This is an appeal from summary judgment in favor of Oliver County. We affirm in part, reverse in part, and remand for further proceedings.
This dispute centers on a 1961 contract between Lloyd and Emma Huber and Oliver County. The contract grants a provisional qualified easement across the Hubers’ land to construct a farm-to-market road. The easement allowed the County to build the road entirely on the Hubers’ land rather than building it along the congressional section line. Building the road along the section line would have required crossing Otter Creek numerous times, each time at tremendous expense. By building the road immediately to the east, however, the crossings could be limited to two, one at either end of a small oxbow in the creek. The contract called for the installation of 24-inch squash culverts at each of the two points where the road crosses the oxbow. The County installed the culverts under the road and constructed a concrete diversion structure at the head of the oxbow. The concrete diversion structure was intended to force normal flows to continue along the oxbow, but it also permitted any excess to partially bypass the oxbow in times of extremely high runoff by running along the newly constructed road ditch. The contract also provided that “[i]n the event said culvert proves unsatisfactory for this purpose, then, and in that event, another method shall be examined and installed at the expense” of the County.
In the spring of 1962 the concrete diversion structure installed in 1961 washed out. After the washout, the creek channel changed. Normal flows began to follow the washed-out and deepened road ditch, rather than flowing through the Hubers’ oxbow. In 1963 the Hubers requested that the County repair the structure. In 1966 the County hauled in rock ballast in an attempt to force the stream back into its original channel. Almost immediately that, too, was washed out. Again, in 1978, Mr. Huber appeared before the county commissioners, requesting the reconstruction of the low-head dam to divert the stream back into its original oxbow channel, so that he might irrigate the adjacent land. Huber complained again in 1978 about the County’s inaction. Finally, in response to his complaints, in 1981 the County told Huber they would attempt to remedy the situation. The County attempted several more times to redirect the stream using rock ballast; however, each attempt failed. The County then employed an engineering firm to give estimates for the reconstruction of the original retention structure. The estimate exceeded $98,000. At this point the County refused to fund the construction.
On appeal the Hubers raise three issues. First, they claim that the trial court improperly found that the statute of limitations had expired; second, they claim that the trial court improperly concluded that they were not eligible to receive specific performance under their contract; and third, they claim the trial court improperly denied them an opportunity to appear and orally argue their motions before the court.
I. Hubers’ Statute of Limitations Claim
The trial court ruled that the proper statute of limitations to be applied in this case is NDCC § 28-01-15. 1 Apparently this was due to the fact that the Hubers’ contract with the County was contained in an instrument granting the County an easement across their land. An easement is defined at least in part as “[a]n interest which one person has in the land of another.” Black’s Law Dictionary 509 (6th ed. 1990). Granting *182 another an interest in real property necessarily “affect[s] the title to real property.” NDCC § 28-01-15(2) (1991). Therefore, on the record before us, we cannot say that the trial court erred in applying this statute of limitations.
Based on the trial court’s ruling, the Hubers’ action had to have been “commenced within ten years after the claim for relief ha[d] accrued.” NDCC § 28-01-15. “The application of the statute of limitations is a legal bar to a cause of action. If it is applicable the claim ceases to be a legal obligation and becomes a mere moral one which the law will not lend its aid to enforce.”
Hagen v. Altman,
A plain language reading of the contract in the instant ease contemplates the possibility that the County’s provisions to keep water flowing through the Hubers’ oxbow might, over time, prove inadequate. As noted, the contract provides that if the “culvert proves unsatisfactory^] ..'. another method shall be examined and installed at the expense” of the County. However, the contract fails to establish any time limit within which the County is required to accomplish such an alternative remedy. Where the parties have failed to specify a time for performance, the law will allow a reasonable time. NDCC § 9-07-22 (1987). Determination of what a reasonable time may be is a question of fact, depending upon the particular circumstances of each case.
First Nat’l Bank of Belfield v. Bunch,
The instant case comes to us from a summary judgment.
Summary judgment is appropriate when, after viewing the evidence most favorable to the party against whom summary judgment is sought, there is no genuine issue of material fact in dispute, and the moving party is entitled to judgment as a matter of law. Even if a factual dispute exists, summary judgment is appropriate if its resolution will not alter the result. Such facts are not material.
Berg v. Lien,
The Hubers also claim that because of discussions taking place between them and the County, the statute should have been tolled. This claim is essentially one of equitable estoppel against the County. Tn order to implement an equitable estoppel claim, plaintiff must show that defendant made statements intending that plaintiff would rely on them; that plaintiff did in fact rely on them, and as a result failed to commence an action within the prescribed period; and, finally, that defendant’s statements were made prior to expiration of the appropriate limita
*183
tion period.
2
Burr v. Trinity Medical Ctr.,
II. Denial of Hubers’ Claim for Specific Performance
The Hubers also complain that they were improperly denied specific performance under the contract by the trial court. Specific performance would require the parties to perform their respective contractual promises. 71 Am.Jur.2d.
Specific Performance
§ 211 (1973). The decision to grant the remedy of specific performance rests in the sound discretion of the' trial court; we will not interfere unless we are shown the court’s discretion was abused.
Harrington v. Harrington,
The trial court concluded that Hu-bers have adequate remedies at law for damages. We agree. Hubers have failed to carry their burden of showing why monetary damages are inadequate in the instant case. In fact Mr. Huber, in his supplemental affidavit, has quantified his losses from the lack of irrigation over 17 years as $83,001. This only reinforces the trial court’s conclusion that the Hubers have failed to support their claim for specific performance. We find the trial court did not abuse its discretion.
III. Hubers’ Reliance on the County’s Request for Oral Argument
Hubers claim they were entitled to rely on the County’s request for oral argument to guarantee them an opportunity to be heard on their own and the County’s motions. We disagree.
Rule 3.2 of the North Dakota Rules of Court guarantees oral argument for parties who have timely served and filed their brief and request oral argument.
Anton v. Anton,
Affirmed in part, reversed in part, and remanded for further proceedings consistent with this opinion.
Notes
. 28-01-15. Actions having ten-year limitations. The following actions must be commenced within ten years after the claim for relief has accrued:
[[Image here]]
2. An action upon a contract contained in any conveyance or mortgage of or instrument affecting the title to real properly except a covenant of warranty, an action upon which must be commenced within ten years after the final decision against the title of the covenantor. ...
NDCC § 28-01-15(2) (1991).
. For a more comprehensive discussion of the general elements and theories encompassing equitable estoppel, see
Farmers Co-op. Assoc. of Churchs Ferry v. Cote,
