HUB CONSTRUCTION SPECIALTIES, INC., Plaintiff and Appellant, v. ESPERANZA CHARITIES, INC., Defendant and Respondent.
No. B263398
Second Dist., Div. Eight
Feb. 8, 2016
rehearing denied February 23, 2016
244 Cal. App. 4th 855
GRIMES,
Respondent‘s petition for review by the Supreme Court was denied May 18, 2016, S233188.
COUNSEL
Howard Goodman for Plaintiff and Appellant.
Romero Law and Alan J. Romero for Defendant and Respondent.
OPINION
GRIMES, J.—
SUMMARY
A preliminary written notice to the property owner is a necessary prerequisite to the validity of a mechanic’s lien. The issue in this case is whether a mechanic’s lien is invalid because the plaintiff lienholder did not strictly
Defendant stipulated that the notice was served by certified mail, that the United States Postal Service Web site tracking certified mail items showed the notice was delivered, and that defendant actually received the notice. Despite these stipulations, defendant contends the lien is invalid because plaintiff has no return receipt, and the statute applicable at the time required plaintiff to prove the notice was served by “affidavit . . . accompanied either by the return receipt of certified or registered mail, or by a photocopy of the record of delivery and receipt maintained by the post office, showing the date of delivery and to whom delivered . . . .” (
We reverse the judgment. While strict compliance with the notice provisions of the mechanic’s lien law is required, the applicable precedents do not require or justify applying that rule to the statutory provisions governing proof that the required notice was properly given. A stipulation eliminates the need for proof. Accordingly, where it is stipulated that notice was given in the statutorily prescribed manner, to require further proof would elevate form over substance to a degree that cannot be countenanced in light of the long-established principle that the mechanic’s lien law is “remedial legislation, to be liberally construed for the protection of laborers and materialmen.” (Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 826-827 [132 Cal.Rptr. 477, 553 P.2d 637] (Connolly).)
FACTS
The parties stipulated to the pertinent facts as follows.
Plaintiff Hub Construction Specialties, Inc., supplied rebar and other materials to the general contractor on a construction project on property owned by defendant Esperanza Charities, Inc. The general contractor failed to pay plaintiff $81,857.55 for the materials, a claim plaintiff has determined is uncollectible.
On March 16, 2012, “[plaintiff] caused a ‘California Preliminary Notice’ to be mailed by Certified Mail, to [the general contractor], [defendant], and the project construction lender, . . . as attested to by Proof of Service executed 9/28/12.”
Plaintiff did not request, and did not pay a fee to the United States Postal Service for, a “return receipt” for the notices.
“The U.S. Postal Service website tracks certified mailed items and the tracking for the certified mailed items indicates that they were all delivered. Further, [defendant] has acknowledged in verified discovery responses that it received the preliminary notice which [plaintiff] served. There is no signed return receipt.”
On December 12, 2012, defendant recorded a notice of completion, reciting that the project was completed on December 3, 2012. On December 27, 2012, plaintiff recorded a mechanic’s lien against the property in the claim sum of $81,857.55. On February 6, 2013, plaintiff filed a complaint to foreclose the mechanic’s lien.
The value of the rebar that plaintiff furnished to the project from February 24, 2012 (20 days prior to the preliminary notice), was $53,070.18, and interest through December 1, 2014, amounted to $9,287.25. Plaintiff sought a judgment for foreclosure of the mechanic’s lien, and defendant sought a judgment that the lien was invalid and an order expunging the lien.
The case was initially scheduled for a court trial on the stipulated facts, but the court ordered a modified summary judgment procedure instead (without separate statements, and based on the stipulated facts). After a hearing, the trial court denied plaintiff’s motion for summary judgment and ordered the property released from plaintiff’s lien. The court found plaintiff “cannot provide sufficient proof of service by documentation of the return receipt of certified mail, [or] a photocopy of the record of delivery and receipt maintained by the post office, showing the date of delivery and to whom delivered . . . as required under the statute in effect at the time the effectiveness of the preliminary notice as given is sought to be established.”
Plaintiff filed a timely notice of appeal.
