98 Kan. 634 | Kan. | 1916
The opinion of the court was delivered by
George W. Humphrey brought this action against M. E. Flaherty, to recover a balance due under a written contract by which the plaintiff was to receive $2500 for remodeling and constructing a house for the defendant and he recovered a judgment for $361.64 from which the defendant appeals.
In the contract, February 1, 1912, was named as the time for completing the building, and it was provided that the plaintiff should forfeit $5 per day for any delay in the com-pletion after that date. It was also provided that payments should be due when certificates of the architect were issued. In his appeal the defendant insists that the trial court erred in not making any allowance for plaintiff’s delay in the completion of the house, and he further insists that the plaintiff was not entitled to judgment because the work was not done according to the contract and certificates had not been given
As to the question that no action would lie because the architect’s certificates had not been issued, it is the contention of the plaintiff that this provision of the contract has also been waived. The contract was for the rebuilding and extension of an old house, and while the contract was in the form ordinarily used by builders in new construction where an architect is employed to supervise the construction, it is in testimony that the parties never contemplated that the architect who made the plans should make estimates or issue certificates. The architect called once shortly after the work was begun and looked at the building, but the defendant did not ask him to certify what was due under the contract. On the contrary, the defendant made payments to the plaintiff from time to time without mention of estimates or certificates. Aside from the cursory look made by the architect a short time
Testimony was introduced to the effect that a small part of the work was imperfectly done, and upon this evidence the court in awarding judgment for the plaintiff credited the defendant with the sum of ten dollars. Under the circumstances the allowance of the credit can not be regarded as a finding that the contract had not been substantially performed by the plaintiff.
The judgment is affirmed.