Cross appeals from a judgment of the Supreme Court, entered June 18, 1979 in Tioga County, upon a decision of the court at a Trial Term, without a jury, which foreclosed a mechanic’s lien on real property. On October 31, 1975 plaintiff contracted to excavate and landscape a race track for defendant Parklaw Realty, Inc. The contract price, which was increased in April, 1976, amounted to $190,000. As the work progressed additional agreements were also allegedly entered into regarding "extra work” done by plaintiff. Plaintiff maintained that the total price for the work done approximated $367,-625 and after receiving a partial payment demanded judgment that it had a valid lien in the sum of $106,808.65. The trial court disallowed certain charges for "extra work” and concluded that plaintiff has a valid lien in the amount of $96,877.65 plus interest. These appeals ensued. Initially, it is argued that there may be no recovery against defendant CIB International in view of the fact that its name was not present on the notice of lien. CIB International appeared at trial by its counsel and this issue was not raised until the present appeal. Consequently, we will not consider the issue since it was not raised before the court of original jurisdiction (see Flanagan v Board of Educ.,