The appellant, the plaintiff below, filed this suit to compel the defendants-appellees to submit two contract disputes to a single arbitration panel. The district court treated the matter as one of state law. and denied relief. Because federal law controls the outcome of the case we must vacate the judgment and remand to the trial court to determine a difficult threshold eleventh amendment question.
Huber, Hunt & Nichols, Inc. (hereinafter referred to as “Huber, Hunt”), was the general contractor for the construction of the Louisiana State University Medical Center and Education Building in New Orleans. The printed contract identifies the owner as “the State of Louisiana, Division of Administration.” The Division of Administration is an arm of the governor’s office. Architectural Stone Company (hereinafter referred to as “Architectural Stone”) was a subcontractor, supplying and installing granite facing for the building’s exterior. The project fell behind schedule, and, pursuant to the general contract, Huber, Hunt asked the American Arbitration Association (hereinafter referred to as (“AAA”) to arbitrate its claim for damages arising from the delay. 1 Huber, Hunt claimed that the building would have been completed on time if the owner had provided adequate specifications for the foundation. It alleged that the original specifications were the cause of “an inordinately high incidence of breakage of prestress concrete pilings.” Subsequently, Architectural Stone asked the AAA to arbitrate its claim against Huber, Hunt for damages caused by construction delays. 2
In an attempt to have the two arbitration proceedings consolidated, Huber, Hunt brought this diversity action 3 in the United States District Court for the Eastern District of Louisiana. The court heard argument on the motion to consolidate before considering the owner’s motion to dismiss for lack of subject matter jurisdiction. 4 *24 Ruling from the bench, the trial judge denied the motion to consolidate. 5
This appeal followed. Huber, Hunt insists that the district court erred in applying Louisiana law. The appellees, needless to say, defend the district court’s decision pointing to a variety of reasons why consolidation is inappropriate under either federal or state law. The crux of their position is that the owner is the State of Louisiana, and hence the suit is barred by the eleventh amendment to the Constitution.
The action was brought against Architectural Stone “and State of Louisiana.”
6
At first blush it would appear that the eleventh amendment precludes the suit, at least as far as the state is concerned. Recently, however, federal courts have permitted actions against the political subdivisions of states, independent state agencies, and state officials acting in their official capacities, especially in cases asserting claims under the Civil War amendments.
See e. g., Monell v. New York City Dept. of Social Services,
“That there has been room for differences of opinion with regard to such limitations the reported cases in this court bear conclusive testimony. It cannot be stated that the case before us is entirely free from any possible doubt . . . .”
Ex parte Young,
In our Circuit the issue of whether a state is “a necessary party,”
Hopkins v. Clemson Agricultural College,
Where, as here, the status of the defendant is unclear, the court must look to any and all available sources for guidance. Consideration should be given to the own
*25
er’s “right to hold and use property,” whether it has express authority to “sue and be sued, plead and be impleaded, in its corporate name,”
Clemson,
The Division of Administration has been a party to several cases recently decided by the Louisiana courts. In
Haughton Elevator Division v. State, Through the Division of Administration,
This court has previously observed that when there is no “controlling state precedent . . . [w]e give great weight to the view of the State law taken by a district judge experienced in the law of that state . . .”
C.H. Leavell & Co. v. Bd. of Comm’rs of Port of New Orleans,
Without reaching the eleventh amendment question, the district court held that he could not grant the requested relief under Louisiana law.
7
He found “dispositive” Louisiana decisions holding that there can be no consolidation absent express contractual provision therefor. Although state law is usually adopted in diversity cases, it is not followed in an action to enforce the arbitration provision of a contract in interstate commerce. The parties to these contracts are from different states, and if, as appears likely, performance necessarily entailed interstate commerce,
cf. E.C. Ernst, Inc. v. Manhattan Construction Co. of Texas,
The Arbitration Act itself is silent on the subject of consolidation, but some federal courts construed it to permit consolidation, even in the face of contrary state law.
Compania Espanola de Petroleas, S.A. v. Nereus Shipping, S.A., 527
F.2d 966 (2d Cir. 1975),
cert. denied,
If the contract comprised a part of interstate commerce, the district court should not have treated the case as one governed by Louisiana law. 9 If its decision on the eleventh amendment issue does not foreclose further action, 10 the court should determine whether the contract involved interstate commerce and, if so, proceed to the propriety of consolidation under the Arbitration Act. 11
The judgment of the district court is VACATED, and the case is REMANDED for further proceedings consistent with this opinion.
Notes
. The owner refused to arbitrate, so Huber, Hunt went to the Louisiana state courts, which eventually ordered the owner to submit to arbitration.
Huber, Hunt & Nichols, Inc. v. State,
. Huber, Hunt urges that both disputes stem from the owner’s “improper rejection of pilings for the project.” Architectural Stone disagrees. The district court never reached this question.
. The complaint does not clearly state the basis of the court’s jurisdiction, but throughout the proceedings the parties treat this as a diversity case.
. The owner maintained that the state was not a citizen for diversity purposes and that the eleventh amendment barred the suit.
Another matter raised below was the satisfaction vel non of the amount-in-controversy requirement. The plaintiff successfully asserted that the ultimate determination of this controversy might result in payments greatly in excess of $10,000.00. The plaintiffs contention that the eleventh amendment does not apply since it can only be a defense when there is a *24 possibility that a judgment will require the state to expend funds from its treasury, which argument we do not accept, is not entirely consistent with this “ultimate-payment” argument.
. The judge then added “I believe that, necessarily, the motion to dismiss is granted.” The owner suggests this comment reflected the conclusion that the court lacked jurisdiction over the owner, but we decline to so-interpret it. The owner itself notes that the district court chose not to hear argument on the jurisdiction issue.
. The presence of the state as a named defendant is not conclusive of the eleventh amendment question; the federal courts have power to entertain the suit unless the state has an actual and direct interest in the outcome of the litigation.
Cf. Ex parte Nebraska,
. The plaintiff asserted that consolidation could be ordered under both Louisiana and federal law, which may explain the trial court’s failure to consider federal law.
. The general contract provides that it should be “governed by the law of the place where the project is located.” To Architectural Stone, this means Louisiana law applies. We are not so sure that this clause was designed to ensure that Louisiana law would govern the enforce
*26
ment of the arbitration provisions, but even if so the Arbitration Act would be dispositive.
Commonwealth Edison v. Gulf Oil Corp.,
. Huber, Hunt asks that we vacate the judgment in the event we hold for the owner on the eleventh amendment question, so that the judgment would not be res judicata on a consolidation request in the state courts. The owner agrees that the judgment should not constitute a bar to litigation in state court.
. Huber, Hunt suggests that the court could order Architectural Stone to enter a consolidated proceeding even if it lacked jurisdiction over the owner. There are obvious problems with this suggestion, cf. Fed.R.Civ.P. 81(a)(3), 19(b) (indispensable parties), but the issue may never arise, and if it does the district court should address it first.
. It seems that consolidation of related arbitration proceedings would be useful, and, as stated in the text, it has found favor in several federal courts. However, this circuit has never approved the practice, and we should not do so until the matter is ripe for decision, with a record sufficient to determine whether the disputes turn on the same facts, and a district court decision upon which to focus our attention. Consequently, we emphasize that we do not now decide whether the United States Arbitration Act empowers a federal district court to order consolidation of related disputes.
