| TAppellant HPD, LLC (HPD) appeals the order entered by the Union County Circuit Court denying its motion to compel arbitration of claims brought against it by appellee TETRA Technologies, Inc. (TETRA). For reversal, HPD contends that the circuit court erred in ruling that threshold issues of arbitrability would be decided by the court, rather than through arbitration. On cross-appeal, TETRA asserts that the circuit court erred by not yet deciding the gateway issues. We reverse and remand for the entry of an order compelling arbitration of all issues. Accordingly, this disposition renders the cross-appeal moot.
As shown by the pleadings in this case, HPD is in the business of designing and selling specialized industrial equipment for use in chemical processing plants, water treatment facilities, and other large-scale industrial settings. TETRA is a producer, marketer, and distributer of chemicals, chiefly calcium chloride. Both are Delaware corporations, but HPD 12has its headquarters in Plainfield, Illinois, while TETRA’s principal place of business is in The Woodlands, Texas. In late 2006, the parties began negotiations regarding TETRA’s plans to construct a chemical processing plant near El Dorado, Arkansas, to produce calcium chloride, sodium chloride, and magnesium oxide from brine. After pilot testing by HPD produced satisfactory results, the parties entered into a “Transparent Execution Engineering & Equipment Supply Agreement” (contract) in November 2007 for HPD to supply equipment to be used in TETRA’s proposed facility in El Dorado. The contract contains a provision for binding arbitration. Construction of the plant began in 2008 and has been completed. TETRA paid HPD in full for its services, a total of $34,540,000.
In March 2011, TETRA filed its initial complaint against HPD in Union County Circuit Court, alleging that the equipment designed by HPD did not perform to expectations. In lieu of filing an answer, HPD moved to dismiss and to compel arbitration in accordance with the arbitration provisions contained in the contract. By its second amended complaint, TETRA asserted causes of action in negligence, gross negligence, professional malpractice, constructive fraud, and breach of fiduciary duty. For these alleged wrongs, it sought both direct and consequential damages. TETRA also sought a declaratory judgment that the contract and the embedded arbitration clause were illegal and thus void because HPD performed engineering services without obtaining a certificate of authorization as allegedly required by Arkansas Code Annotated section 17-30-308 (Supp.2011).
In support of its motion to compel arbitration, HPD asserted that the arbitration clause required arbitration of “[a]ll claims, disputes or other controversies arising out of, or relating |3to, this Agreement.” It also pointed out that the arbitration clause incorporated by reference the Construction Industry Arbitration Rules of the American Arbitration Association (AAA Rules), which grants an arbitrator “the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement” and “the power to determine the existence or validity of a contract of which an arbitration clause forms a part.” Based on the “broad” language of the arbitration clause and the terms of the AAA Rules, HPD argued that all claims and issues, including questions of arbitrability, were to be decided in arbitration.
In resisting arbitration, TETRA maintained that the contract was illegal and unenforceable because HPD had provided engineering services without a certificate of authorization. Citing Sarkco v. Edwards,
Following briefing of the arbitration issue, TETRA filed a motion for partial summary judgment on the declaratory aspect of the amended complaint in which it sought a determination that the contract and arbitration clause were void for illegality. It maintained that there was no dispute as to material fact that HPD provided engineering services without a certificate of authority and argued that, as a matter of law, the contract and the arbitration clause itself, as promotive and auxiliary to an illegal contract, were void. It also urged that HPD lacked the capacity to enter into the contract without a certificate of authority.
On September 27, 2011, the circuit court held a hearing on the motion to compel arbitration. After the parties’ oral presentations, the court took the matter under advisement and subsequently issued an order on November 4, 2011. The circuit court ruled in TETRA’s favor that it would determine the threshold issues of arbitra-bility before deciding whether the case must proceed to arbitration. The court directed HPD to file an answer to the amended complaint and a response to TETRA’s motion for summary judgment. From the circuit court’s order, HPD filed a timely notice of appeal, and TETRA filed a timely notice of cross-appeal.
