor & Tanner by the latter’s breach of “its duties to observe the progress of the work and to endeavor to guard [Hunt-Stephens] against defects in the work of the [general contractor].” On the other hand, the consideration Hunt-Stephens received under the prior settlement compensated Hunt-Stephens for acts and omissions of others, including the general contractor. Ellisor & Tanner was not a party to the settlement agreement. Therefore, the present case presents the situation where each wrongdoer pays separately for its own acts or omissions. Hence, we conclude that no double recovery occurs in the present case within the context of
Duncan,
Hunt-Stephens’ Challenge to the Evidence
The remaining issue arises from Hunt-Stephens’ challenge to the adequacy of the $41,500.00 jury damage award. Hunt-Stephens advances two points of error directed at the adequacy of the jury damage award. In its first point of error, Hunt-Stephens contends that the jury’s damage award of $41,500.00 was grossly inadequate and
[t]his is not a measure of damages case. [Ellisor & Tanner] did not appeal the measure of damages submitted by the District Court, and the resolution of this appeal does not turn on whether or not “diminution in value” is the proper measure of damages; instead, the question is whether the jury was free to be the sole judges of the credibility of [Hunt-Stephens’] expert witnesses on damages, and the weight to be given to their testimony.
Consequently, for the purposes of this opinion, we treat diminution in market value as the proper measure of damages.
Special issue number eight and the jury’s answer follow:
What sum of money, if any, if paid now in cash will fully compensate [Hunt-Stephens] for any permanent diminution in market value of [the shopping center and office complex] which was caused by the acts or omissions of [Ellisor & Tanner], despite the completion of all reasonable repair procedures? Answer in dollars and cents, if any.
ANSWER: $41,500
The question before us requires this court to consider and weigh all of the evidence in the case and to set aside the verdict and remand the cause for a new trial, if it thus concludes that the verdict is so against the great weight and preponderance of the evidence as to be manifestly unjust — this, regardless of whether the record contains some “evidence of probative force” in support of the verdict.
In re King’s Estate,
On the other hand, Ellisor & Tanner finds evidence in support of the jury’s finding resulting from its cross-examination of Halford. This cross-examination took into account the repairs of defects which the general contractor undertook pursuant to its settlement agreement with Hunt-Ste
In light of Halford’s testimony that some of the general contractor’s repairs would actually enhance -the market value and in light of the phrase contained in special issue number eight reading “despite the completion of all reasonable repair procedures,” we conclude that certain matters need now be addressed. We reach this conclusion because Hunt-Stephens’ theory of the case reduces the thrust of the phrase contained in special issue number eight reading, “despite the completion of all reasonable repair procedures.” Thus, we conclude that the phrase “despite the completion of all reasonable repair procedures” does not apply to negate the important consequences of Halford’s testimony that some of the repairs which the general contractor was performing actually would enhance the value of the shopping center and office complex. That the phrase does not apply becomes evident once the reader understands Hunt-Stephens’ position as to diminution of value in relation to repair procedures. Therefore, we note Hunt-Stephens’ position as to diminution of value in relation to repair procedures. We quote the first two paragraphs of Hunt-Stephens’ brief under its fact statement to its first point of error:
In understanding this point of error, a brief overview of HUNT-STEPHENS’ theory of damages will be helpful. As a result of the settlement with all other Defendants, many of the specific items for which specific remedial damages would have been sought were eliminated from the case. The case thus proceeded to trial on the question of whether or not [Ellisor & Tanner's] negligent design of the parking deck caused certain identifiable damages. Since the jury found no negligence in design, those items of damage are obviously irrelevant now. The case also proceeded to trial, however, on the theory that the pervasive misplacement of steel had caused a permanent diminution in value which would exist even after all remedial steps were taken. That permanent diminution in value is at the heart of this point of error,
(emphasis added). Thus, we read Hunt-Stephens’ brief to contend that in spite of
Considering and weighing all the evidence, we are unable to “state in what regard the contrary evidence greatly outweighs the evidence in support of the verdict.”
Pool v. Ford Motor Co.,
Disposition
Having sustained Hunt-Stephens’ third point of error, the comparison issue fails. Thus, we reverse the trial court’s judgment. When we reverse the trial court’s judgment, this court proceeds to render such judgment as the trial court should have rendered.
See
TEX.R.APP.P. 81(c). Having overruled Hunt-Stephens’ first and second points of error, the $41,500.00 jury damage award stands. Hence, we must render such judgment as the trial court should have rendered. Hunt-Stephens’ brief makes this alternative prayer for relief: “Alternatively, and only in the event the court finds the damage award was adequate but the comparative causation submission was error, Hunt-Stephens requests the court render judgment for $41,500.” We have found the judgment award adequate and the comparative causation submission error. Therefore, we grant Hunt-
Notes
. Computation of judgment rate by the consumer credit commissioner for month of July, 1986, 11 Tex.Reg. 3082 (1986), pursuant to TEX.REV. CIV.STAT.ANN. art. 5069-1.05, § 2 (Vernon Supp.1987). The contents of the Texas Register are to be judicially noticed and constitute prima facie evidence of the text of the documents published in the Register and of the fact that they are in effect on and after the date of the notation. TEX.REV.CIV.STAT.ANN. art. 6252-13a, § 4(c) (Vernon Supp.1987).