DISCUSSION
Plaintiff contends the absence of a return receipt does not bar enforcement of the mechanic’s lien, because proof of service is unnecessary where service
We conclude from the relevant authorities that, while the principle of strict construction applies to “the manner or form of serving notice upon an affected party” (Harold L. James, Inc. v. Five Points Ranch, Inc. (1984) 158 Cal.App.3d 1, 6 [204 Cal.Rptr. 494] (Harold L. James)), it does not extend to matters of proof in a case where the defendant has admitted that notice was served in the statutorily prescribed manner.
We begin by reciting the statutory provisions in effect when the preliminary notice was served, and then turn to the relevant case authorities.
1. The Statutory Background
Under current law, this case would not be before us. The law that became operative on July 1, 2012—several months after plaintiff served the preliminary 20-day notice, but before execution of plaintiff’s affidavit of service—expanded methods of giving notice and methods of proving that notice was given. Defendant concedes that, under current law, the “certified mailer manifest” proffered by plaintiff “might well have sufficed as a record of ‘payment.’”2 The statutes that were operative until July 1, 2012, however, stated as follows:
Current law states that, notwithstanding its July 1, 2012 operative date, “the effectiveness of a notice given or other action taken on a work of improvement before July 1, 2012, is governed by the applicable law in effect before July 1, 2012, and not by this part.” (
2. Case Authorities
We begin by noting the well-established principle that the mechanic’s lien law is “remedial legislation, to be liberally construed for the protection of laborers and materialmen.” (Connolly, supra, 17 Cal.3d at pp. 826-827.) At the same time, the Legislature “imposed the notice requirements for the concurrently valid purpose of alerting owners and lenders to the fact that the property or funds involved might be subject to claims arising from contracts to which they were not parties and would otherwise have no knowledge.” (Romak Iron Works v. Prudential Ins. Co. (1980) 104 Cal.App.3d 767, 778 [163 Cal.Rptr. 869] (Romak).) The liberal construction rule “may not be applied to frustrate the Legislature’s manifested intent to exact strict compliance with the preliminary notice requirement.” (Ibid.)
Several Court of Appeal cases tell us that strict compliance with the notice requirements of
IGA Aluminum Products, Inc. v. Manufacturers Bank (1982) 130 Cal.App.3d 699 [181 Cal.Rptr. 859] (IGA) is the principal case cited for the proposition that notice requirements are to be strictly construed. In IGA, the question on appeal was “whether the notice requirement of [Civil Code] section 3097 is satisfied by actual written notice delivered by ordinary first class mail, and thus if there were a triable issue of fact raised as to whether such notice was given.” (Id. at p. 702.) The court rejected the premise of the plaintiff’s argument: “that actual written notice, even though not transmitted in strict compliance with the terms of section 3097, satisfies the statutory notice requirement.” (Ibid.) “We conclude that such premise is incorrect as a matter of law,” and so summary judgment was proper. (Ibid.; see id. at pp. 703, 704 [“[o]bviously the substantial compliance doctrine has no application in the present case”; former section 3097 was “unambiguous as to its notice requirement, and therefore there is no room for judicial construction, liberal or otherwise”]; see also Romak, supra, 104 Cal.App.3d at pp. 778, 773 [the plaintiff failed to give preliminary 20-day notice to the defendant construction lender; notice given to owner did not suffice; compliance was not excused by lack of knowledge of the identity of the lender, as the statute allowed plaintiff to mail notice to the jobsite; statute “imposed on [the plaintiff] an absolute obligation (‘must’) to give a preliminary 20-day notice to [the construction lender] ‘as a necessary prerequisite to the validity’ of any stop notice given it later”].)
