Howell v. Karl Koch Erecting Corp.Howell v. Karl Koch Erecting Corp.
OPINION OF THE COURT
Defendant and third-party plaintiff Karl Koch Erecting Corp.
Facts:
The following facts are alleged by plaintiff Jeffrey Howell in his May 4, 1999 examination before trial.
At around 1:00 p.m., on February 2, 1996, Howell allegedly slipped and fell on a crane deck and sustained injuries. Howell is licensed in New York City and New York State as a hoisting machine operator. At the time of the incident, he was employed by third-party defendant River Pile. His duties consisted of operating a 35-ton Grove hydraulic crane which was owned and leased from New York Crane. Beginning September 25, 1995, and at the time of the incident, River Pile was working on the Bronx River drawbridge, also known as Hunt’s Point Drawbridge.
At the work site, River Pile was a subcontractor for general contractor Karl Koch. River Pile’s function at the site was to drive caissons at the footings of the bridge for support, i.e., installing a “fender system.” The crane in question was situated atop a barge on the north side of the bridge. From January 15 through 24, 1996, the work at the site was halted due to severe weather. However, all snow and ice was removed from the crane deck each morning and on the morning of the incident. To prevent slipping, paint and skid pads were situated up the center of the crane deck and across the top of its fenders.
The crane deck was situated approximately six feet off the barge deck. It had four “exits” — one from each side and two off the back. The incident occurred on the right front fender which is just in front of steps exiting down the right side of the crane. Howell had never fallen before nor had he known of any other slip and fall incidents.
Before the incident, Howell had climbed up the left side of the crane to enter the cab. After working the crane for a while, Howell exited right from the operator cab door. He proceeded to the left front fender, stepped into the center well and then to the right front fender. Howell was walking to the exit steps situated on the right side of the crane. He proceeded in this direction because the position of the “house” prevented him from exiting off the rear. This was the first time he had walked on the front right fender that day.
As Howell was completing his step to the right fender, he saw red oil on its surface. Although he believed both feet landed
Prior to the incident, Howell made numerous complaints about leaking oil. One such complaint was to the inspector of the work site, Anoop Kesnani, who later put drip pans under the leak. On January 30, 1996, Howell made a specific complaint to Bruce Snyder about oil on the entire deck. He made numerous complaints to Nicky Fiume (general foreman) and Phil Glaser (River Pile superintendent), as well as people in his crew. He also called New York Crane about six times concerning the leak. One such call to Sal Isalo, from New York Crane, was as early as October 13, 1995. Furthermore, on the Monday prior to the incident, Howell told Tom Gatley — the “operating engineer” and “oiler” — to check the oil. Gatley was responsible for all minor maintenance on the crane. Anything other than these minor procedures was done by New York Crane. Gatley informed Howell that he had filled the machine with five gallons of oil.
Howell had authority to shut down the machine if it became too dangerous to operate. He had shut down the crane once before when his “control rack” fell apart. He claims that he had spoken with several people about shutting down the machine due to the oil problem, but never actually did. Howell made a repair request to Bruce Snyder during the week before the incident. Early in the morning on February 2, 1996, he told Phil Glaser to call New York Crane to repair the crane.
Discussion:
Pursuant to CPLR 3212, on a motion for summary judgment, the moving party has the burden of giving sufficient evidence to eliminate any material issues of fact from the case (Winegrad v New York Univ. Med. Ctr.,
The question of whether 12 NYCRR 23-8.1 (b) (1), (2) and (5) are specific enough to uphold a section 241 (6) claim is one of first impression in this Department. In determining this, we must look to the guidelines set forth in Ross v Curtis-Palmer Hydro-Elec. Co. (
However, 12 NYCRR 23-8.1 (b) (1), which requires mandatory monthly inspection of cranes at work sites, is specific enough to raise a triable issue. First, requiring monthly inspection contributes to overall safety of the work site. Second, inspection may prevent numerous crane injuries by revealing crane defects which might be otherwise undetectable. Third, the regulation cites “all blocks, shackles, sheaves, wire rope, connectors, the various devices on the mast or boom, hooks,
The plaintiff also relies on 12 NYCRR 23-1.7 (d), which requires relief from slipping hazards, to supplement his section 241 (6) claim. The Court of Appeals has previously held that 12 NYCRR 23-1.7 (d) mandates a distinct standard of conduct which is sufficient to give rise to a triable claim for damages under section 241 (6) (Rizzuto v Wenger Contr. Co.,
With respect to vehicles, two cases exist which elicit conflicting views on whether 12 NYCRR 23-1.7 (d) may apply in this
Despite their seemingly contradictory holdings, the above cases offer a guide for resolving the present case. First, plaintiff in Bond chose to come off the vehicle by way of its track. In the present case, Howell slipped on a fender of a crane deck on his way to one of its specified exits. While a vehicle’s track is certainly not a “floor, passageway, walkway, scaffold, platform or other elevated working surface,” the path taken on a crane deck to an exit might be. Second, although plaintiff in Cafarella was not exiting his vehicle at the time of his fall, the Court recognized the rear bed of a dump truck as a possible “floor, passageway, walkway, scaffold, platform or other elevated working surface.” In light of Cafarella, the present case, in which plaintiff walked on the crane deck to a designated exit, has some merit.
Plaintiff also testified at his deposition that various tasks, including checking the cooling system and oil as well as releasing the boom’s safety catch, are done at certain positions on the crane deck. Furthermore, the manufacturer placed skid pads over the entire crane deck. Therefore, evidence exists that the entire deck of the crane is used during normal work. In light of the foregoing facts and cases, this court holds that the crane deck on which plaintiff fell does constitute a “floor, passageway, walkway, scaffold, platform or other elevated working surface” within the meaning of 12 NYCRR 23-1.7 (d).
Therefore, defendant’s motion for summary judgment dismissing plaintiffs’ action under Labor Law § 241 (6) is denied.