The plaintiffs brought this action in contract and tort against the defendant Melrose-Wakefield Hospital Association (the hospital) for damages arising from water damage to their property located at 87 Rowe Street in Mel-rose. A judge of the Superior Court denied the plaintiffs’ mo
On August 3, 1992, the plaintiffs commenced this action in the District Court against the hospital for breach of contract and negligence. After summary judgment proceedings in the District Court,
We recite the pertinent facts as stated in the opening. In
During the summer of 1990, the hospital demolished an existing structure at 87 Rowe and had Whitney Construction Company (Whitney Construction) construct a new foundation there for the plaintiffs’ home. As Whitney Construction proceeded to construct the foundation, it began to fill with water, and Whitney Construction used five to six times the normal amount of crushed stone to address the water problem. With the authorization of the hospital, which still owned 87 Rowe and was aware of the water problem, Whitney Construction installed a sump pump.
Plaintiff Henry Hubert inspected the foundation at 87 Rowe and saw water pooling in the foundation. He became concerned and, through counsel, negotiated an agreement which the parties executed on October 25, 1990 (the compensation agreement), which provides in pertinent part:
“The . . . [h]ospital . . . shall compensate . . . [the plaintiffs] for any damage which they incur as a result of water leaking or flooding into the basement of the property located at 87 Rowe ... for a period commencing on October 3, 1990 and ending on October 2, 1992.”
In October, 1990, the parties closed, and the plaintiffs’ house was transported from 62 Rowe Street to 87 Rowe, and the plaintiffs occupied the house.
In June, 1991, the plaintiffs began to experience serious
Commencing in the summer of 1991, the plaintiffs hired several workmen for extensive repair work. A contractor installed a second sump pump in the plaintiffs’ basement, put waterproof cement in several locations in the basement to stem the flow of water into the house, and constructed a total of three dry wells in the front and rear of 87 Rowe, all of which were reasonably necessary to deal with the water problem. The plaintiffs also had a generator installed in their yard to ensure that the sump pumps would continue to operate in the event that there was a power failure in the house. The plaintiffs expended in excess of $28,600 for repairs as a result of the water problem. The flooding, which occurred over a period of approximately two years, not only affected their basement, but also occasionally flooded their front yard to street level as a result of water pumped out of the basement by the sump pumps.
After the plaintiffs’ opening, the judge ruled that the term “damage” in the compensation agreement was unambiguous and that it did not include compensation for consequential damages. He denied the motion to amend the complaint and ordered that judgment be entered dismissing the complaint.
1. Denial of the motion to amend. The plaintiffs claim error in the judge’s denial of their motion for leave to amend their complaint. Broad discretion is vested in the judge in ruling on such motions. Harvard Law Sch. Coalition for Civil Rights v. President & Fellows of Harvard College,
2. Directed verdict on opening statement. When a plaintiff’s opening statement fails to show the existence of a cause of action, the trial judge may properly direct a verdict for the defendant. Wornat Dev. Corp. v. Vakalis,
Whether the judge properly directed a verdict is a question of law. Smith & Zobel, Rules Practice § 50.12 (1977). The judge must take the statements and all rational inferences therefrom in the opening as true, and regard them in the light most favorable to the plaintiff. Singarella v. Boston,
3. The contract count. The judge found that the use of the word “damage” was unambiguous in the compensation agreement. He ruled, relying on dictionary definitions, that it did not encompass consequential damages and directed a verdict
When a written agreement, as applied to the subject matter, “is in any respect uncertain or equivocal in meaning, all the circumstances of the parties leading up to its execution may be shown for the purpose of elucidating but not of contradicting or changing its terms.” Robert Indus., Inc. v. Spence,
It was error to direct a verdict for the defendant on the plaintiff’s opening as there was a genuine issue regarding interpretation of the compensation agreement.
4. The negligence count. In ordering that judgment be entered for the hospital, the judge relied solely on his interpretation of the contract. The complaint, however, contains a second count against the hospital alleging negligent construction of the foundation by the hospital’s agent, Whitney Construction. Ordinarily, the question of negligence is one of fact. Mullins v. Pine Manor,
The order denying the motion to amend the complaint is affirmed. The judgment is reversed, and the case is remanded to the Superior Court for trial.
So ordered.
Notes
The plaintiffs moved for summary judgment. On grounds that there were genuine issues of material fact as to each count of the complaint, the hospital opposed the motion, which was denied.
The judge focused on the word “damage” in the contract between the parties and stated that the pertinent issue was whether that word meant direct damage to 87 Rowe, or whether it meant “damages" in the sense of compensation for consequential expenses. The judge stated:
“Under the circumstances, it appeared to me that it was not necessary to impanel the jury, because after hearing counsel at length and talking about it with them, and examining numerous dictionaries, and whatever case law there might be in Massachusetts on the issue ... 1 have reached the conclusion that the word damage referred to direct injury to the property.”
Neither party objected to the judge’s suggested procedure, which we may best describe as affording the plaintiffs an opportunity to make an offer of proof. The judge indicated that he was treating the statement as an opening, although he stated, “I suppose technically what it is, is a hearing on the Motion for Summary Judgment.” The record does not show, however, that the plaintiffs had renewed their motion for summary judgment in the Superior Court, or that the hospital had moved for summary judgment or a directed verdict. For present purposes, we accept the judge’s characterization and treat his ruling as having directed a verdict on the opening statement. The standard of review for both the granting of a motion for summary judgment and for a directed verdict is the same — whether there was a genuine issue of material fact. Smith & Zobel, Rules Practice § 50.2 (1977).
Although the hospital asserts that the plaintiffs failed to identify an expert witness to establish negligent construction, in their opening the plaintiffs identified, without objection from the hospital, a witness who would testify as to the work done on the foundation to alleviate the flooding problems.
