This litigаtion between The Houston Exploration Company (“THEC”) and Halliburton Energy Services, Inc. (“Halliburton”) over the consequences of a THEC gas well blowout is before this court for the second time. The dispute concerns the extent and consequеnces of a work order that absolves Halliburton of liability for its own (ordinary) negligence. In the first appeal, we reversed the district court’s decision that Halliburton was grossly negligent in providing drill testing services to THEC. On remand, the district court again found in favоr of THEC, determining that the work order’s indemnity provision was invalid because THEC’s “company man” did not have actual or apparent authority to bind THEC to its terms. Halliburton again appealed. We reverse and remand.
I. BACKGROUND
This case arises from a 1997 natural gas explosion from THEC’s well located in the Gulf of Mexico. THEC sued Halliburton in federal court, asserting that Halliburton’s failure properly to perform drill stem testing operations led to the blowout. Halliburton argued that the parties’ indemnity provision precluded recovery. The case was tried before the district court in March 2000. The district court held that Halliburton’s conduct was grossly negligent, and thus beyond the scope of the indemnity provision. The court awarded THEC approximately $7,000,000 in dаmages. We reversed that decision and remanded the case for the district court to determine whether the indemnity provision was “executed by an authorized agent of THEC[.]”.
See Houston Exploration Co. v. Halliburton Energy Servs., Inc.,
On remand, the district сourt examined the agency question, as well as THEC’s other challenges to the validity of the indemnity agreement. 1
The relevant facts are largely undisputed. The contract for Halliburton to provide drill testing services to THEC was executed through а work order. The work order stated, in red ink directly above the signature line, that “Customer hereby acknowledges and agrees to the terms and conditions on the reverse side hereof which include, but are not limited to PAYMENT, RELEASE, INDEMNITY, and LIMITED WARRANTY provision.” The reverse *779 side of the work order contained the indemnity provision at issue. 2
Halliburton presented the work order to James Hileman, THEC’s on-site company man and drilling supervisor. Hileman signed the work order in advance of the job, as was the customary practice between the parties. THEC does not dispute that Hileman had authority to sign the work orders to engage Halliburton’s services. THEC asserts instead that he lacked the specific authority to negotiate or execute the indemnity provision on behalf of THEC.
The district court, applying Louisiana law, agreed with THEC and concluded that Hileman lacked “actual authority” because “[n]o evidence was admitted at trial to demonstrate that THEC and Hileman agreed that Hileman could enter into an indemnity agreement with Halliburton on behalf of THEC.” 3 Houston Exploration Co. v. Halliburton Energy Servs., Inc., 2002 WL 1963313, *6 (E.D.La. Aug.22, 2002). The district court further concluded that Hileman lacked “implied actual authority” because “Hileman’s representation of THEC on the rig as a company man does not manifest an intention on the part of THEC for him to have permission to contract with Halliburton for indemnification and release from liability.” Id. Last, the district court found that Hileman lacked “apparent authority” because Halliburton did not reasonably rely on Hile-man’s manifestation of authority. Id. at *7-8. Accordingly, the district court ruled in favor of THEC and reinstated the award. Halliburton appealed.
II. STANDARD OF REVIEW
On appeal from a judgment after a bench trial, we review the findings of fact for clear error and the legal issues de novo.
Gebreyesus v. F.C. Schaffer & Assocs., Inc.,
III. DISCUSSION
Halliburton argues that Hileman had actual authority to enter into the work order agreement, which by implication included the indemnity provision. There is no dispute that Hileman had express authorization to sign the work orders. Express actual authority is crеated by the oral or written agreement between the principal and the agent.
AAA Tire & Export, Inc. v. Big Chief Truck Lines, Inc.,
The question here is one of agency by implication.
See Anderson Window & Patio Co. v. Dumas,
In
Southern States,
the defendant contracted with the plaintiff 43 times over a three-year period to lease property used to install street lights and traffic signals.
Southern States,
The Louisiana court of appeals reached the same result in
Hawthorne.
There, the defendant’s employees contracted with the plaintiff, a waste disposal corporation, tо empty trash dumpsters at various stores.
