292 S.W.2d 364 | Tex. App. | 1956
This is an action to recover damages for perosnal injuries brought against the Hous-
However, the compensation carrier for the Barry Construction Company, for which the plaintiff was working at the time “he received his injuries, being the New Amsterdam Casualty Company, duly paid plaintiff or for his behalf the compensation benefits to which he was entitled. Amd said compensation carrier intervened in said suit seeking to recover out of any recovery of plaintiff the amount of the "benefits which it had so paid out, together with attorney’s fees. And the court awarded said intervenor the recovery of the compensation benefits for which, it .•sued, together with $500 attorney’s fees, to be taken out of such sum as plaintiff recovered.
In order to understand the points on which defendant predicates its appeal, it is here necessary to make the following statement: A three hundred foot section ■of defendant’s transmission line, inclusive <of a valve, which lay beneath a highway and railroad crossing near Liverpool, in Brazoria County, had become defective, .and had to be replaced with new pipe and .a valve. The pipe line consisted of 16 inch pipe, and, as indicated, it lay beneath the surface of the highway and railroad crossing and carried live gas to defendant’s customers. In connection with making said ■repairs, it was necessary, among other ithings, for the Houston representatives of defendant to notify its said customers residing in the towns on the other side from Houston from the place where the pipe had to be repaired when the gas and service would be cut, and when it would be restored. It was also necessary to remove the defective pipe from the earth and to replace it with new pipe. This required the use of special tools or equipment, and the service of men skilled in their use.
Among other equipment necessary to be used was a back hoe tractor to dig ditches and a “hellhole” (being the hole necessary to be dug in order to remove the defective pipe, and to install the new pipe). Also, among the tools to be used was a welding rig to cut and weld the pipe, and two large sideboom tractors, weighing 30,000 pounds each to lift and lower the pipe into the hellhole, and other special equipment not necessary to enumerate. The Barry Construction Company owned equipment fitted to removing the defective pipe and employed workers skilled in the use thereof, and said company specialized in doing such work.
At the time defendant learned of the 300 foot defective section in its pipe line, the Barry Construction Company happened to be doing work for the defendant which said company had obtained by competitive bidding. Said work was being done under a written contract, which expressly provided that the work was being done by the Construction Company as an independent contractor. The defendant asked the Construction Company if it cared to do the repair work to the defective section aforesaid, to have a man down at the place where the repairs were needed to be made, and there meet a foreman which defendant would send. At this conference, defendant’s foreman marked on the ground the points between which the defective pipe extended and had to be replaced. The Construction Company then contracted with defendant to do the repair work on a cost-plus basis.
'Defendant predicates this appeál upon eight points. The first four points in effect complain that there was no evidence to justify the submission to the jury of fact issues, and, of course, complain that there was no evidence to support the following findings by the jury, to wit: (1) That the defendant retained the right of control over whether the sides of the hellhole should be sloped, (2) That defendant failed to cause .the sides of the hellhole to be properly sloped, (3) That such failure was a proximate cause of the injuries received by plaintiff in the cave-in, (4) That defendant retained the right of control over whether the hellhole should have been braced or shored, (5) That the failure of defendant to' shore dr brace the sides of the hellhole was negligence, and (6) That such negligence was a proximate causé.
The undisputed evidence showed that a skilled employee of the Construction Company operated the back hoe machine which dug the hellhole. Such employee testified that the hellhole was properly constructed and no one could tell him how to construct such hellhole. The work on the project had been in progress for some four days when, plaintiff, the general superintendent of the Construction ’ Company, came, down to the. job to do the necessary welding. Plaintiff also testified that the hellhole was properly constructed. Indeed, plaintiff’s attorneys admit in their brief that the bell-hole, as it was constructed by the Construction Company’s aforesaid skilled employee, was'.properly constructed. But as we understand' said counsel, it is their position that defendant should nevertheless have foreseen that the large boom tractors would have been moved too close to the hellhole, and so should have sloped the sides. However, plaintiff testified that the cave-in was not due ‘to the manner in which the hellhole was constructed.
We digress here to repeat 'that the contract between defendant and the Construction. Company did not mention or provide for the construction of a hellhole; that the hellhole was a means adopted by the .Construction Company to enable it to lift and remove such pipe and to lower new pipe in its place.
We deem it clear from the undisputed evidence that the manner in which the bell-hole was constructed was at most the condition under which the cave-in happened and was not itself the cause thereof: The plaintiff himself testified that it was ’the movement of the Construction Company’s two sideboom tractors, each weighing 30,-000 pounds, and which the Construction Company used to lift and lower the pipe, which caused the cave-in by moving too close to the side of the hellhole. Said side-boom tractors were part of the equipment used by the Construction Company to perform its obligations under the contract and the same were operated by its employees who were skilled in their operation.
Plaintiff urges that there is evidence that defendant’s foreman wanted the foreman of the Construction Company to have the second sideboom tractor moved down to assist the first sideboom tractor in removing an obstacle. If it be conceded
Plaintiff has conceded that, generally speaking^ the Construction Company (plaintiff’s employer) performed the job as an independent -contractor. Here we inject a definitiqn of “independent contrac-tor” which has been approved and adopted by our Supreme Court, .namely, “‘A contractor is any person who, in the pursuit of an independent business, undertakes to do a specific piece of work for other persons,' using his own means and methods, without submitting himself to their control in respect to all its details.' The true test of- a contractor would seem to be that he renders service in the course of an independent occupation, representing the will of his employer only as to the result of his work, and not as to the means by which it is- accomplished.’ ” Shannon v. Western Indemnity Co., Tex.Com.App., 257 S.W. 522, 524. But plaintiff here contends that his employer was hot operating as an independent contractor relative to the sloping or shoring of the sides of the hellhole. One position taken by plaintiff ’is that the- de-' fendant “retained the right of control over whether the . sides of the-hellhole should have been sloped,” etc. As stated before, there was concededly nothing in the contract relating to any hellhole and .the same was constructed by the Construction Company to serve its own purpose and convenience in removing and replacing pipe; but the contract, as stated before, was let on a cost-plus basis and plaintiff would argue from that fact that defendant had retained authority .to cause and. require the Construction Company to take such sfeps as' would hasten the completion of the job and to refrain from taking ;any steps which might delay the completion of the job. As we understand the evidence, had the sides been sloped or shpred, as plaintiff contends should have been 'done, 'such would have taken some 15 minutes; and plaintiff further argues, if we understand him correctly, that the occasion to do this work on the side of the hellhole arose when the side-boom tractors were moved too close to the ditch.
There is no evidence, in our opinion, to support the jury findings of any retention of the right to control the construction of the hellhole to support any judgment of liability against defendant. This contention of plaintiff, in the final analysis, boils down to a claim that in going onto defendant’s premises and into that portion thereof where the hellhole was dug, plaintiff occupied the status of defendant’s invitee and that defendant as the owner of the premises was under the duty to protect plaintiff against any dangers or perils on the premises of which defendant had a superior • knowledge, or should have ' had' superior knowledge, to thát of plaintiff. That principle of law is not applicable here. ■ The undisputed evidence is 'that the Construction Company went into possession of the premises for the purpose of 'removing defective 'pipe and replacing it with new pipe, and further that the Construction Company, by the use of its own equipment which was operated by its own employees, made all' the alterations which were made on the premises and which 'changed it from the condition' in! which it was when the Construction Company took charge.
What we have said- above requires, that the judgment of the court below be re
The parties have discussed matters which, however interesting, need not be here noticed since judgment has here been rendered for defendant.
Reversed and rendered.