Howard W. Heck, and Associates, Inc. (“Heck”) appeals the judgment of the Court of Federal Claims,
BACKGROUND
In order to expand Heck’s existing residential development in Farmingdale, New Jersey, Heck applied to the Corps for a Clean Water Act (“CWA”) section 404 permit 2 on April 5, 1991, to discharge, dredge, and fill 13 acres of wetlands within Heck’s 24 acre parcel of property. A WQC from the State of New Jersey, or a waiver by the Corps of such, was a statutory prerequisite for the Corps to issue a section 404 permit. See 33 U.S.C. § 1341 (1994); 33 C.F.R. § 325.2(b)(1)(h) (1996).
Heck had submitted a WQC application to the New Jersey Department of Environmental Protection (“NJDEP”) on January 3, 1989. On February 16, 1989, the NJDEP responded by letter to Heck requesting, among other things, submission of a complete discussion of alternatives (an “alternatives analysis”) for the proposed project. 3 Heck responded that
the property could not physically be developed without removal of vegetation, grading and fill for proper drainage purposes. Accordingly, there is no other alternative to the approved residential project, other than to allow the land to remain idle and vacant.
[alternatives are to include both on and off-site considerations. On-site alternatives would include minimizing water quality impact through the minimization of discharge and fill, and/or total avoidance of wetland impact. The consideration of off-site alternatives must also be demonstrated. The Division does not consider ownership of a particular property as reason to reject alternative sites. A complete alternatives analysis must be submitted prior to further review of this application.
Id.
At that point, a disagreement ensued which continued over a three year period between Heck and the NJDEP about the legal basis upon which the NJDEP could require this alternatives analysis. Heck also argued to the NJDEP that because its application had been filed over a year previously, the WQC requirement should be presumed waived. Heck’s argument was based on section 401 of the CWA which presumes waiver for purposes of a federal application when a state does not act upon a WQC application within one year. See 33 U.S.C. § 1341(a)(1). On December 16, 1992, however, having not received an alternatives analysis from Heck in over three years, the NJDEP canceled Heck’s WQC application.
While trying to secure a WQC from the State of New Jersey, Heck proceeded with the section 404 permit process before the Corps. During the process, the Corps requested and Heck provided additional information, and in October 1992, the Corps notified Heck that the application had been sent out for public notice and reminded Heck of its responsibility to obtain state approval and a WQC from the NJDEP. In response to the public notice, the Corps received comments from the Environmental Protection Agency (“EPA”) and the Department of the Interior (“DOI”), both of whom expressed the opinion that Heck’s proposed development would violate the CWA.
In November 1992, Heck argued to the Corps that, because NJDEP had failed to act upon its application within one year, the Corps should deem the requirement of a WQC waived by the State of New Jersey. However, because the NJDEP timely reviewed but ultimately canceled Heck’s WQC
Instead of re-filing a permit application with the Corps, however, Heck filed a Fifth Amendment taking claim in the Court of Federal Claims. The court, in granting the government’s motion to dismiss for lack of jurisdiction, held that Heck’s claim was not ripe for adjudication.
See Heck,
Furthermore, the court stated that it was the wrong forum to address Heck’s challenges under the Administrative Procedure Act to either the NJDEP’s decision requiring the alternatives analysis or to the Corps’ decision not to waive the WQC requirement. See id. at 255. This timely appeal followed.
DISCUSSION
I.
We review
de novo
whether the Court of Federal Claims possessed jurisdiction.
Wheeler v. United States,
II.
A. State Certification Is a Prerequisite For a Final Decision by the Corps and Hence for Judicial Review
The CWA specifically makes submission by the applicant of certification by the state in which the discharge will originate a prerequisite for issuance by the Corps of a section 404 permit. 33 U.S.C. § 1341 (1994). The reason, as the legislative history indicates, is to maintain the particular state’s water quality standard which may be higher than that established federally by the CWA S.Rep. No. 92-414, at 69 (1971),
reprinted in
1972 U.S.C.C.AN. 3668, 3735. Should the state refuse to give its approval, the provisions of 33 C.F.R. § 320.4(j) grant the Corps discretion to deny the permit without prejudice. Here, however, the State of New Jer
Heck, however, argues that the NJDEP’s cancellation of its WQC application constitutes a final decision by the Corps. In order for this argument to succeed, Heck must prove both that (1) the NJDEP made a decision on the merits that denied Heck “economically viable” use of its land, and (2) this state action constitutes a federal taking.
As Heck utterly fails to prove the first requirement, we do not decide the second. The NJDEP canceled Heck’s WQC application solely because Heck refused to submit an alternatives analysis, a fact that is indisputable. The NJDEP issued no final determination directly affecting the property but only canceled the application as incomplete, allowing the opportunity to refile.
Cf. MacDonald,
B. Heck’s Other Arguments Are Without Merit
We have considered Heck’s remaining arguments and find that they lack merit. Heck alleges that the mere requirement of an alternatives analysis makes the application process futile because were Heck to submit an alternatives analysis the WQC surely would be denied. However, the futility exception simply serves “to protect property owners from being required to submit
multiple
applications when the manner in which the first application
was rejected
makes it clear that no project will be approved.”
Southern Pac. Transp. Co. v. City of Los Angeles,
Nor did Heck show undue delay by the State of New Jersey. In fact, the delay of three years was nearly all attributable to Heck itself.
Heck’s “hardship” argument also is without merit because any “hardship” experienced due to lack of a final decision is entirely the fault of Heck itself. Heck could have completed a valid WQC application with the NJDEP, but it unilaterally refused and still has not done so.
To the extent that Heck alleges that the NJDEP violated state law in demanding an alternatives analysis, the appropriate forum would be the New Jersey state courts.
6
For the above reasons, the judgment of the Court of Federal Claims is
AFFIRMED.
Notes
. "[N]or shall private property be taken for public use, without just compensation.” U.S. Const. amend. V, cl. 4.
. Section 404(b)(1) provides that permits shall be granted for discharge into navigable waters (including wetlands) "based upon criteria comparable” to those criteria used for granting permits to dispose of material into territorial seas, the contiguous zone, and the ocean. 33 U.S.C. § 1344(b)(1).
. The Corps may waive the required state WQC if the state has not acted on the WQC application within one year of receiving a valid request for certification. See 33 C.F.R. § 325.2(b)(l)(ii) (1996). Despite Heck’s arguments, the state and not the Corps has the responsibility to determine if it has received a valid request. 51 Fed.Reg. 41,206, 41,211 (1986). According to the NJDEP, Heck never submitted a valid request for a WQC because Heck failed to provide the state with the mandatory alternatives analysis.
. When evaluating a WQC application, the NJDEP incorporates the logic of the CWA alternatives analysis in section 404(b)(1), which is also a requirement when applying to the Corps for a section 404 permit.
. Heck's reliance on
Ciampetti v. United States,
. Heck failed to challenge the construction of the statute by the NJDEP in New Jersey state court, and Heck’s reliance on
New Jersey Chapter of the National Association of Industrial and Office
