Two appeals are involved here. Plaintiffs appeal from the portion of the judgment foreclosing the mechanics’ liens of some of their assignors and denying relief for the claim of Hubbard & Carmichael, one of plaintiffs’ assignors. Plaintiffs also appeal from the order of the trial court refusing to strike out the cost bill for costs on a former appeal.
The present plaintiffs are the executors of the original plaintiff, now deceased.
When this ease was originally tried the judgment in .favor of the then plaintiff included the Hubbard & Carmichael lien filed July 2, 1913. The defendants each appealed from the judgment and order denying a new trial. On this appeal the judgment was modified in certain respects, including the disallowance of this particular lien on account of the claim of lien having been filed too late.
(Hubbard
v.
Jurian,
Appellants, in seeking a reversal of the judgment, contend (1) that the finding that Odell and Jurian were estopped from claiming that the work had been abandoned prior to March 10, 1913, by reason of having alleged in their answer that the abandonment occurred on or about that date, should prevail over the finding that the contractor ceased from all labor on the building on March 1, 1913, which it is argued
(2) is not supported by the evidence.
Appellant also urges (3) that Hubbard & Carmichael Bros., having filed a stop notice under section 1184 of the Code of Civil Procedure, were entitled to be paid out of the money in the hands of the owners belonging to the contractor, which was found to be $948; and (4) that a laborer or materialman máy recover from the surety of the contractor without having perfected a lien.
The decision on the former appeal of this case disposes of most, if not all, of the points, and, therefore, is the law of the case with respect to the question decided on that appeal. The doctrine of the decision on the former appeal in this
*545
ease on the fourth point above urged by appellants has been departed from by the supreme court, since the judgment herein was entered on the
remittitur,
in the later case of
General Electric Co.
v.
American Bonding Co.,
But with respect to the other three points on appeal appellants assert that there is no law o‘f the case. First, they point out that in the first decision the word “estoppel” is not used, and that therefore their first point is still open c for decision. We do not agree with this. Although the word “estoppel” is not used as is claimed, yet the decision fully discusses this point, and decides that the defendants’ pleading as a whole is of such a nature that it does not estop them, and that the finding as to the date of abandonment stands. We quote from the decision as follows:
“It is contended upon behalf of the respondent Hubbard that the claim of lien of Hubbard & Carmichael which was filed on July 2, 1913, was within time because it was filed within 120 days from March 10, 1913, ‘on or about’ which date the answer alleged work on the building was abandoned. In this behalf it is urged that this date, by reason of the averments of the answer, was admitted by the defendants to be the date when work ceased upon the building, and that as a consequence the trial court should have accepted that date as the time of cessation of labor despite evidence to the contrary, and that the finding of the trial court that work ceased upon the building on March 1, 1913, was, in so far as the Hubbard & Carmichael claim was concerned, unauthorized, and cannot, therefore, be permitted to prevail over the admitted fact.
“In support of this contention we are cited to the familiar rule that an admission made in the pleading is binding on the party making it; that a fact admitted by the pleadings *546 of an opponent need not be proved; and that any evidence introduced contrary to such admission must be disregarded by the trial court when making its finding. In our opinion this rule has no application to the situation presented by the pleadings in the present case. The burden of proof was upon the plaintiff to show that his assignor, Hubbard & Carmichael, had filed their claim of lien within the statutory time after constructive completion of the building. (Bloom’s Law of Mechanics, Supp., p. 258.) The answer of the defendants squarely and sufficiently denied the allegation of the complaint that the building was completed on June 20, . 1913. This denial made it incumbent upon the plaintiff to proffer proof showing that the claim of lien had been filed within time. Moreover the phrase ‘on or about March 10th,’ as used in the answer, is indefinite and uncertain, and might, therefore, consistently mean several days before or after that date, and, inasmuch as the exact date of the completion of the building or the cessation of work thereon was a material fact to be determined by the court below as a foundation for the allowance or rejection of the claims of lien, it cannot be said that the allegation in question was such a definite admission of fact as would preclude the necessity for the taking of evidence • or the making, a finding thereon.
“The finding of the trial court that work on the building ceased on March 1, 1913, and that such cessation continued for more than a period of thirty days, being • sufficiently supported by evidence, it follows that the Hubbard & Carmichael lien, which was filed July 2, 1913 (123 days after March 1, 1913), was just three days too late, and therefore should not have been allowed.”
It is thus stated in the decision that the finding of the date of cessation of labor is sufficiently supported by the evidence.
Is this amount available to plaintiffs under the stop notice, in face of the fact that there are valid liens greatly .in excess of this sum? The judgment distributes this sum proportionately among the several valid lien claimants, and also gives them judgment against the sureties on the statutory bond filed by defendant Maryland Casualty Company. Therefore, while the amount of $948 was due the contractor under the terms of his contract, in one sense, it is not in another. He will never receive it and is not entitled to it. (Code Civ. Proc., sec. 1193.)
It was said in
Hughes Bros.
v.
Hoover,
Plaintiffs by reason of the stop notice, therefore, were not entitled to judgment against the owner, nor to be paid out of this fund to the exclusion in whole or in part of the valid lien claimants. This disposes of all the points of the appellants on the appeal from the judgment.
The judgment and order appealed from are affirmed.
Waste, P. J., and Richards, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on July 15, 1920.
All the Justices concurred, except Wilbur, J., and Lennon, J., who were absent.
