75 A.D.2d 464 | N.Y. App. Div. | 1980
OPINION OF THE COURT
For reasons stated herein we conclude that the trial court erred in denying the State’s motion for permission to serve a counterclaim and thereafter in refusing to permit the State to introduce evidence tending to show that much of claimant’s claim for extra work was performed only to cure design defects which were its own responsibility and not recoverable under its contract with the State; that the court also erred in construing the stated ultimate cost or ceiling price in the contract to be merely an estimate of total compensation; and that absent additional proof, claimant’s recovery in any event cannot exceed such stated amount, and so it cannot exceed the sum of $9,783.90.
In March, 1966 claimant contracted with the State to provide architectural services in the design and construction of a State office building in the City of Utica. This contract was supplemented by four agreements as the work progressed. The original contract specified many duties for claimant to perform, primarily design work. The second supplement added to such list and also required claimant to supervise construction. In the original contract and in each of the supplements a ceiling price was specified, limiting the total amount which claimant might recover for its services. Prior to the fourth
In July, 1975 claimant filed notice of claim for a total additional amount of $50,786.87, much of which was based upon time that it spent preparing to resist the claims against the State by contractors Green and Rouse, founded upon alleged design errors. The State did not answer the claim. At that time claims against the State were deemed denied without answer (see former 22 NYCRR 1200.14), but if the State wished to file a counterclaim, it had 20 days in which to do so (see former 22 NYCRR 1200.15). In November, 1975 the State moved for joint trial of claimant’s claim along with the claims by Green and Rouse, and it also moved for permission to file a counterclaim against claimant for damages in the sum of $1,500,000 by reason of claimant’s negligence and breach of contract. The court granted the motion for joint trial but denied the State permission to file the counterclaim.
Following such denial, the State instituted an action against claimant in the Supreme Court for its damages by reason of claimant’s alleged negligence and breach of contract. In 1977 the State renewed its motion to interpose its counterclaim, but the court again denied the motion, noting that the State had its action thereon pending in the Supreme Court; and it specified its reasons for not permitting, in effect, a transfer of the State’s action to the Court of Claims (cf. Forest-Fehlhaber v State of New York, 74 AD2d 272, approving a Supreme Court order transferring from it to the Court of Claims an
At trial in 1978 the court refused to permit the State to raise as a defense its assertion that since the claim was based on services necessitated by claimant’s own design errors, they were not compensable under the contract, and it refused to permit the State to submit evidence thereon in diminution of claimant’s claim. The court so ruled because it found that the contract was divisible, and that defects in the design phase could not bar recovery for services performed in the construction phase (see 10 NY Jur, Contracts, §§ 255, 337).
The court erred in applying the principle of a divisible contract in this case; for it is not the State’s position that claimant’s breach of the design phase would excuse the State’s performance of the construction phase. Rather, the State contends that the contract provides no compensation for claimant for time spent in correcting its own mistakes and hence that the claim is not within the scope either of the original contract or contract supplement II. Since the State’s defense is not grounded on the principle that damages may not be recovered by one who himself has not fully performed, the concept of divisibility is irrelevant. Thus, the court erred in excluding the State’s offer of proof of claimant’s design errors. For the same reason the court erred in denying the State’s late motion for permission to interpose its counterclaim for damages for claimant’s alleged breach of contract and for negligent design (see Fehlhaber Corp. & Horn Constr. Co. v State of New York, 69 AD2d 362, 374). It is clear that the State instituted its action in the Supreme Court because the court denied its motion to file the counterclaim; and the existence of that action should not have been used at the trial to bar the State’s defense against that claim. In addition, permitting filing of the counterclaim will result in judicial economy, because the issue of design error must be reached in resolving the main claim.
Moreover, we cannot agree that claimant may receive total compensation under the contract in an amount in excess of the $504,000 stated in contract supplement IV. The contract and the first three supplements thereto are clear and unambiguous on this point, because each states that the ceiling amount may be increased, but only by supplemental agreement. The last supplement omits this sentence, but any ambiguity resulting thereby must be construed against the
We also disagree that the record supports a finding that the State is estopped from relying on the contract ceiling price. Although the doctrine of equitable estoppel may be applied against the State (see Bender v New York City Health & Hosps. Corp., 38 NY2d 662, 668; Matter of 1555 Boston Rd. Corp. v Finance Administrator of City of N. Y., 61 AD2d 187, 192; cf. Eden v Board of Trustees of State Univ. of N. Y., 49 AD2d 277, 283-284), it will not be applied without a showing that the defendant concealed facts from claimant or made a false representation to it and that claimant relied thereon (Triple Cities Constr. Co. v Maryland Cas. Co., 4 NY2d 443, 448; Special Event Entertainment v Rockefeller Center, 458 F Supp 72, 76, and cases cited; 21 NY Jur, Estoppel, § 21). There has been no showing in this case that the State concealed facts from claimant or made any misrepresentation of fact to it upon which claimant relied to its detriment. The State’s prior conduct in raising the ceiling amount cannot be viewed as misleading in light of the State’s February, 1972 letter which very clearly put claimant on notice that no further increase would be forthcoming. Claimant cannot claim estoppel "merely because he thought, through some 'secret operation of his own mind’” (see Wood v State of New York, 12 NY2d 25, 28), that the State would waive the contract limit.
The judgment should, therefore, be reversed and a new trial granted in accordance herewith.
Dillon, P. J., Cardamons, Doerr and Moule, JJ., concur.
Judgment unanimously reversed, on the law and facts, without costs, and a new trial granted.