OPINION
This is аn appeal from a judgment ordering specific performance of a real estate option agreement, awarding attorney’s fees and granting incidental relief. Trial was to the court without a jury.
We affirm the judgment of the trial court.
On January 30, 1981, the parties entered into an option agreement wherein apрellant granted appellee the option to purchase approximately three acres of land fronting on Highway 624 in what is known as the Five Points area of Nueces County, Texas. The tract subject to the option agreement is a portion of a ten acre tract owned by appellant. Appellee was interested in acquiring the site as a home of a new banking facility with which he was connected. Appellant planned to develop the remaining seven acres of the ten acre tract.
Appellee exercised the option within the time specified and, while the agreement called for the closing to take place within thirty days of the date of exercising the option, this provision was waived by the parties and they agreed that the closing should take place within a reasonable time.
In order to close the transaction and deliver good and marketable title to the property, it was necessary to re-plat the three acres. To accomplish the re-platting, the city of Corpus Christi required a plan for developing the entire ten acres owned by appellant. The city’s requirements included a park dedication, voluntary annexation and a drainage plan. An additional problem arose when an easement was discovered that interfered with a provision in the option contract to build a road over the property which would connect appellant’s remaining property with the highway.
George T. Morse, III, an attorney representing appellee, prepared the option agreement and consulted with appellant in attempting to solve the problems raised by the city’s requirements and the easement.
The firm of Urban Engineering wаs hired in January, 1982 to accomplish the re-platting. A major stumbling block was the drainage plan. Various alternatives were presented to appellant to meet the city’s requirements. The only method of solving the drainage problem which was acceptable to appellant involved obtaining a voluntary agreement with the owners of adjoining property. Appellant hired Naismith Engineering to pursue the voluntary landowners’ agreement. When Naismith was hired Urban was discharged. The evidence is conflicting concerning the reason for discharging Urban. Apparently, appel-lee believed the entire re-platting was to be taken over by Naismith, while appellant’s position was that Naismith’s work was to supplement that being done by Urban. While Naismith attempted to obtain the adjoining landowners’ consent to the proposed drainage plan, appellee, through
The parties remained in contact with each other, and on December 20, 1983, a proposal to satisfy the city’s requirements was submitted to appellant. At that time appellee was ready, willing and able to close the sale. Appellant failed to execute the proposal submitted on December 20, 1983. This suit resulted.
Appellant presents seventeen points of error for review. Point of errоr eleven charges error in the awarding of attorney’s fees. The other sixteen points of error attack the trial court’s action in granting specific performance, claiming that this is not a proper case for such action, that the trial court abused its discretion in granting such reliеf, that appellee was estopped from obtaining specific performance, that there was no evidence or insufficient evidence to justify each of the disputed findings of fact and conclusions of law and that such findings and conclusions were against the great weight and preponderance of the evidence.
In points of error twelve through seventeen, appellant complains that the trial court’s findings of fact were based on no evidence, or, alternatively, insufficient evidence, or that they were against the great weight and prepondеrance of the evidence. In considering a “no evidence” or “insufficient evidence” point of error, we will follow the well established test set forth in
Glover v. Texas General Indemnity Company,
Furthermore, we overrule appellant’s “insufficient evidence” and “against the great weight and preponderance” points. Although the facts in this case are vigоrously contested, the trial court, as the finder of fact, had the duty to assess the credibility of the witnesses. The court could accept all, part, or none of the testimony, or make its own deduction from all the evidence.
Hendershot v. Amarillo National Bank,
In points of error one through six and in point ten, appellant attacks the propriety of the granting of specific performance by the trial court. Appellant challenges the equitable relief as both an abuse of discretion and an error of law, alleging that appellee failed to meet his obligations under the contract. Specifically, appellant alleges that appellee failed to close within a reasonable period and failed to make a valid tender of the purchase price. Appellant further alleges that appellee failed to establish that he had no adequate remedy at law, so specific performanсe is error.
The trial court found that the appellant “failed to make the decisions in reference to re-platting which were uniquely his to make, and in effect, made himself una
Carter v. Gerald,
In a suit for specific performance, the buyer need only allege he is ready, willing, and ablе to pay.
Burford v. Pounders,
The plaintiff pled, and the trial court found, that appellee “was and is ready, willing, and able to pay the purchase price upon receipt of the copy of the sufficient warranty deed which was to have been submitted by W.R. Hubler, Sr., to Joseph Oshman’s counsel ten days before closing.”
Before appellant sent his letter purporting to cancel, appelleе was not obligated to tender because he had not yet received the copy of the warranty deed. Appellant’s attempt to cancel in January 1983 and refusal to execute the re-plat proposal in December 1983 showed his repudiation of the contract, so that appellant was relieved of his obligation to tender to appel-lee. Using Burford as a model, appellee paid the balance of the purchase price into the registry of the court, which then issued its judgment.
Appellant’s complaint that specific performance should not have been, granted because appellant failed to show he had not adequate remedy at law is also without validity.
There was no evidence showing the contract itself objectionable in any fashion. It is as much a matter of course for a court to decree sрecific performance of a contract to sell real estate as it is to give damages for its breach.
Bennett v. Copeland,
149. Tex. 474,
We hold that the trial court did not abuse its discretion in ordering specific performance in this case. Points of error one through six and ten are overruled.
The judgment enterеd by the trial court in this case recites “that Plaintiff’s prayer for specific performance be granted.” It further orders that fee simple title to the property in dispute be vested in appellee and divested from appellant; that $232,-850.00, the balance of the purchase pricе, which had been deposited in the registry of the court, be paid to appellant; that appel-lee be solely responsible for re-platting the subject property; and that certain easements described in the judgment and contemplated by the option agreement be dеdi
In points of error seven and eight, appellant complains that the trial court’s judgment should be set aside because it failed to require performance on the part of ap-pellee of conditions and obligations imposed upon him and it would require long and continuous supervision of the parties by the court.
Certainly, the court has no power to decree specific performance in any manner except in keeping with the terms of the agreement made by the partiеs.
Brantly v. Etter,
Appellant urges waiver and estoppel in point nine. The court found that Oshman “proceeded with diligence and good faith to enable the sale of the property to close” and that he “was and is ready, willing, and able to pay,” while it was Hubler who failed to perform. As stated previously, these findings are supported by the evidence. Therefore appellant’s complaints have no basis in the facts. Point of error nine is overruled.
Appellant’s eleventh point complains of the award of attorney’s fees to appellee because оf the pleadings. Appel-lee dictated an amendment into the record at trial to request attorney’s fees. The allowance of trial amendments is within the discretion of the trial court, and TEX.R. CIV.P. 66 directs the court to freely allow trial amendment when the presentation of the merits will be subserved thereby and the objecting party fails to satisfy the court that the allowance of such amendment would prejudice his defense on the merits. TEX.R.CIV.P. 45 requires that pleadings in a district court be “in writing, signed by the party or his attorney, and be filed with the clerk.” It has been held that where an attorney for the plaintiff personally dictated an amendment into the record, he left no doubt as to the party responsible for what was dictated and that he appeared for the plaintiff, so the amendment was proper.
Missouri-Kansas-Texas Railroad Company v. Gage,
The judgment of the trial court is AFFIRMED.