Case Information
*1
[Cite as
Hulett v. Ohio Dept. of Transp.
,
Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us JUDITH L. HULETT
Plaintiff
v.
OHIO DEPARTMENT OF TRANSPORTATION
Defendant
Case No. 2010-04165-AD
Deputy Clerk Daniel R. Borchert
MEMORANDUM DECISION
Plaintiff, Judith L. Hulett, filed this action against defendant, Department of
Transportation (ODOT), contending her 2007 Pontiac G6 was damaged as a proximate cause of negligence on the part of ODOT in maintaining a hazardous condition on the entrance ramp to Interstate 75 from State Route 63 in Warren County. Plaintiff related she was traveling on the Interstate 75 North entrance ramp when her automobile “hit (a) pot hole at (the) bottom of (the) ramp” causing tire and wheel damage to the vehicle. Plaintiff recalled the described incident occurred on February 18, 2010 at approximately 7:00 a.m. Plaintiff requested damage recovery in the amount of $1,345.60, the stated total cost of a tire and two replacement rims. The filing fee was paid. Defendant acknowledged the roadway area where plaintiff’s incident
occurred was within the limits of a working construction project under the control of ODOT contractor, John R. Jurgensen Company (Jurgensen). Defendant explained the particular construction project “dealt with widening I-75 between Cincinnati-Dayton Road and SR 122 in Butler and Warren Counties.” According to defendant, the construction project limits “corresponds (to) state mileposts 21.0 to 32.0” on Interstate *2 75 and plaintiff’s damage incident occurred at milepost 29.12, a location within the construction area limits. Defendant asserted that this particular construction project was under the control of Jurgensen and consequently ODOT had no responsibility for any damage or mishap on the roadway within the construction project limits. Defendant argued that Jurgensen, by contractual agreement, was responsible for maintaining the roadway within the construction zone. Therefore, ODOT contended that Jurgensen is the proper party defendant in this action. Defendant implied that all duties such as the duty to inspect, the duty to warn, the duty to maintain, and the duty to repair defects were delegated when an independent contractor takes control over a particular section of roadway. Furthermore, defendant contended that plaintiff failed to introduce sufficient evidence to prove her damage was proximately caused by roadway conditions created by ODOT or its contractors. All construction work was to be performed in accordance with ODOT requirements and specifications and subject to ODOT approval. Also evidence has been submitted to establish that ODOT personnel were present on site conducting inspection activities. For plaintiff to prevail on a claim of negligence, she must prove, by a
preponderance of the evidence, that defendant owed her a duty, that it breached that
duty, and that the breach proximately caused her injuries.
Armstrong v. Best Buy
Company, Inc.,
99 Ohio St. 3d 79,
condition for the motoring public.
Knickel v. Ohio Department of Transportation
(1976),
*3
{¶ 5} Alternatively, defendant denied that neither ODOT nor Jurgensen had any notice of the particular pothole prior to plaintiff’s property damage event. Defendant pointed out that ODOT records “indicate that no calls or complaints were received regarding a pothole prior to Plaintiff Hulett’s incident.” Defendant advised, “[i]t should be noted that this portion of I-75 has an average daily traffic volume between 73,320 and 93,130, however, no other complaints were received (regarding a roadway defect) prior to plaintiff’s alleged incident.” Defendant contended plaintiff failed to offer any evidence of negligent roadway maintenance on the part of ODOT and failed to produce evidence to establish her property damage was attributable to conduct on either the part of ODOT or Jurgensen. Defendant denied receiving any complaints before February 18, 2010 regarding a pothole on the Interstate 75 entrance ramp at approximate milepost 29.12. Defendant submitted a letter from Jurgensen Project Manager, Kate Holden, who recorded she was notified of a pothole “at the end of the ramp from SR 63 to northbound I-75” on February 23, 2010 by an e-mail from Jurgensen Project Engineer, Mark Wilson, According to Holden, this pothole on the Interstate 75 entrance ramp was repaired on February 24, 2010. In order to find liability for a damage claim occurring in a construction
area, the court must look at the totality of the circumstances to determine whether
ODOT acted in a manner to render the highway free from an unreasonable risk of harm
for the traveling public.