On the other hand, in Industrial Asphalt, Inc. v. Garrett Corp. (1986) 180 Cal.App.3d 1001 [226 Cal.Rptr. 17] (Industrial Asphalt), the plaintiff served the required preliminary 20-day notice on the defendant owner, but did not serve the required notice on the original contractor (who later declared bankruptcy). (Id. at p. 1005.) The Court of Appeal reversed the trial court’s invalidation of the lien, stating: “To construe the statute strictly would require us to invalidate a lien against an owner who received notice because someone else, the original contractor, did not receive notice. That strict statutory construction would allow a party who received the required notice to be insulated from liability because another party did not receive notice. We do not believe that the statute’s purpose should, or does, lead to this aridly formalistic result. We hold that the plaintiff’s notice to the defendant satisfied the prerequisites for a valid lien against the defendant, and we reverse the trial court’s judgment.” (Id. at p. 1006; see id. at p. 1007 [“where the lien claimant has observed the property owner’s right to notice, he should be allowed to proceed to perfect his lien. We see no reason, in the absence of
Several other cases involve other aspects of
The court in Harold L. James reviewed cases such as IGA and Romak requiring strict compliance, as well as cases finding that other mistakes in lien documents did not preclude enforcement of the lien. (E.g., Wand Corp. v. San Gabriel Valley Lumber Co. (1965) 236 Cal.App.2d 855 [46 Cal.Rptr. 486] (Wand Corp.) [mistake in failing to designate the contractor in the lien document did not preclude enforcement of the lien, where the contractor was correctly designated in the prelien notice, and the document itself was not fraudulent or misleading].)
Harold L. James distilled the following principle reconciling cases requiring strict compliance and cases calling for liberal construction of lien statutes: “The general principles of liberal construction enunciated in Wand Corp. are still good law, subject to this refinement . . . : where the Legislature has provided a detailed and specific mandate as to the manner or form of serving notice upon an affected party that its property interests are at stake, any deviation from the statutory mandate will be viewed with extreme disfavor.” (Harold L. James, supra, 158 Cal.App.3d at p. 6.)
Harold L. James involved
Harold L. James continued: “we need not speculate as to what, if any, deviations from the currently specified statutory lien language might permit a court to determine that such deviations did not render the subsequent lien unenforceable.” (Harold L. James, supra, 158 Cal.App.3d at p. 7.) The court held: “we conclude that the transmittal methods and notice requirements must be strictly construed. However, the issue of minor errors in the body of the notice must be independently addressed on a case-by-case basis, if and when such a case is presented.” (Ibid.; see also San Joaquin Blocklite v. Willden (1986) 184 Cal.App.3d 361, 366, 364-365 [228 Cal.Rptr. 842] [applying the same rule in a public works case; the plaintiff admitted not sending a preliminary 20-day notice, but argued that the defendant’s actual knowledge of the material supplier, plus a notice sent by the state about the materials, either excused compliance or constituted a kind of substantial compliance; “transmittal methods and notice requirements” must be strictly construed].)3
3. This Case
From the stipulated facts and case authorities, several points are clear.
First, the cases demonstrate that the courts do not demand strict compliance with every aspect of the mechanic’s lien law. The cases go no further than to say that “transmittal methods and notice requirements must be strictly construed.” (Harold L. James, supra, 158 Cal.App.3d at p. 7.)
Second, plaintiff in fact served the preliminary notice on defendant in strict compliance with
Third, defendant in fact received the preliminary notice that plaintiff served by certified mail. The stipulated facts tell us not only that defendant actually received the notice (a point that is not determinative), but also that plaintiff actually mailed the preliminary notice by certified mail to defendant (a point that is determinative). And if that were not enough, the stipulated facts also tell us that plaintiff furnished sufficient postage to the United States Postal Service for the certified mail items; that plaintiff has a stamped record from the United States Postal Service (a “Certified Mailer Manifest for: 3-16-12”) “reflecting [the contractor, defendant, and the construction lender] as addressees”; and that the United States Postal Service Web site tracking for the certified mailed items “indicates that they were all delivered.”
In the face of the agreed facts and in the absence of binding authority to the contrary, we decline to find that plaintiff’s lien is unenforceable for lack of a return receipt. We do not disagree with the rule that strict compliance with the notice requirements of
DISPOSITION
The judgment is reversed, and the cause is remanded to the trial court with directions to vacate its order releasing the property from plaintiff’s lien and
Bigelow, P. J., and Rubin, J., concurred.
A petition for a rehearing was denied February 23, 2016, and respondent‘s petition for review by the Supreme Court was denied May 18, 2016, S233188.
