The Housing Authority of Washington, Georgia contracted with MMT Enterprises, Inc. to renovate 96 housing units. After the authority terminated the contract, MMT sued for monies owed and the authority filed a counterclaim for breach of contract. The trial court ordered the authority to deposit in escrow the funds that it retains under the contract pending the project’s completion. The authority appeals that order. Because the trial court abused its discretion in ordering an injunction when the contractor had an adequate remedy at law, we reverse.
1. A trial court may not grant equitable relief if a party has an adequate remedy at law.
1
OCGA § 9-5-6 provides that “[creditors without liens may not, as a general rule, enjoin their debtors from disposing of property nor obtain injunctions or other extraordinary relief in equity.” Here the trial court issued a mandatory interlocutory injunction requiring the authority to pay approximately $70,000, the sum that the authority
2. In the cross-appeals, the contractor and bonding company challenge the denial of summary judgment and motions to compel discovery. We conclude that the trial court did not commit reversible error in denying MMT’s motion for partial summary judgment or American Bonding Company’s motion for summary judgment and did not abuse its discretion in denying MMT’s discovery requests.
Judgment reversed in Case No. S96A1053. Judgment affirmed in Case Nos. S96X1055 and S96X1057.
Notes
Thomas v. Mayor of Savannah,
The contract authorizes the authority to retain ten percent of the progress payments until final completion and acceptance of the project.
See
Patel v. Alpha Investment Properties,
