Case Information
*1 Before KELLY , TYMKOVICH , and McHUGH , Circuit Judges.
This appeal arises out of the arbitration of a construction dispute between a subcontractor, Hungry Horse LLC, and a prime contractor, E Light Electric Services, Inc. (E Light). Hungry Horse claims the district court erred in denying its motion to vacate the arbitration award because the arbitration panel exceeded its authority. Exercising jurisdiction under 9 U.S.C. § 16(a)(3), we affirm.
BACKGROUND
E Light engaged Hungry Horse to perform subcontractor duties on two solar panel projects in New Mexico. Toward completion of the projects, a dispute arose between the two regarding the amount Hungry Horse was owed for work completed under the subcontract and for additional work. Hungry Horse filed mechanic’s liens against the projects, claiming it was owed approximately $2.8 million.
I. Mediation Proceedings
The parties first attempted to resolve their dispute through mediation. As part of that process, Hungry Horse and E Light each filed a written mediation statement, outlining their positions on the proper interpretation of the contract, the scope of the work performed, and the validity of the mechanic’s liens. Neither party raised any issues with respect to Hungry Horse’s contractor’s license in its written mediation statement. When the mediation failed, the parties stipulated to submit their dispute to binding arbitration.
II. Arbitration Proceedings
Hungry Horse and E Light entered into an arbitration agreement that provides:
Pursuant to the statements made at the settlement conference held January 25, 2012, this is to confirm the Stipulation reached in the above-captioned case upon the following terms: *3 1. The parties agree to binding arbitration of all disputed issues including the issues related to the Mechanics Lien and Bond . . . .
Aplt. App. 272. The parties further agreed the arbitration would be held in Colorado but governed by New Mexico law pursuant to the forum selection and choice of law provisions of their construction agreement.
To recover in a suit for compensation in New Mexico, a contractor must “alleg[e] and prov[e] that such contractor was a duly licensed contractor at the time the alleged cause of action arose.” N.M. Stat. § 60-13-30(A); see also id. § 60-13-30(B) (stating that any contractor operating without a required license “shall have no right to file or claim any mechanic’s lien”). Accordingly, Hungry Horse’s statement of claims filed with the arbitration panel included an allegation stating, “[Hungry Horse] is licensed to undertake the construction activities required by the expressed and implied agreement between the parties to this dispute.” Aplt. App. 147. In its initial answer to Hungry Horse’s statement of claims, E Light indicated it lacked sufficient information to confirm, and therefore denied, Hungry Horse’s allegation with respect to its license. It also asserted affirmative defenses that Hungry Horse “failed to fulfill all conditions precedent to its right to assert its mechanic’s liens” and that Hungry Horse’s “mechanic’s liens are invalid and unenforceable under applicable law.” Aplt. App. 161. After discovery, E Light filed a supplemental answer to Hungry *4 Horse’s statement of claims in which it asserted as an affirmative defense that Hungry Horse was not duly licensed (the duly licensed issue).
During the arbitration proceedings, E Light argued Hungry Horse did not have the correct license for the type of work performed and the license it did hold never should have been issued. In support of the latter claim, E Light relied on New Mexico’s requirement that no construction license be issued unless the director of the New Mexico Construction Industries Division of the Regulations and Licensing Department (Division) is satisfied that an applicant employs or is owned by a qualifying party. N.M. Stat. § 60-13-14(A); N.M. Admin. Code R. § 14.6.3.8. Under New Mexico law, a “qualifying party” is a licensed individual “who is responsible for the licensee’s compliance” with New Mexico construction “regulations, codes, and standards.” N.M. Stat. § 60-13-2(E).
In its license application, Hungry Horse had listed Mr. Stokes, a New Mexico contractor, as its qualifying party. Although Mr. Stokes and a company he owned had valid New Mexico contractor’s licenses, E Light claimed Mr. Stokes had no involvement in the solar projects and was neither an owner nor employee of Hungry Horse. At the arbitration hearing, E Light presented evidence that Hungry Horse had paid Mr. Stokes’s company $1,500 to use his name on Hungry Horse’s license application. E Light argued that under these facts, Hungry Horse was not duly licensed and could not recover on its compensation claims.
Hungry Horse objected to any inquiry by the arbitration panel into whether its construction license had been properly issued, arguing the panel was empowered to consider only whether the license covered the type of work performed. The arbitration panel disagreed and found Mr. Stokes had never been an owner or employee of Hungry Horse. Because Hungry Horse was not owned by and did not employ a qualifying party, the panel treated Hungry Horse as an unlicensed contractor and denied its claims for unpaid construction work. The panel did award Hungry Horse $350,000 for supplying materials to the solar panel projects, a task which did not require a license.