Before this court, HPD argues that the circuit court erred by not compelling | sarbitration of TETRA’s tort claims and the issues TETRA raised regarding arbi-trability. It contends that the scope of the arbitration clause is expansive to include all claims, disputes, and controversies arising out of or relating to the contract. Citing First Options of Chicago, Inc. v. Kaplan,
An order denying a motion to compel arbitration is an immediately appeal-able order. Ark. RApp. P.-Civil 2(a)(12); Ark.Code Ann. § 16-108-228(1) (Supp. 2011); see IGF Ins. Co. v. Hat Creek P’ship,
The parties in this case agree that the Federal Arbitration Act (FAA) applies to this dispute. Congress enacted the FAA, 9 U.S.C. §§ 1-16, to overcome judicial resistance to arbitration. Buckeye Check Cashing, Inc. v. Cardegna,
Section 2, the “primary substantive provision of the Act,” Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp.,
A written provision in ... a contract evidencing a transaction involving commerce to settle by arbitration a controversy thereafter arising out of such contract ... shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract.
The FAA thereby places arbitration agreements on equal footing with other contracts, and requires courts to enforce them according to their terms. Rent-A-Center, West, Inc. v. Jackson,
In deciding whether to grant a motion to compel arbitration, two threshold questions must be answered. First, is there a valid agreement to arbitrate between the parties? Second, if such an agreement exists, does the dispute fall within its scope? See AT & T Techs., Inc. v. Commc’ns Workers of Am.,
In the present case, the dispute-resolution provision states that “[a]ll claims, disputes or other controversies arising out of, or relating to, this Agreement ... shall be initially submitted to a Senior Officer from each Party for resolution by mutual agreement between said officers.” If that endeavor fails, the arbitration provision states,
Arbitration. To the extent that any Dispute continues to exist after the consultation provided for in Paragraph 12.1 and to the exclusion of any court of law, either Party may refer the Dispute to arbitration, and all Disputes shall be resolved by such arbitration. The arbitration shall be conducted in a non-administered proceeding in Houston, Texas before three arbitrators in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. The award of the arbitrators shall be final and binding and judgment upon the award may be entered in any court of competent jurisdiction. The arbitrators shall have no jurisdiction to hear claims for or authority to award punitive, treble, special, exemplary, incidental, indirect or consequential damages against either Party. The- arbitrators shall not have the authority to modify or amend any term or provision of this Agreement, or make any ruling, finding, or award that does not conform to the terms and conditions of this Agreement. In deciding the dispute, the arbitrators shall apply the substantive law of the State of Texas, which govern this Agreement, without regard to conflict of laws principles of that jurisdiction.
|sThis provision references the AAA Rules of the construction industry, which provide as follows:
R-9 Jurisdiction
(a) The arbitrator shall have the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement.
(b) The arbitrator shall have the power to determine the existence or validity of the contract of which an arbitration clause forms a part. Such an arbitration clause shall be treated as an agreement independent of the other terms of the contract. A decision by the arbitrator that the contract is null and void shall not for that reason alone render invalid the arbitration clause.
Further, Rule R-l(a) states that “[t]he parties shall be deemed to have made these Rules a part of their arbitration agreement whenever they have provided for arbitration by the American Arbitration Association ... under its Construction Industry Arbitration Rules[.]”
In its argument, HPD relies on the decision in Contec Corp. v. Remote Solution Co.,
TETRA, however, argues that the parties did not clearly and unmistakably agree to arbitrate issues of arbitrability even though the AAA Rules were incorporated. It refers to Imthe severability clause to argue that the parties contemplated that questions of enforceability might be decided in a court of law. It further argues that the default provision, allowing resort to all remedies at law or in equity, and the limitation placed on the arbitrators’ authority in the arbitration clause also detract from such clear and unmistakable intent. TETRA suggests that, despite the delegation of authority found in the AAA Rules, the ambiguity created by these provisions diminishes any clear and unmistakable intent for an arbitrator to decide issues of arbitrability.
TETRA’s argument, as it relates to the severability clause, finds some support in appellate decisions from California and Alabama. See Peleg v. Neiman Marcus Grp., Inc.,
In the case at bar, our object is to ascertain the intention of the parties, not from particular words or phrases, but from the entire context of the agreement. See Byrne, Inc. v. Ivy,
Reversed and remanded.