Hawthorne,
THEC erroneously relies on
Equipment Rental Svcs., Inc. v. Campesi,
In the instant case, THEC approved and paid hundreds of similar work orders without objection. Many of these work orders were signed by company men, including Hileman, who was THEC’s “ultimate authority” for the well in question. In fact, Hileman testified that he continued to sign similar work orders even after the blowout. As in
Southern States
and
Hawthorne,
the repeated approval of work orders manifests the scope Hileman’s authority. Furthermore, Halliburton refused to commence drill testing unless THEC agreed each time to the terms of the work order. Without Hileman’s consent to the indemnity provision, Halliburton would not have performed the service THEC readily admits Hileman was authorized to procure. Thus, Hileman’s consent to the indemnity provision was “reasonably related to the agent’s position” and was “a reasonable and necessary concomitant ] of the agent’s express authori-zationf.]”
AAA Tire,
In the end, THEC management consented to Halliburton’s release and indemnity provision, despite any earlier misgivings.
See Morgan v. Cedar Grove Ice Co.,
*782 IV. CONCLUSION
For the reasons stated above, we REVERSE the district court’s decision that THEC’s agent exceeded his authоrity and REMAND for a determination of Halliburton’s contractual entitlement to attorneys’ fees and for further proceedings consistent herewith.
REVERSED and REMANDED.
Notes
. THEC offered several other theories in addition to the authority argument: (1) there was no consent to the object of the contract; (2) the agreement is vitiated due to error; (3) the agreement impermissibly attempts to renounce the warranty of workmanlike performance; (4) the indemnity agreement is ambiguous; (5) a literal reading of the provision leads to absurd consequences; (6) redhi-bition; (7) breach of contract; and (8) that the indemnity agreement was a contract of adhesion. The district court rejected each of these arguments in open court without elaborаtion.
. The indemnity provision provided that:
CUSTOMER AGREES TO RELEASE HALLIBURTON FROM ANY AND ALL LIABILITY FOR ANY AND ALL DAMAGES WHATSOEVER TO PROPERTY OF ANY KIND OWNED BY, IN THE POSSESSION OF, OR LEASED BY CUSTOMER AND THOSE PERSONS AND ENTITIES CUSTOMER HAS THE ABILITY TO BIND BY CONTRACT. CUSTOMER ALSO AGREES TO DEFEND INDEMNITY AND HOLD HALLIBURTON GROUP HARMLESS FROM AND AGAINST ANY AND ALL LIABILITY, CLAIMS, COSTS, EXPENSES, ATTORNEY FEES AND DAMAGES WHATSOEVER FOR PERSONAL INJURY, ILLNESS, DEATH, PROPERTY DAMAGE AND LOSS RESULTING FROM: ... LOSS OF WELL CONTROL ... CUSTOMER’S RELEASE, INDEMNITY AND HOLD HARMLESS OBLIGATIONS WILL APPLY EVEN IF THE LIABILITY AND CLAIMS ARE CAUSED BY THE SOLE, CONCURRENT, ACTIVE OR PASSIVE NEGLIGENCE, FAULT, OR STRICT LIABILITY OF ONE OR MORE MEMBERS OF THE HALLIBURTON GROUP, IN THE SEAWORTHINESS OF ANY VESSEL, OR ANY DEFECT IN THE DATA, PRODUCTS, SUPPLIES, MATERIALS OR EQUIPMENT FURNISHED BY HALLIBURTON GROUP, WHETHER IN THE DESIGN, MANUFACTURING, MAINTENANCE OR MARKETING THEREOF OR FROM FAILURE TO WARN OF SUCH DEFECT.
. Under the Outer Continental Shelf Lands Act, 43 U.S.C. § 1333(a)(2000), the law of the adjacent state, Louisiana, provides the rule of decision.
. The district court found that "Hileman's representation of THEC on the rig as a company man does not manifest an intentiоn on the part of THEC for him to have permission to contract with Halliburton for indemnification and release from liability.”
. Because we conclude that Hileman had actual authority as a matter of law, we need not reach the aрparent authority question.
. Like the district court, we reject THEC's other assignments of error. The district court did not abuse its discretion in excluding evidence regarding the scope of authority of
*782
Halliburton's employees, as such evidence was immаterial. Furthermore, THEC's remaining arguments are barred from consideration under this court's mandate rule.
See Tollett v. City of Kemah,