III. District Court Proceedings
Hungry Horse filed an action to vacate the arbitration award, alleging the arbitrators “exceeded their powers” in violation of the Federal Arbitration Act (FAA), 9 U.S.C. § 10(a)(4). Hungry Horse argued the Division had the exclusive jurisdiction to issue contractor licenses, thereby precluding the arbitration panel from considering whether Hungry Horse’s license had been properly issued. Hungry Horse also claimed the arbitration panel had revoked the license issued to Hungry Horse and that only the New Mexico Construction Industries Commission (Commission) had the power to do so.
The district court denied Hungry Horse’s motion to vacate, concluding the panel had acted within its broad authority. The district court explained the panel properly decided whether Hungry Horse was duly licensed as part of its *6 determination of whether Hungry Horse could recover additional compensation from E Light. It further found the panel did not revoke Hungry Horse’s license, but merely refused to treat Hungry Horse as duly licensed with respect to the work performed on the solar panel projects. Accordingly, the district court refused to vacate the arbitration award. Hungry Horse appeals.
DISCUSSION
When considering a district court’s decision on a motion to vacate an
arbitration award, we review the court’s conclusions of law de novo and its
findings of fact for clear error.
Bowen v. Amoco Pipeline Co.
,
Hungry Horse contends we should vacate the award under this narrow standard of review because, “the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.” 9 U.S.C. § 10(a)(4). [1] It claims the arbitration panel lacked authority to consider whether Hungry Horse’s license was properly issued and also exceeded its power by invading the exclusive jurisdiction of the Commission and revoking Hungry Horse’s license.
I. Arbitrability and Authority
In considering the limits of an arbitration panel’s power, we apply different
standards of review to questions of arbitrability than to questions of the extent of
the panel’s authority in deciding arbitrable issues.
See Burlington
, 636 F.3d at
*8
567–68. The Supreme Court has explained that the initial question of whether the
parties “agreed to arbitrate the merits” of their dispute is “about the
arbitrability
of the dispute,” which turns on the scope of the arbitration agreement.
See First
Options
,
Once the court determines that the parties agreed to submit an issue to
arbitration, we afford the arbitration panel “extreme deference” regarding the
extent of its authority to decide the arbitrable issue.
See Burlington
,
If an issue is arbitrable and the arbitration panel renders a decision on the
merits, the circumstances under which the award can be set aside as exceeding the
arbitrator’s powers are quite limited.
See Oxford Health Plans
,
II. Nature of this Dispute
A. Arbitrability: Scope of the Arbitration Agreement
Hungry Horse admits in its reply brief on appeal it “never contested the
authority of the Panel to determine if [it] was duly licensed,” and it “was required
to prove [it] was ‘duly licensed’” to recover on its claims for additional
compensation. Aplt. Reply Br. 12. Thus, there is no dispute the duly licensed
issue was arbitrable. Likewise, our independent analysis of whether the duly
licensed question falls within the scope of the parties’ arbitration agreement is
consistent with Hungry Horse’s concession.
See Burlington
,
Whether a dispute falls within the scope of an agreement’s arbitration
clause is determined by first “‘classify[ing] the particular clause as either broad
or narrow.’”
Cummings v. FedEx Ground Package Sys., Inc.
,
“To determine the breadth of an arbitration clause, we ask if the parties
clearly manifested an intent to narrowly limit arbitration to specific disputes that
might arise between them.”
Chelsea Family Pharm., PLLC v. Medco Health
Solutions, Inc.
,
Hungry Horse and E Light agreed to “binding arbitration of all disputed
issues including the issues related to the Mechanics Lien and Bond.” We agree
with E Light that this is a broad arbitration provision. It broadly refers to “all
disputed issues,” listing two specific examples, the mechanic’s lien and bond, but
does not expressly indicate that no issues other than those specifically identified
are subject to arbitration.
Cf. Burlington
,
Hungry Horse relies on the arbitration agreement’s inclusion of the phrase,
“[p]ursuant to the statements made at the settlement conference,” to argue the
issues submitted to the arbitration panel were limited to those discussed at
mediation. Aplt. Br. 17–18. We need not consider this argument because Hungry
Horse did not raise it until its reply brief below and the district court did not
address it.
See FDIC v. Noel
,
The introductory language of the arbitration clause indicates only that the
parties reached an agreement at the settlement conference to arbitrate; the issues
they agreed to arbitrate are identified in the plain language that follows.
See First
Options
,
As discussed, in New Mexico, a contractor may not recover on a compensation claim unless it proves it was duly licensed at the time the work was performed. See N.M. Stat. § 60-13-30(A). During the arbitration proceedings, E Light disputed Hungry Horse’s claim it was duly licensed and placed that issue squarely before the panel. Thus, the duly licensed issue is a disputed issue and “on its face within the purview of the [arbitration] clause.” Cummings , 404 F.3d at 1261 (internal quotation marks omitted).
Even if the duly licensed issue were collateral, it would be arbitrable.
Given the broad language of the arbitration clause, we presume collateral matters
implicating issues of contract construction or the parties’ rights and obligations
under the subcontract fall within the scope of the arbitration agreement.