Feichtner v. Ohio Dept. of Transp.
(1995), 114 Ohio App. 3d
*4
346, 683 N.E. 2d 112. In fact, the duty to render the highway free from an
unreasonable risk of harm is the precise duty owed by ODOT to the traveling public
under both normal traffic and during highway construction projects. See e.g.
White v.
Ohio Dept. of Transp.
(1990),
{¶ 8}
In order to prove a breach of the duty to maintain the highways, plaintiff
must prove, by a preponderance of the evidence, that defendant had actual or
constructive notice of the precise condition or defect alleged to have caused the
accident.
McClellan v. ODOT
(1986), 34 Ohio App. 3d 247, 517 N.E. 2d 1388.
Defendant is only liable for roadway conditions of which it has notice but fails to
reasonably correct.
Bussard v. Dept. of Transp.
(1986), 31 Ohio Misc. 2d 1, 31 OBR
64,
{¶ 9} Generally, in order to recover in a suit involving damage proximately caused by roadway conditions including potholes, plaintiff must prove that either: 1) defendant had actual or constructive notice of the pothole and failed to respond in a reasonable time or responded in a negligent manner, or 2) that defendant, in a general sense, maintains its highways negligently. Denis v. Department of Transportation (1976), 75-0287-AD. There is no evidence that defendant had actual notice of the pothole condition. Therefore, in order to recover plaintiff must produce evidence to prove constructive notice of the defect or negligent maintenance.
{¶ 10}
“[C]onstructive notice is that which the law regards as sufficient to give
notice and is regarded as a substitute for actual notice or knowledge.”
In re Estate of
Fahle
(1950),
constructive notice, unless evidence is presented in respect to the time the defective
condition developed.
Spires v. Ohio Highway Department
(1988), 61 Ohio Misc. 2d
262,
time has elapsed after the dangerous condition appears, so that under the circumstances defendant should have acquired knowledge of its existence. Guiher v. *5 Dept. of Transportation (1978), 78-0126-AD. Size of the defect is insufficient to show notice or duration of existence. O’Neil v. Department of Transportation (1988), 61 Ohio Misc. 2d 287, 587 N.E. 2d 891. “Obviously, the requisite length of time sufficient to constitute constructive notice varies with each specific situation.” Danko v. Ohio Dept. of Transp. (Feb. 4, 1993), Franklin App. 92AP-1183. No evidence has shown ODOT had constructive notice of the pothole. Plaintiff has not produced any evidence to infer that defendant, in a
general sense, maintains its highways negligently or that defendant’s acts caused the
defective condition.
Herlihy v. Ohio Department of Transportation
(1999), 99-07011-AD.
Plaintiff has failed to prove that her damage was proximately caused by any negligent
act or omission on the part of ODOT or its agents. See
Wachs v. Dept. of Transp., Dist.
12
, Ct. of Cl. No. 2005-09481-AD,
Court of Claims of Ohio
The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us JUDITH L. HULETT
Plaintiff
v.
OHIO DEPARTMENT OF TRANSPORTATION
Defendant
Case No. 2010-04165-AD
Deputy Clerk Daniel R. Borchert
ENTRY OF ADMINISTRATIVE DETERMINATION
*6 Having considered all the evidence in the claim file and, for the reasons set forth in the memorandum decision filed concurrently herewith, judgment is rendered in favor of defendant. Court costs are assessed against plaintiff.
________________________________ DANIEL R. BORCHERT Deputy Clerk Entry cc:
Judith L. Hulett Jolene M. Molitoris, Director 1377 Lakeshore Drive Department of Transportation Monroe, Ohio 45050 1980 West Broad Street
Columbus, Ohio 43223 RDK/laa 8/10 Filed 9/15/10
Sent to S.C. reporter 12/29/10
