¶ 1. December 19, 2007.
¶ 2. The Town sought to drill one or two temporary exploratory wells on a dirt road, known as Reed Road, to ascertain the presence of adequate underground water for use as a public water supply source. Landowners both own property abutting this road. The Town obtained a permit to drill two test wells on Reed Road from the Agency of Natural Resources, but did not commence any condemnation proceeding, or make a finding of necessity and public good related to the site. Landowners filed for declaratory judgment in superior court, seeking only a “preliminary and permanent injunction prohibiting [the Town] from proceeding with the drilling of the test well until proper and formal procedures have been followed.” In their suit, landowners claimed that they owned the land and that the Town could not drill wells without first undergoing a formal condemnation proceeding. The Town disputed that Reed Road was private and asserted the road was a public highway over which the Town had an easement, and further that it could drill a test well without instituting a condemnation action.
¶ 3. Both parties filed for summary judgment. The superior court concluded that because the parties disputed whether the road was public or private and presented conflicting evidence on the issue, the road’s status could not be resolved on summary judgment. Nevertheless, the court concluded that resolution of the road’s ownership was not critical because the Town had statutory authority to drill test wells on private property prior to instituting a formal condemnation proceeding. The court relied on the statutes related to municipal water supply construction, 24 V.S.A. §§ 3301, 3303, and concluded that the statutes authorized the Town to enter upon land without complying with “any procedural steps that must precede such entry.” The court, persuaded by the statute’s language that referred to assessing damages in both the future and past tenses, held that landowners could request compensation after-wards if any damage resulted from the entry. Landowners filed this appeal.
¶ 4. On appeal, landowners argue that the court misinterpreted the statute and that the Town lacked statutory authority to dig the wells without first undergoing a formal condemnation proceeding.
1
At oral argument, all parties agreed that since the case was submitted to this Court, the
¶ 5. In general, a case is moot when “the issues presented are no longer live or the parties lack a legally cognizable interest in the outcome.”
In re Moriarty,
¶ 6. Landowners originally sought injunctive relief to prevent the Town from digging wells without first undergoing a condemnation proceeding. All parties agree that the Town has completed the drilling without any condemnation action. A decision at this stage as to whether the Town had statutory authority to drill the wells without undergoing a condemnation action cannot undo the drilling. As one court explained, “where the activities sought to be enjoined have already occurred, and the appellate courts cannot undo what has already been done, the action is moot, and it must be dismissed.”
Seven Words LLC v. Network Solutions,
¶ 7. Landowner Houston argues that the controversy is still live because the wells are an ongoing taking for which she is entitled to damages. Although landowner admits that damages were not explicitly requested at trial, she suggests that a request for damages was inherent in her original complaint. Landowner’s claim for a damage reward at this stage in the legal process does not create a live controversy that can avoid the mootness of the case. See
Dorian v. Unin of Vt.,
¶ 8. Landowner Damon argues that the Town is committing an ongoing trespass and therefore there is an ongoing controversy. For support, landowner cites
State v. Preseault,
¶ 9. We conclude that this case is distinguishable from Preseault in several ways. First, the party complaining about mootness in Preseault was the one against whom the injunction ran, and the same party that continued to threaten to use the property in violation of the preliminary injunction. In arguing that the action was moot, the defendants sought to relieve themselves of the obligation to comply with an injunction with which they disagreed. Therefore, a permanent injunction was necessary to preserve the status quo and the case could not be considered moot.
¶ 10. In contrast, landowners here wish to avoid mootness to impose an injunction against the other party. Landowners were denied an injunction, the only relief they sought, and now the drilling they sought to prevent has already occurred. Unlike the defendants in Preseault, the Town claims it has no intention of further drilling. It is unnecessary, however, to rely on the Town’s bald assertion to find there is no ongoing controversy; the drilling was a discrete event that is now over and cannot be undone.
¶ 11. Landowner Damon argues, nevertheless, that the case is not moot because the injury is likely to recur and will evade review. This exception to the mootness doctrine applies if “(1) the challenged action was in its duration too short to be fully litigated prior to its cessation or expiration, and (2) there was a reasonable expectation that the same complaining party would be subjected to the same action again.”
In re Vt. State Employees’ Ass’n,
¶ 12. In sum, landowners sought to prevent the Town from digging test wells without undergoing a condemnation action. Because the drilling is complete and cannot be undone, this Court can no longer grant the injunctive relief that landowners originally sought and the case is moot. Whatever other claims landowners may have in the future for damages caused by the wells or for future incursions are not before us in this appeal.
Dismissed.
Notes
Landowners did not raise any constitutional claims in the trial court or on appeal. Landowners’ sole argument on appeal was that the trial court’s holding contravened the plain meaning of the statute.
Landowner Houston has since filed a new action against the Town in superior court for monetary damages related to the drilling.
Before drilling, the Town is required to obtain a permit from the Agency of Natural Resources. Landowners agree that they received notice of this permit process. Therefore, landowners would have adequate advance notice before the Town could engage in any future drilling.