Burlington
,
Whether we resolve the arbitrability question based on Hungry Horse’s concession or by construction of the arbitration agreement’s broad arbitration provision, we reach the conclusion the duly licensed issue was arbitrable.
B.
Authority: Scope of the Arbitration Panel’s Inquiry
In characterizing the issue on appeal, Hungry Horse states the parties have
a “fundamental disagreement as to what one must prove to meet its burden of
establishing the contractor is ‘duly licensed.’” Aplt. Reply Br. 12. Accordingly,
the issue before us is whether the arbitration panel had the authority to consider
the circumstances under which Hungry Horse obtained its license in determining
whether it was duly licensed when it performed work on the solar panel projects.
Although Hungry Horse frames this dispute as a question of arbitrability, we are
convinced it is a question of the proper extent of the panel’s authority to decide
the “duly licensed” issue Hungry Horse admits was submitted to arbitration.
See
Burlington
,
For example, in Burlington , the Public Service Company of Oklahoma (PSO) and Burlington Northern and Santa Fe Railway Company (BNSF) disagreed on the proper interpretation of the rate provisions governing the amount due to BNSF under a coal transportation agreement. PSO calculated the rate using an amended rate adjustment procedure agreed to in connection with the resolution of a prior dispute. Id. at 566. BNSF sought a higher amount based on a “rate floor” of $11.77 per ton included in the pre-amendment agreement. Id. Eventually, the parties asked an arbitration board to adjudicate: 1) BNSF’s claim the rate could not be less than $11.77 per ton; and 2) all of PSO’s defenses to BNSF’s claim. The arbitration agreement further provided the arbitration board “shall not consider any [other] claims by BNSF and PSO.” See id. The arbitration board issued an award holding the rate floor in the pre-amendment agreement had been extinguished when the parties adopted the amended rate adjustment procedure. Id. at 566–67. BNSF brought a motion to vacate the award in the district court, claiming the arbitration board had exceeded its powers by interpreting the rate floor provision of the prior contract. Id. at 567. The district court denied the motion to vacate. Id.
This court affirmed. We first rejected BNSF’s attempt to characterize the question on appeal as one of arbitrability. Id. at 568. Because BNSF’s claims and *16 PSO’s defenses were arbitrable, we held, “the board’s determination that it had the authority to declare no rate floor provision existed is entitled to the same ‘extreme deference’ as its determinations on the merits.” Id. ; see also id. at 569 (“After the district court independently concluded the parties’ rate dispute was arbitrable, it correctly applied a deferential standard of review to the board’s determination of the scope of its authority.”).
The same level of deference is appropriate here. The parties agree the duly licensed issue was arbitrable. Thus, the arbitration panel’s implicit “determination that it had the authority to declare” no license should have been issued to Hungry Horse is entitled to “extreme deference.” See id. at 568. Under that standard, we cannot say the panel exceeded its powers by considering the circumstances under which Hungry Horse obtained its contractor’s license.
C. Correctness of the Arbitration Panel’s Decision Finally, Hungry Horse argues the arbitration panel exceeded its powers because the Division and the Commission have exclusive jurisdiction to issue licenses in the first instance and to review or revoke licensing decisions. Aplt. Br. 19–20 (citing N.M. Stat. §§ 60-13-12, -14, -15, -30). In particular, Hungry Horse claims the arbitration panel’s decision is contrary to New Mexico’s statutory scheme and the legal decisions addressing the duly licensed requirement in the context of contractor claims. This challenge is appropriately considered an attack *17 on the merits of the arbitration panel’s decision that Hungry Horse was not duly licensed when it performed the work on the solar projects.
In such circumstances, Hungry Horse “bears a heavy burden” in seeking
relief under section 10(a)(4) of the FAA.
See Oxford Health Plans
,
CONCLUSION
Because the duly licensed issue was arbitrable, we afford extreme deference to the panel’s determination of the proper extent of the inquiry necessary to decide that question and to its decision on the merits. Hungry Horse has not demonstrated that the district court erred in refusing to vacate the arbitration award.
AFFIRMED.
ENTERED FOR THE COURT Carolyn B. McHugh Circuit Judge
Notes
[*] This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. The court generally disfavors the citation of orders and judgments; nevertheless, an order and judgment may be cited under the terms and conditions of 10th Cir. R. 32.1.
[1] Section 10 of the FAA allows an arbitration award to be vacated if: (1) “the award was procured by corruption, fraud, or undue means”; (2) “there was evident partiality or corruption in the arbitrators”; (3) the “arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced”; or (4) “the arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final, and definite award upon the subject matter submitted was not made.” 9 U.S.C. § 10(a). Hungry Horse relies only on subsection 10(a)(4).
[2] Because we adopted our scope-of-agreement test from the Second Circuit,
see Cummings v. FedEx Ground Package System, Inc.
,
